Summary
Indemnity costs require conduct unreasonable to a high degree or circumstances taking the case outside the norm. An arguable but unsuccessful claim does not ordinarily meet that standard.
Where a costs management order exists, the approved budget is the benchmark for standard assessment. A party seeking an increased budget must apply formally and promptly, before trial, once a material excess becomes apparent. Retrospective revision after judgment is incompatible with costs management.
Departure from an approved budget requires good reason. An unexplained budgeting error, predictable expenditure or overspending caused by non-compliance with court directions will not ordinarily suffice. A genuinely unforeseen and reasonably incurred category of evidence may justify a limited departure.
Treatment over time
Cited in 13 later judgments between 2013 and 2026. Applied, followed or approved 8 times, most recently by the High Court in April 2025.
Most often cited for
- Approved budgets govern assessment unless revised or good reason justifies departure; the receiving party bears a substantial burden
- Indemnity costs require high-degree unreasonableness or circumstances taking the case outside the norm; a weak arguable claim is insufficient
- Approved budgets cannot be revised retrospectively after judgment, and very late revision requires good reason for delay
Factual background
The claimant's substantive claim had been dismissed in an earlier judgment, [2013] EWHC 1191 (TCC), while one element of the defendant's counterclaim succeeded. The claimant accepted liability for the defendant's costs.
The defendant's approved costs budget, as enlarged, was £268,488. It later sought £497,593.66, although it had neither applied before trial to revise the costs management order nor obtained approval for the increase.
The court determined whether costs should be assessed on the indemnity basis, whether an approved budget remained relevant to indemnity costs, whether the defendant could revise its budget after judgment or show good reason to depart from it, and the appropriate interim payment.
Held
Standard-basis costs. The defendant was entitled to its costs, but only on the standard basis. Indemnity costs require conduct unreasonable to a high degree or circumstances taking the case outside the norm. The claimant's case raised numerous arguable issues, included a sound initial allegation of breach and was not pursued disproportionately. Its experts were unpersuasive, but neither unreasonable nor responsible for materially increasing the trial. Refusal of the defendant's inclusive settlement offer did not make the claimant's conduct sufficiently unreasonable.
Indemnity assessment and approved budgets. Although this issue was obiter, an approved budget should remain the starting point even for indemnity assessment. A budget estimates the whole costs likely to be incurred rather than costs calculated for a particular basis of assessment. Treating it as the starting point preserves certainty and discourages routine applications for indemnity costs. An indemnity order may, depending on the facts, constitute good reason for departure.
No retrospective budget revision. A party seeking approval for a significant increase must make a formal application. Merely filing and serving a revised budget is insufficient. The application should be made immediately when a more than minimal excess becomes apparent and must be made before trial. Revision after judgment would cease to be budgeting, encourage parties to wait and see, and destroy the certainty provided by costs management. The defendant could not retrospectively double its approved budget.
Good reason for departure. The same good-reason standard governs approval of a revised budget and departure on assessment. Unidentified or unexplained mistakes in the original estimate do not ordinarily constitute good reason. Nor did predictable work, unchanged pleaded issues, excessive expert involvement or expenditure caused by failure to comply with directions justify departure here. The later need for expert evidence about the costs of implementing the planning permission was genuinely unforeseen and could justify a limited departure.
The defendant remained entitled to argue other alleged departures before the costs judge. Their scope was likely to be limited. The claimant was ordered to pay £250,000 on account of costs within 28 days of the hearing.
The court’s approach to earlier authorities
Available to signed-in members.
Appellate history
- High Court (Technology and Construction Court): In the earlier merits judgment, [2013] EWHC 1191 (TCC) , the claimant's claim was dismissed and one element of the defendant's counterclaim was allowed for £3,500 plus VAT. This subsequent judgment determined the basis and management of the defendant's costs.
Other judgments in these proceedings
2 judgments in these proceedings, earliest first. Linked by the shared court number HT-11-284, and by appeals.
- 24 May 2013Elvanite Full Circle Ltd v AMEC Earth & Environmental (UK) Ltd
- 14 June 2013Elvanite Full Circle Ltd. v Amec Earth & Environmental (UK) Ltd.
Often cited alongside this case
Of these 8 cases: 4 cited with it on 2 different points; 4 cited alongside it for other points.
Cited together forApproved budgets govern assessment unless revised or good reason justifies departure; the receiving party bears a substantial burden
1 related case for signed-in readers
Cited together forIndemnity costs require high-degree unreasonableness or circumstances taking the case outside the norm; a weak arguable claim is insufficient
- Kiam v MGN Ltd (No 2)Cited together in 7 later judgments
+2 more for signed-in readers
Cited alongside it for other points
- Euroption Strategic Fund Ltd v Skandinaviska Enskilda Banken ABIndemnity costs require conduct or circumstances taking the case outside the normCited together in 4 later judgments
- Harrison v University Hospitals Coventry & Warwickshire NHS TrustDeparture from an approved or agreed costs budget requires good reason, applied rigorouslyCited together in 3 later judgments
+2 more for signed-in readers
5 more related cases for signed-in readers. A free account is enough.
Key cases cited
6 authorities cited.
- Henry v News Group Newspapers Ltd [2013] EWCA Civ 19
- Excelsior Commercial & Industrial Holdings Limited v Salisbury Hammer Aspden & Johnson (a firm) [2002] EWCA Civ 879
- Kiam v MGN Ltd (No 2) [2002] EWCA Civ 66
- Murray & Anor v Neil Dowlman Architecture Ltd [2013] EWHC 872 (TCC)
- Euroption Strategic Fund Ltd v Skandinaviska Enskilda Banken AB [2012] EWHC 749 (Comm)
- Digicel (St. Lucia) Ltd & Ors v Cable & Wireless Plc & Ors [2010] EWHC 888 (Ch)
Sign in to see how the court treated each authority. A free account is enough.
Cases citing this case
13 later cases · 8 positive · 3 neutral · 2 caution
Most senior citing decisions:
- Car-Wizard Ltd v Vixen Surface Treatments Limited [2026] EWHC 2177 (Ch) distinguished
- Thomas Barry & Anor v Denis Barry [2025] EWHC 819 (KB) applied
- Hope Capital Limited & Anor v Alexander Reece Thomson LLP [2023] EWHC 3157 (KB) followed
- RESOURCE RECOVERY SOLUTIONS (DERBYSHIRE) LIMITED v DERBYSHIRE COUNTY COUNCIL & Anor. [2022] EWHC 1209 (TCC)
- Ramsden v Revenue And Customs (Costs) [2020] EWHC 357 (QB)
- Hochtief (UK) Construction Ltd & Anor v Atkins Ltd [2019] EWHC 3028 (TCC)
- Burgess & Anor v Lejonvarn [2019] EWHC 369 (TCC)
- Sharp v Blank & Ors [2017] EWHC 3390 (Ch)
- Bank of Ireland (Governors and Company of) & Anor v Watts Group Plc [2017] EWHC 2472 (TCC)
- Merrix v Heart of England NHS Foundation Trust [2017] EWHC 346 (QB)
Sign in for the full treatment table, including the other 3 cases. A free account is enough.