Summary
A party seeking fortification of a cross-undertaking in damages need not prove loss on the balance of probabilities. It must show a good arguable case by providing an intelligent and realistic estimate of likely loss, a sufficient risk that loss will occur, and a causal link between the interim order and that loss.
The court should not conduct a mini-trial of disputed causation at the interlocutory stage. Where a freezing order prevents a commercial party using money that would otherwise have been paid to it, the ordinary measure of the loss of use is interest at the usual cost of borrowing an equivalent sum. Actual borrowing or a present need to borrow need not be proved.
Treatment over time
Cited in 21 later judgments between 2015 and 2026. Applied, followed or approved 18 times, most recently by the High Court in July 2026. 1 negative treatment, by the Court of Appeal in 2025.
Most often cited for
- Fortification requires an intelligent loss estimate, sufficient risk and a good arguable causal connection
Factual background
The appellant, Energy Venture Partners Ltd, had obtained a worldwide freezing order against Malabu Oil and Gas Ltd. US$215 million that would otherwise have been paid to Malabu was paid into court. The order was supported by a cross-undertaking in damages.
Hamblen J ordered further fortification of that undertaking, assessed by reference to the US Prime Rate: [2012] EWHC 79 (Comm). The appellant appealed, challenging the legal test for fortification, the entitlement to fortification, and the rate used to assess it.
The appeal had largely become academic after the substantive action concluded, but retained possible costs consequences. The central issue was the proper interlocutory test for requiring security for a cross-undertaking in damages.
Held
The appeal was dismissed. The court upheld the order requiring fortification of the cross-undertaking in damages.
The correct test does not require the applicant to establish loss on the balance of probabilities. The court must make an intelligent estimate of likely loss caused by the interim order, decide whether there is a sufficient risk of that loss, and be satisfied that the loss has been, or is likely to be, caused by the injunction. These requirements are linked. In this interlocutory context, a sufficient risk is synonymous with a good arguable case for fortification.
Causation requires a cause without which the loss would not have been suffered. If a good arguable causal case is shown, the respondent may disprove it. The court should not, however, resolve it through extensive contentious evidence and argument at an interlocutory hearing. That would produce wasteful satellite litigation.
Malabu had a good arguable case that, but for the freezing order, it would have received and been able to use the US$215 million. It did not need to prove that it actually would borrow replacement funds. Nor did a possible obligation to transfer the money to others defeat its prima facie claim. The ordinary compensation for loss of use of money was interest based on the usual cost of borrowing an equivalent sum.
For commercial parties, borrowing cost is ordinarily the relevant measure. A deposit return may be appropriate in another case, but it could not improve the appellant’s position here because the available deposit rate was higher than the borrowing rate used by Hamblen J.
The court also dismissed the appellant’s late applications to adduce fresh evidence and adjourn the appeal. The delay was unjustified, and admission would have required further proceedings to permit a response. Costs were apportioned by reference to the parties’ October 2013 agreement and the later conduct of the appeal.
The court’s approach to earlier authorities
Available to signed-in members.
Appellate history
- Court of Appeal (Civil Division) dismissed the appeal and upheld the fortification order: [2014] EWCA Civ 1295 .
- High Court, Commercial Court (Field J) dismissed an application under CPR 3.1(7) to revoke the fortification order: [2012] EWHC 2215 Comm.
- High Court, Commercial Court (Hamblen J) ordered further fortification of the cross-undertaking in damages: [2012] EWHC 79 (Comm).
Appeal route
- Appealed fromUnknown case[2012] EWHC 79 (Comm) EWHCUpheldAppeal dismissed (applications to adduce fresh evidence and adjourn the appeal dismissed)
- This judgment · 9 October 2014 [2014] EWCA Civ 1295 Court of Appeal (Civil Division)
Related cases
Not part of these proceedings, but heard together with this judgment or between the same parties.
Often cited alongside this case
Of these 8 cases: 4 cited with it on the same point; 3 cited alongside it for other points; 1 related in other ways.
Cited together forFortification requires an intelligent loss estimate, sufficient risk and a good arguable causal connection
- Jirehouse Capital & Anor v Beller & AnorCited together in 5 later judgments
- Phoenix Group Foundation & Ors v Cochrane & OrsCited together in 5 later judgments
+2 more for signed-in readers
Cited alongside it for other points
- Bloomsbury International Ltd & Ors v Holyoake & OrsFreezing-order loss requires realistic assessment of risk and causation on available evidenceCited together in 6 later judgments
+2 more for signed-in readers
Other related cases
1 related case for signed-in readers
5 more related cases for signed-in readers. A free account is enough.
Key cases cited
6 authorities cited.
- Tibbles v SIG Plc (t/a Asphaltic Roofing Supplies) [2012] EWCA Civ 518
- Bloomsbury International Ltd & Ors v Holyoake & Ors [2010] EWHC 1150 (Ch)
- Jirehouse Capital & Anor v Beller & Anor [2008] EWHC 725 (Ch)
- Harley Street Capital v Tchigirinski [2005] EWHC 2471 (Ch)
- Sinclair Investment Holdings SA v Cushnie & Ors [2004] EWHC 218 (Ch)
- Air Express v Ansett Transport Industries [1981] 146 CLR 249
Sign in to see how the court treated each authority. A free account is enough.
Cases citing this case
21 later cases · 18 positive · 1 neutral · 1 caution · 1 negative
Most senior citing decisions:
- Yodel Delivery Network Limited v Jacob Corlett & Ors [2025] EWCA Civ 1108 not applied
- The Claimants Listed in Schedule 1 to the Claim Form v Nicholas Spence & Ors. [2022] EWCA Civ 500 applied
- Schettini v Silvestri & Ors [2019] EWCA Civ 349 mentioned
- SCF Tankers Ltd & Ors v Privalov & Ors [2017] EWCA Civ 1877
- JAC Mezhdunarodniy Promyshlenniy Bank & Anor v Pugachev [2015] EWCA Civ 139
- Ciright Inc v Centili Group Limited [2026] EWHC 1865 (Ch)
- Fitrite Fencing and Decking Limited v John Ross & Anor [2026] EWHC 708 (Ch)
- Mex Group Worldwide Limited v Stewart Owen Ford & Ors [2025] EWHC 2689 (KB)
- LAX SA v JBC SA [2024] EWHC 2042 (Comm)
- Omni Bridgeway (Fund 5) Cayman Invt Limited v Bugsby Property LLC & Anor [2023] EWHC 2755 (Comm)
Sign in for the full treatment table, including the other 11 cases. A free account is enough.