RWE Npower Renewables Ltd v J N Bentley Ltd

[2014] EWCA Civ 150

Cited by 7 later cases6 positive1 negative

Summary

Complex contract documents forming one agreement should, so far as possible, be read as complementary and coherently. A contractual order of precedence is engaged only by a clear and irreconcilable inconsistency.

Where competing provisions describe a bundle of obligations, any conflict should be resolved at the level of the obligation concerning the same subject matter, rather than by discarding an entire clause. The scope of sectional completion may be informed by the agreement as a whole, including key dates, programmes and the language used for other sections. A liquidated damages regime may assist, but negotiated figures whose basis is unclear carry limited interpretative weight.

Treatment over time

Cited in 7 later judgments between 2015 and 2025. Applied, followed or approved 6 times, most recently by the Court of Appeal in March 2025. 1 negative treatment, by the High Court in 2016.

Most often cited for

  1. Contract documents should be read together, with precedence used only for irreconcilable discrepancies7 judgments

Factual background

RWE sought declaratory relief under Part 8 concerning the date and scope of Bentley’s obligation to complete section 2 of civil engineering works for a hydro-electricity generating plant. The dispute concerned the relationship between Option X5 in Part 1 of the Contract Data and clause 6.2 of the Works Information.

An adjudicator held that Option X5 took precedence and that section 2 had been completed on 21 February 2012. Akenhead J held that the contract should be read as a whole, that the provisions were substantially consistent, and that the penstock pipeline had to be completed by 27 May 2011. The appeal concerned the proper construction of those contractual provisions and the extent of the precedence clause.

Held

The Court of Appeal unanimously dismissed Bentley’s appeal.

  1. The contract documents were to be read, so far as possible, as complementary and as expressing the parties’ intentions consistently and coherently. The contractual order of precedence was relevant only if there was a clear and irreconcilable discrepancy.
  2. Option X5 and clause 6.2 could be read together. Both referred to completion and testing of the penstock pipeline. The references to installation, testing and commissioning of the hydro plant did not create an inconsistency because that work belonged to Andritz, not Bentley. Section 2 therefore comprised substantially all Bentley’s work other than section 1, and Bentley was obliged to complete the pipelines by 27 May 2011.
  3. If a genuine discrepancy existed, precedence was to be determined by reference to individual obligations concerning the same subject matter. An inconsistency in one respect did not require the abandonment of an entire complex contractual provision. The pipeline requirement could not be extracted and treated as a free-standing obligation separate from the obligation to complete the prescribed work for section 2.
  4. The liquidated damages provisions provided limited assistance. Although the figures had been negotiated, the material did not disclose the basis on which they had been calculated. Their principal significance was that they were intended to compensate RWE for losses caused by delay affecting the following contractor.
  5. Even construing Option X5 without clause 6.2, the key dates for completion of the intake and testing of the pipelines, the contractual programmes, and the contrast between the wording of sections 1 and 2 showed that the parties contemplated completion and testing of the whole pipelines before installation of the hydro plant. Section 2 was therefore not complete until the whole penstock pipeline had been completed and tested.

The court’s approach to earlier authorities

Available to signed-in members.

Appellate history

  • Court of Appeal (Civil Division): In [2014] EWCA Civ 150 , the appeal was dismissed.
  • High Court of Justice, Technology and Construction Court: Akenhead J gave judgment for RWE on its claim for declaratory relief in [2013] EWHC (TCC).
  • Adjudication: The adjudicator held that Option X5 took precedence and that section 2 had been completed on 21 February 2012.

Appeal route

  1. Appealed from[2013] EWHC (TCC)This appealappeal dismissed (unanimous)
  2. This judgment · 19 February 2014 [2014] EWCA Civ 150 Court of Appeal (Civil Division)

Other judgments in these proceedings

2 judgments in these proceedings, earliest first. Linked by appeals and by the court numbers the judgments share.

  1. 22 April 2013RWE Npower Renewables Ltd v J N Bentley Ltd[2013] EWHC 978 (TCC) · High Court (Technology and Construction Court)
  2. 19 February 2014RWE Npower Renewables Ltd v J N Bentley Ltd[2014] EWCA Civ 150 · Court of Appeal (Civil Division) · this judgment

Often cited alongside this case

Of these 3 cases: 3 cited alongside it for other points.

Cited alongside it for other points

  1. Rainy Sky S. A. and others v Kookmin Bank[2011] UKSC 50 · United Kingdom Supreme CourtContractual construction is a unitary contextual exercise, favouring business common sense where wording permitsCited together in 3 later judgments
  2. Arnold v Britton and others[2015] UKSC 36 · United Kingdom Supreme CourtContractual meaning is determined objectively from language, context, purpose and commercial common senseCited together in 3 later judgments
  3. Investors Compensation Scheme Ltd v West Bromwich Building Society (Investors Compensation Scheme Ltd v Hopkins & Sons)[1997] UKHL 28 · House of LordsContractual meaning is what a reasonable person with the parties’ available background knowledge would understandCited together in 3 later judgments

Key cases cited

Available to signed-in members.

Cases citing this case

7 later cases · 6 positive · 1 negative

Most senior citing decisions:

Sign in for the full treatment table. A free account is enough.