CIP Properties (AIPT) Ltd v Galliford Try Infrastructure Ltd (Costs NO. 2)

[2015] EWHC 481 (TCC)

Summary

In costs management, the court must take incurred costs into account when fixing future costs so that the overall recoverable costs remain reasonable and proportionate. Where a party’s budget is unreliable and its incurred costs are excessive, the court may make a tailored costs management order. It may cap recoverable incurred costs on assessment, approve reduced future phase costs, and require a pound-for-pound reduction of those future costs if the assessed incurred costs exceed the stated cap.

Proportionality requires attention to the statutory factors, particularly the complexity and value of the litigation. A substantial monetary claim does not by itself justify costs which are disproportionate to the work required to litigate it.

Treatment over time

Cited in 16 later judgments between 2015 and 2026. Applied, followed or approved 11 times, most recently by the High Court in July 2024. 1 negative treatment, by the High Court in 2019.

Most often cited for

  1. Courts may manage incurred and future costs together to control overall recoverable costs9 judgments
  2. Costs budgeting requires structured consideration of proportionality, reasonableness and available options6 judgments

Factual background

The claimant brought a construction-defects claim against the contractor concerning a Birmingham development. The contractor had commenced related claims against specialist subcontractors and the architects.

At a costs-management hearing, the claimant’s asserted incurred and future costs exceeded £8.9 million. The other parties contended that its budget was unreliable, disproportionate and unreasonable. The court considered whether to require a new budget, decline to approve it, fix future figures only, or allow no further costs beyond those incurred.

The central issue was how to make a just and workable costs management order where the claimant’s stated incurred costs already approached the proportionate cost of the case as a whole.

Held

  1. A modified costs management order was made. The claimant’s budget was unreliable. Its large and unexplained increases in incurred and estimated costs, extensive assumptions and contingencies, and later corrections showed that it had not provided a dependable basis for ordinary costs management.

  2. The claimant’s total asserted costs were disproportionate and unreasonable. Applying the factors in CPR r 44.3(5), the court held that this was a relatively standard defects claim in which expert evidence, rather than extensive factual material, would be decisive. Complexity was more significant than the claimed value. The claimant’s costs were more than twice the defendant’s, although the defendant bore the additional burden of defending the claim and pursuing the additional parties.

  3. The court rejected an order for a new budget because it would generate further cost without a realistic prospect of reliable information. It also rejected declining to approve the budget, since that would leave the disputes unresolved. A nil prospective budget was potentially unfair because the claimant’s incurred costs could later be reduced on assessment without any corresponding allowance for future work.

  4. The court therefore set recoverability figures for incurred phases and approved future phase figures. If the claimant recovered more than the stated incurred-cost cap on assessment for pre-action costs, statements of case, CMCs, disclosure, or experts, its approved future costs would reduce pound for pound. The resulting total recoverable cost allowance was £4.28 million.

  5. The defendant’s budget was reduced to £4,226,446.41. The additional parties’ budgets were approved in full.

The court’s approach to earlier authorities

Available to signed-in members.

Appellate history

High Court (TCC): This second costs judgment followed a CMC in the same proceedings. At that CMC, the court rejected the claimant’s argument that the value of the claim prevented any costs management order: [2014] EWHC 3546 (TCC) .

Other judgments in these proceedings

3 judgments in these proceedings, earliest first. Linked by the shared court number HT-13-390, and by appeals.

  1. 29 October 2014CIP Properties (AIPT) Ltd v Galliford Try Infrastructure Ltd & Ors[2014] EWHC 3546 (TCC) · High Court (Technology and Construction Court)
  2. 5 March 2015CIP Properties (AIPT) Ltd v Galliford Try Infrastructure Ltd (Costs NO. 2)[2015] EWHC 481 (TCC) · High Court (Technology and Construction Court) · this judgment
  3. 21 May 2015CIP Properties (AIPT) Ltd v Galliford Try Infrastructure Ltd & Ors[2015] EWHC 1345 (TCC) · High Court (Technology and Construction Court)

Often cited alongside this case

Of these 3 cases: 2 cited with it on 2 different points; 1 cited alongside it for another point.

Cited together forCourts may manage incurred and future costs together to control overall recoverable costs

  1. Kazakhstan Kagazy Plc & Ors v Zhunus & Ors[2015] EWHC 404 (Comm) · High Court (Commercial Court)Also cited together for: Costs budgeting requires structured consideration of proportionality, reasonableness and available optionsCited together in 4 later judgments

Cited together forCosts budgeting requires structured consideration of proportionality, reasonableness and available options

  1. GSK Project Management Ltd v QPR Holdings Ltd[2015] EWHC 2274 (TCC) · High Court (Technology and Construction Court)Cited together in 4 later judgments

Cited alongside it for other points

  1. Yeo v Times Newspapers Ltd[2015] EWHC 209 (QB) · High Court (Queen's Bench Division)Costs budgets assess whether phase totals fall within a reasonable and proportionate range, not by detailed advance assessmentCited together in 4 later judgments

Key cases cited

4 authorities cited.

Sign in to see how the court treated each authority. A free account is enough.

Cases citing this case

16 later cases · 11 positive · 2 neutral · 2 caution · 1 negative

Most senior citing decisions:

Sign in for the full treatment table, including the other 6 cases. A free account is enough.