| Date | Case | Cited by |
|---|---|---|
| 21 Dec 2015 |
[2015] EWHC 3737 (TCC)
In adjudication enforcement proceedings, a misdescription of the contractual route does not deprive an adjudicator of jurisdiction where every realistically…
|
2 |
| 18 Dec 2015 |
[2015] EWHC 3898 (TCC)
On an application to lift an automatic suspension under the Public Contracts Regulations 2015, the court applies the ordinary interim-relief approach. The…
|
7 |
| 18 Dec 2015 |
[2015] EWHC 3650 (TCC)
A contract for supplying and installing substantial machinery is a construction contract only if the installation involves construction operations within the…
|
1 |
| 10 Dec 2015 |
[2015] EWHC 3606 (TCC)
Disclosure cannot be ordered against a defendant who credibly states that the documents are not in his possession, custody or control unless there is material…
|
|
| 7 Dec 2015 |
[2015] EWHC 3573 (TCC)
Contractual exclusion and limitation clauses are construed by applying the ordinary principles of contractual interpretation. The court must identify what a…
|
|
| 1 Dec 2015 |
[2015] EWHC 3479 (TCC)
Specific disclosure must be confined to documents relevant to the issues and sought in a proportionate manner. The court may make a targeted disclosure order…
|
|
| 1 Dec 2015 |
[2015] EWHC 3455 (TCC)
Expert evidence in professional-negligence proceedings is not automatically required. The court must consider the pleaded issues and ask whether expert…
|
|
| 30 Nov 2015 |
[2015] EWHC 3385 (TCC)
A Part 36 offer made by a defendant with a counterclaim is classified by construing the offer as a whole. The existence of a counterclaim does not…
|
2 |
| 24 Nov 2015 |
[2015] EWHC 3352 (TCC)
In a hybrid construction contract, the Housing Grants (Construction and Regeneration) Act 1996 applies only to the construction operations within its scope.…
|
3 |
| 20 Nov 2015 |
[2015] EWHC 3360 (TCC)
A binding settlement may arise from an exchange of emails where the parties’ words and conduct objectively demonstrate an intention to create legal relations…
|
|
| 17 Nov 2015 |
[2015] EWHC 3320 (TCC)
Where a Part 8 claim produces mixed results on several issues, costs should reflect the parties’ relative success and the proportion of time and preparation…
|
|
| 16 Nov 2015 |
[2015] EWHC 3244 (TCC)
On a summary judgment application, the court may decide a short point of law or construction where the evidence is sufficient and the parties have had a proper…
|
|
| 13 Nov 2015 |
[2015] EWHC 2887 (TCC)
For jurisdiction purposes, a contribution claim is characterised by its substance. A claim between parties with no relevant contract is ordinarily a matter…
|
|
| 12 Nov 2015 |
[2015] EWHC 3074 (TCC)
A contractor seeking additional payment for unforeseen ground conditions must satisfy every contractual condition, including timely notice, materially…
|
|
| 2 Nov 2015 |
[2015] EWHC 3167 (TCC)
Applications to transfer proceedings into the Technology and Construction Court must be determined by weighing the matters identified in CPR 30.3(2). For…
|
|
| 30 Oct 2015 |
[2015] EWHC 3067 (TCC)
An adjudicator asked to determine the true value of variations may compare that value with sums already certified and paid, where the referral seeks such other…
|
|
| 30 Oct 2015 |
[2015] EWHC 3063 (TCC)
Where a party is entitled to apply to strike out a claim for failure to serve Particulars of Claim on time, the costs of that application may be awarded even…
|
|
| 29 Oct 2015 |
[2015] EWHC 3050 (TCC)
Where security for costs has been provided through an agreed after-the-event insurance policy and incorporated into a court order, the court should not vary…
|
|
| 28 Oct 2015 |
[2015] EWHC 3091 (TCC)
Costs on opposed amendment applications are not determined solely by identifying which party obtained permission. The court must consider the parties’ conduct…
|
|
| 23 Oct 2015 |
[2015] EWHC 2915 (TCC)
A contractual adjudication procedure must be construed so that amendments are given practical effect. Where an amendment would otherwise be pointless, the…
|
|
| 21 Oct 2015 |
[2015] EWHC 3051 (TCC)
An open offer is a package of terms. A party cannot treat part of it as an admission while rejecting the remainder. For judgment under Civil Procedure Rules…
|
|
| 21 Oct 2015 |
[2015] EWHC 2954 (TCC)
Applications to amend pleadings are assessed by reference to the overriding objective and proportionality. Lateness is relative. An amendment is particularly…
|
|
| 21 Oct 2015 |
[2015] EWHC 2889 (TCC)
A party may participate in an adjudication while reserving its right to challenge the adjudicator’s jurisdiction at enforcement. Agreement to the adjudicator’s…
|
1 |
| 16 Oct 2015 |
[2015] EWHC 2923 (TCC)
A professional client may defend a claim for fees by showing that a discrete professional service was not performed, or was so poorly performed that it was…
|
2 |
| 16 Oct 2015 |
[2015] EWHC 2900 (TCC)
An incentive fee agreement payable on a no win, no fee basis may entitle an agent to a percentage of the saving achieved against the original accepted price…
|
|
| 16 Oct 2015 |
[2015] EWHC 2858 (TCC)
A contractual time bar preventing proceedings by a beneficiary does not, without clear words, extinguish the beneficiary’s underlying right. It therefore does…
|
1 |
| 15 Oct 2015 |
[2015] EWHC 18 (TCC)
Fixed recoverable costs may apply to a low-value road-traffic personal injury claim which began under the RTA Protocol, left the Protocol and Stage 3…
|
|
| 2 Oct 2015 |
[2015] EWHC 2372 (TCC)
A project monitor must exercise reasonable skill and care in checking drawdown applications, reporting material cost increases, and ensuring that lending is…
|
|
| 28 Sep 2015 |
[2015] EWHC 2694 (TCC)
On an application to end an automatic suspension under the Public Contracts Regulations 2006, the court applies the ordinary American Cyanamid principles on…
|
14 |
| 16 Sep 2015 |
[2015] EWHC 2624 (TCC)
For summary judgment enforcing an adjudicator’s decision, the court asks whether the defendant has no real prospect of successfully defending the claim and…
|
4 |
| 14 Aug 2015 |
[2015] EWHC 2433 (TCC)
An interim application under a construction contract must be clear, unambiguous and identifiable in substance, form and intent as an application for a…
|
4 |
| 7 Aug 2015 |
[2015] EWHC 2384 (TCC)
Applications for relief from sanctions must be assessed using the three-stage approach in Denton v White: the seriousness and significance of the breach…
|
|
| 31 Jul 2015 |
[2015] EWHC 2692 (TCC)
An adjudication concerning valuation, termination and payment may constitute a single dispute where the issues are financially and factually linked. A party…
|
|
| 30 Jul 2015 |
[2015] EWHC 2128 (TCC)
In a dilapidations claim, damages for breach of a repairing covenant are capped by the diminution in the value of the reversion where Landlord and Tenant Act…
|
|
| 29 Jul 2015 |
[2015] EWHC 2274 (TCC)
Costs budgets should ordinarily be reviewed quickly and with a broad brush. Detailed examination is justified where the aggregate estimate is plainly…
|
8 |
| 14 Jul 2015 |
[2015] EWHC 2172 (TCC)
Where a procurement evaluation is fundamentally flawed and the claimant would otherwise have won, the court should not ordinarily compel the contracting…
|
2 |
| 14 Jul 2015 |
[2015] EWHC 2011 (TCC)
In public procurement, published award criteria must be clear, precise and unequivocal. Contracting authorities must apply them transparently and treat…
|
11 |
| 14 Jul 2015 |
[2015] EWHC 1969 (TCC)
Contractual service-point values expressed as maximum values permit an award within a range, having regard to the gravity and circumstances of the breach. They…
|
|
| 3 Jul 2015 |
[2015] EWHC 1802 (TCC)
A court should not determine an otherwise academic question merely because a party seeks a declaration. Where an alleged threat to adjudicate has been…
|
1 |
| 29 Jun 2015 |
[2015] EWHC 2012 (TCC)
An agent must provide the principal, on demand, with documents relating to the principal’s affairs. The duty is ongoing and extends to documents created during…
|
1 |
| 29 Jun 2015 |
[2015] EWHC 1855 (TCC)
Adjudication decisions are generally enforced without reopening issues decided by the adjudicator. An exception arises where the issue is short, self-contained…
|
13 |
| 29 Jun 2015 |
[2015] EWHC 1854 (TCC)
A procurement framework for locum doctors may lawfully provide for both direct supply from a supplier’s own resource pool and supplementary supply managed…
|
|
| 12 Jun 2015 |
[2015] EWHC 1687 (TCC)
Under the current Civil Procedure Rules, a judge may summarily assess costs arising from a hearing conducted, or an order made, by another judge where the…
|
2 |
| 22 May 2015 |
[2015] EWHC 1443 (TCC)
An adjudicator’s jurisdiction is defined by the dispute identified in the notice of adjudication, rather than by the remedy sought. A dispute concerning…
|
|
| 22 May 2015 |
[2015] EWHC 1400 (TCC)
Under a construction contract, an agreement to alter interim-payment dates may implement an express contractual flexibility rather than vary the contract. An…
|
5 |
| 22 May 2015 |
[2015] EWHC 1387 (TCC)
Permission to bring committal proceedings for false statements should be granted only after a cautious assessment of whether there is a strong prima facie case…
|
|
| 21 May 2015 |
[2015] EWHC 1345 (TCC)
Permission for late amendments is governed by the overriding objective of dealing with cases justly and at proportionate cost. Lateness is relative and depends…
|
59 |
| 20 May 2015 |
[2015] EWHC 1460 (TCC)
Indemnity costs require conduct which takes the case out of the ordinary run and is unreasonable to a high degree. A party’s defeat, a robust judgment, or the…
|
|
| 20 May 2015 |
[2015] EWHC 1396 (TCC)
Estoppel by convention may arise where parties to a contract communicate and act upon a shared assumption about fact or law, even without a further concluded…
|
15 |
| 14 May 2015 |
[2015] EWHC 1263 (TCC)
Under a payment mechanism requiring self-monitoring, contractual payment reports must record all service failures notified to the helpdesk, even where the…
|
|
| 6 May 2015 |
[2015] EWHC 1175 (TCC)
Loss of revenue payable under a contractual performance regime may be recoverable as consequential loss where physical damage to revenue-generating property…
|
|
| 30 Apr 2015 |
[2015] EWHC 1150 (TCC)
Under section 45 of the Arbitration Act 1996, the court may determine a contractual question of law arising in arbitration where the statutory conditions are…
|
2 |
| 29 Apr 2015 |
[2015] EWHC 1122 (TCC)
An after-the-event insurance policy can provide security for costs, but only where its terms and the surrounding circumstances give the defendant real…
|
5 |
| 29 Apr 2015 |
[2015] EWHC 1121 (TCC)
Early specific disclosure in procurement litigation depends on the individual circumstances. An unsuccessful tenderer should generally receive promptly the…
|
5 |
| 22 Apr 2015 |
[2015] EWHC 1521 (TCC)
An application made shortly before trial for specific disclosure and permission to rely on new expert evidence must be properly justified. Although the…
|
|
| 22 Apr 2015 |
[2015] EWHC 1117 (TCC)
Relief from sanctions should be refused where a party persistently breaches an order requiring a properly particularised pleading, serves defective particulars…
|
|
| 17 Apr 2015 |
[2015] EWHC 1446 (TCC)
Summary judgment may be granted where pleaded admissions and an unparticularised denial disclose no arguable defence. A professional negligence counterclaim…
|
|
| 17 Apr 2015 |
[2015] EWHC 1009 (TCC)
A court may revisit a judgment before the order is sealed, but a party is not ordinarily entitled to reopen submissions merely because it has developed a new…
|
4 |
| 1 Apr 2015 |
[2015] EWHC 876 (TCC)
On an application to lift the automatic suspension in a public procurement challenge, the court applies the ordinary American Cyanamid approach. The threshold…
|
9 |
| 20 Mar 2015 |
[2015] EWHC 758 (TCC)
An agreement to refer a construction dispute to adjudication may make the adjudicator’s decision finally binding, rather than temporarily binding, if that is…
|
|
| 20 Mar 2015 |
[2015] EWHC 604 (TCC)
A statutory seven-day period for serving a procurement challenge is satisfied when the step required by the relevant rules of court is completed within that…
|
4 |
| 11 Mar 2015 |
[2015] EWHC 667 (TCC)
Adjudicators’ decisions will ordinarily be enforced summarily. A challenge succeeds only where there is a properly arguable breach of natural justice or want…
|
2 |
| 11 Mar 2015 |
[2015] EWHC 587 (TCC)
An adjudicator has no jurisdiction to determine which adjudication provisions govern his appointment or conduct where competing provisions make a material…
|
3 |
| 10 Mar 2015 |
[2015] EWHC 661 (TCC)
An adjudicator’s decision will not be summarily enforced where the circumstances give rise to a real possibility of apparent bias or where the adjudicator…
|
3 |
| 10 Mar 2015 |
[2015] EWHC 556 (TCC)
A professional engineer’s duty to warn is determined in the context of the contractual services undertaken. It is an aspect of the duty to exercise the…
|
|
| 6 Mar 2015 |
[2015] EWHC 459 (TCC)
On discontinuance, the claimant ordinarily pays the defendant’s costs under Civil Procedure Rules 1998, rule 38.6(1). The claimant must show a good reason to…
|
|
| 5 Mar 2015 |
[2015] EWHC 481 (TCC)
In costs management, the court must take incurred costs into account when fixing future costs so that the overall recoverable costs remain reasonable and…
|
16 |
| 27 Feb 2015 |
[2015] EWHC 412 (TCC)
An adjudicator’s decision on an interim payment must be enforced summarily where the adjudicator answered the question referred and no breach of natural…
|
13 |
| 26 Feb 2015 |
[2015] EWHC 457 (TCC)
In an application to lift the statutory suspension in a public procurement challenge, the court applied the established interim-injunction approach: serious…
|
5 |
| 17 Feb 2015 |
[2015] EWHC 325 (TCC)
A contractual time limit for correcting clerical errors in an adjudication award must be applied objectively. A request is operative only if it identifies the…
|
|
| 17 Feb 2015 |
[2015] EWHC 311 (TCC)
Following a finding of serious irregularity under Arbitration Act 1996, remission is the default remedy. The court may set aside an award only where remission…
|
3 |
| 13 Feb 2015 |
[2015] EWHC 269 (TCC)
In a battle of forms, standard terms become contractual only where the party relying on them gives reasonable notice and makes its intention objectively clear.…
|
8 |
| 3 Feb 2015 |
[2015] EWHC 152 (TCC)
Declaratory relief may be granted where there is a live dispute arising from specific existing facts and the declaration will have practical utility, including…
|
|
| 2 Feb 2015 |
[2015] EWHC 949 (TCC)
Courts will rarely restrain payment under an on-demand bond. Intervention is justified only where there is a seriously arguable case of fraud known to the…
|
5 |
| 22 Jan 2015 |
[2015] EWHC 70 (TCC)
A JCT final certificate may be challenged only in proceedings commenced within the contractual 28-day period, subject to the specific protection for…
|
3 |
| 21 Jan 2015 |
[2015] EWHC 96 (TCC)
In adjudication enforcement proceedings, a dispute crystallises when a claim is expressly rejected or, depending on the contractual context, when the…
|
2 |
| 19 Jan 2015 |
[2015] EWHC 58 (TCC)
In an oral framework agreement for property development, “build costs” ordinarily comprise direct labour and materials and site-specific preliminaries. They do…
|
|
| 16 Jan 2015 |
[2015] EWHC 30 (TCC)
On an application for summary judgment, the court must determine whether the claim has a realistic prospect of success without conducting a mini-trial. A short…
|
1 |
| 16 Jan 2015 |
[2015] EWHC 27 (TCC)
For limitation purposes, deliberate concealment requires more than negligent advice. Under section 32(2) of the Limitation Act 1980, the claimant must show a…
|
|
| 15 Jan 2015 |
[2015] EWHC 33 (TCC)
Indemnity costs require conduct that takes the case out of the ordinary run and is generally unreasonable to a high degree. Losing a case, advancing a strongly…
|
2 |
| 14 Jan 2015 |
[2015] EWHC 47 (TCC)
A party wall award incorporating a method statement must be complied with strictly. An obstruction includes material created by the works themselves, where the…
|
|
| 14 Jan 2015 |
[2015] EWHC 187 (TCC)
Preliminary issues concerning the meaning and effect of a settlement, waiver or release should be ordered only where they can sensibly be tried separately and…
|
|
| 23 Jan 2014 |
[2015] EWHC 73 (TCC)
Failure by an unsuccessful tenderer to trigger the statutory suspension under regulation 47G does not automatically break the chain of causation or bar…
|