High Court: Technology and Construction Court judgments, 2015

83 judgments, newest first. Open any case for its summary, the legal points it decides and how later courts have treated it.

Date Case Cited by
21 Dec 2015
[2015] EWHC 3737 (TCC)
In adjudication enforcement proceedings, a misdescription of the contractual route does not deprive an adjudicator of jurisdiction where every realistically…
2
18 Dec 2015
[2015] EWHC 3898 (TCC)
On an application to lift an automatic suspension under the Public Contracts Regulations 2015, the court applies the ordinary interim-relief approach. The…
7
18 Dec 2015
[2015] EWHC 3650 (TCC)
A contract for supplying and installing substantial machinery is a construction contract only if the installation involves construction operations within the…
1
10 Dec 2015
[2015] EWHC 3606 (TCC)
Disclosure cannot be ordered against a defendant who credibly states that the documents are not in his possession, custody or control unless there is material…
7 Dec 2015
[2015] EWHC 3573 (TCC)
Contractual exclusion and limitation clauses are construed by applying the ordinary principles of contractual interpretation. The court must identify what a…
1 Dec 2015
[2015] EWHC 3479 (TCC)
Specific disclosure must be confined to documents relevant to the issues and sought in a proportionate manner. The court may make a targeted disclosure order…
1 Dec 2015
[2015] EWHC 3455 (TCC)
Expert evidence in professional-negligence proceedings is not automatically required. The court must consider the pleaded issues and ask whether expert…
30 Nov 2015
[2015] EWHC 3385 (TCC)
A Part 36 offer made by a defendant with a counterclaim is classified by construing the offer as a whole. The existence of a counterclaim does not…
2
24 Nov 2015
[2015] EWHC 3352 (TCC)
In a hybrid construction contract, the Housing Grants (Construction and Regeneration) Act 1996 applies only to the construction operations within its scope.…
3
20 Nov 2015
[2015] EWHC 3360 (TCC)
A binding settlement may arise from an exchange of emails where the parties’ words and conduct objectively demonstrate an intention to create legal relations…
17 Nov 2015
[2015] EWHC 3320 (TCC)
Where a Part 8 claim produces mixed results on several issues, costs should reflect the parties’ relative success and the proportion of time and preparation…
16 Nov 2015
[2015] EWHC 3244 (TCC)
On a summary judgment application, the court may decide a short point of law or construction where the evidence is sufficient and the parties have had a proper…
13 Nov 2015
[2015] EWHC 2887 (TCC)
For jurisdiction purposes, a contribution claim is characterised by its substance. A claim between parties with no relevant contract is ordinarily a matter…
12 Nov 2015
[2015] EWHC 3074 (TCC)
A contractor seeking additional payment for unforeseen ground conditions must satisfy every contractual condition, including timely notice, materially…
2 Nov 2015
[2015] EWHC 3167 (TCC)
Applications to transfer proceedings into the Technology and Construction Court must be determined by weighing the matters identified in CPR 30.3(2). For…
30 Oct 2015
[2015] EWHC 3067 (TCC)
An adjudicator asked to determine the true value of variations may compare that value with sums already certified and paid, where the referral seeks such other…
30 Oct 2015
[2015] EWHC 3063 (TCC)
Where a party is entitled to apply to strike out a claim for failure to serve Particulars of Claim on time, the costs of that application may be awarded even…
29 Oct 2015
[2015] EWHC 3050 (TCC)
Where security for costs has been provided through an agreed after-the-event insurance policy and incorporated into a court order, the court should not vary…
28 Oct 2015
[2015] EWHC 3091 (TCC)
Costs on opposed amendment applications are not determined solely by identifying which party obtained permission. The court must consider the parties’ conduct…
23 Oct 2015
[2015] EWHC 2915 (TCC)
A contractual adjudication procedure must be construed so that amendments are given practical effect. Where an amendment would otherwise be pointless, the…
21 Oct 2015
[2015] EWHC 3051 (TCC)
An open offer is a package of terms. A party cannot treat part of it as an admission while rejecting the remainder. For judgment under Civil Procedure Rules…
21 Oct 2015
[2015] EWHC 2954 (TCC)
Applications to amend pleadings are assessed by reference to the overriding objective and proportionality. Lateness is relative. An amendment is particularly…
21 Oct 2015
[2015] EWHC 2889 (TCC)
A party may participate in an adjudication while reserving its right to challenge the adjudicator’s jurisdiction at enforcement. Agreement to the adjudicator’s…
1
16 Oct 2015
[2015] EWHC 2923 (TCC)
A professional client may defend a claim for fees by showing that a discrete professional service was not performed, or was so poorly performed that it was…
2
16 Oct 2015
[2015] EWHC 2900 (TCC)
An incentive fee agreement payable on a no win, no fee basis may entitle an agent to a percentage of the saving achieved against the original accepted price…
16 Oct 2015
[2015] EWHC 2858 (TCC)
A contractual time bar preventing proceedings by a beneficiary does not, without clear words, extinguish the beneficiary’s underlying right. It therefore does…
1
15 Oct 2015
[2015] EWHC 18 (TCC)
Fixed recoverable costs may apply to a low-value road-traffic personal injury claim which began under the RTA Protocol, left the Protocol and Stage 3…
2 Oct 2015
[2015] EWHC 2372 (TCC)
A project monitor must exercise reasonable skill and care in checking drawdown applications, reporting material cost increases, and ensuring that lending is…
28 Sep 2015
[2015] EWHC 2694 (TCC)
On an application to end an automatic suspension under the Public Contracts Regulations 2006, the court applies the ordinary American Cyanamid principles on…
14
16 Sep 2015
[2015] EWHC 2624 (TCC)
For summary judgment enforcing an adjudicator’s decision, the court asks whether the defendant has no real prospect of successfully defending the claim and…
4
14 Aug 2015
[2015] EWHC 2433 (TCC)
An interim application under a construction contract must be clear, unambiguous and identifiable in substance, form and intent as an application for a…
4
7 Aug 2015
[2015] EWHC 2384 (TCC)
Applications for relief from sanctions must be assessed using the three-stage approach in Denton v White: the seriousness and significance of the breach…
31 Jul 2015
[2015] EWHC 2692 (TCC)
An adjudication concerning valuation, termination and payment may constitute a single dispute where the issues are financially and factually linked. A party…
30 Jul 2015
[2015] EWHC 2128 (TCC)
In a dilapidations claim, damages for breach of a repairing covenant are capped by the diminution in the value of the reversion where Landlord and Tenant Act…
29 Jul 2015
[2015] EWHC 2274 (TCC)
Costs budgets should ordinarily be reviewed quickly and with a broad brush. Detailed examination is justified where the aggregate estimate is plainly…
8
14 Jul 2015
[2015] EWHC 2172 (TCC)
Where a procurement evaluation is fundamentally flawed and the claimant would otherwise have won, the court should not ordinarily compel the contracting…
2
14 Jul 2015
[2015] EWHC 2011 (TCC)
In public procurement, published award criteria must be clear, precise and unequivocal. Contracting authorities must apply them transparently and treat…
11
14 Jul 2015
[2015] EWHC 1969 (TCC)
Contractual service-point values expressed as maximum values permit an award within a range, having regard to the gravity and circumstances of the breach. They…
3 Jul 2015
[2015] EWHC 1802 (TCC)
A court should not determine an otherwise academic question merely because a party seeks a declaration. Where an alleged threat to adjudicate has been…
1
29 Jun 2015
[2015] EWHC 2012 (TCC)
An agent must provide the principal, on demand, with documents relating to the principal’s affairs. The duty is ongoing and extends to documents created during…
1
29 Jun 2015
[2015] EWHC 1855 (TCC)
Adjudication decisions are generally enforced without reopening issues decided by the adjudicator. An exception arises where the issue is short, self-contained…
13
29 Jun 2015
[2015] EWHC 1854 (TCC)
A procurement framework for locum doctors may lawfully provide for both direct supply from a supplier’s own resource pool and supplementary supply managed…
12 Jun 2015
[2015] EWHC 1687 (TCC)
Under the current Civil Procedure Rules, a judge may summarily assess costs arising from a hearing conducted, or an order made, by another judge where the…
2
22 May 2015
[2015] EWHC 1443 (TCC)
An adjudicator’s jurisdiction is defined by the dispute identified in the notice of adjudication, rather than by the remedy sought. A dispute concerning…
22 May 2015
[2015] EWHC 1400 (TCC)
Under a construction contract, an agreement to alter interim-payment dates may implement an express contractual flexibility rather than vary the contract. An…
5
22 May 2015
[2015] EWHC 1387 (TCC)
Permission to bring committal proceedings for false statements should be granted only after a cautious assessment of whether there is a strong prima facie case…
21 May 2015
[2015] EWHC 1345 (TCC)
Permission for late amendments is governed by the overriding objective of dealing with cases justly and at proportionate cost. Lateness is relative and depends…
59
20 May 2015
[2015] EWHC 1460 (TCC)
Indemnity costs require conduct which takes the case out of the ordinary run and is unreasonable to a high degree. A party’s defeat, a robust judgment, or the…
20 May 2015
[2015] EWHC 1396 (TCC)
Estoppel by convention may arise where parties to a contract communicate and act upon a shared assumption about fact or law, even without a further concluded…
15
14 May 2015
[2015] EWHC 1263 (TCC)
Under a payment mechanism requiring self-monitoring, contractual payment reports must record all service failures notified to the helpdesk, even where the…
6 May 2015
[2015] EWHC 1175 (TCC)
Loss of revenue payable under a contractual performance regime may be recoverable as consequential loss where physical damage to revenue-generating property…
30 Apr 2015
[2015] EWHC 1150 (TCC)
Under section 45 of the Arbitration Act 1996, the court may determine a contractual question of law arising in arbitration where the statutory conditions are…
2
29 Apr 2015
[2015] EWHC 1122 (TCC)
An after-the-event insurance policy can provide security for costs, but only where its terms and the surrounding circumstances give the defendant real…
5
29 Apr 2015
[2015] EWHC 1121 (TCC)
Early specific disclosure in procurement litigation depends on the individual circumstances. An unsuccessful tenderer should generally receive promptly the…
5
22 Apr 2015
[2015] EWHC 1521 (TCC)
An application made shortly before trial for specific disclosure and permission to rely on new expert evidence must be properly justified. Although the…
22 Apr 2015
[2015] EWHC 1117 (TCC)
Relief from sanctions should be refused where a party persistently breaches an order requiring a properly particularised pleading, serves defective particulars…
17 Apr 2015
[2015] EWHC 1446 (TCC)
Summary judgment may be granted where pleaded admissions and an unparticularised denial disclose no arguable defence. A professional negligence counterclaim…
17 Apr 2015
[2015] EWHC 1009 (TCC)
A court may revisit a judgment before the order is sealed, but a party is not ordinarily entitled to reopen submissions merely because it has developed a new…
4
1 Apr 2015
[2015] EWHC 876 (TCC)
On an application to lift the automatic suspension in a public procurement challenge, the court applies the ordinary American Cyanamid approach. The threshold…
9
20 Mar 2015
[2015] EWHC 758 (TCC)
An agreement to refer a construction dispute to adjudication may make the adjudicator’s decision finally binding, rather than temporarily binding, if that is…
20 Mar 2015
[2015] EWHC 604 (TCC)
A statutory seven-day period for serving a procurement challenge is satisfied when the step required by the relevant rules of court is completed within that…
4
11 Mar 2015
[2015] EWHC 667 (TCC)
Adjudicators’ decisions will ordinarily be enforced summarily. A challenge succeeds only where there is a properly arguable breach of natural justice or want…
2
11 Mar 2015
[2015] EWHC 587 (TCC)
An adjudicator has no jurisdiction to determine which adjudication provisions govern his appointment or conduct where competing provisions make a material…
3
10 Mar 2015
[2015] EWHC 661 (TCC)
An adjudicator’s decision will not be summarily enforced where the circumstances give rise to a real possibility of apparent bias or where the adjudicator…
3
10 Mar 2015
[2015] EWHC 556 (TCC)
A professional engineer’s duty to warn is determined in the context of the contractual services undertaken. It is an aspect of the duty to exercise the…
6 Mar 2015
[2015] EWHC 459 (TCC)
On discontinuance, the claimant ordinarily pays the defendant’s costs under Civil Procedure Rules 1998, rule 38.6(1). The claimant must show a good reason to…
5 Mar 2015
[2015] EWHC 481 (TCC)
In costs management, the court must take incurred costs into account when fixing future costs so that the overall recoverable costs remain reasonable and…
16
27 Feb 2015
[2015] EWHC 412 (TCC)
An adjudicator’s decision on an interim payment must be enforced summarily where the adjudicator answered the question referred and no breach of natural…
13
26 Feb 2015
[2015] EWHC 457 (TCC)
In an application to lift the statutory suspension in a public procurement challenge, the court applied the established interim-injunction approach: serious…
5
17 Feb 2015
[2015] EWHC 325 (TCC)
A contractual time limit for correcting clerical errors in an adjudication award must be applied objectively. A request is operative only if it identifies the…
17 Feb 2015
[2015] EWHC 311 (TCC)
Following a finding of serious irregularity under Arbitration Act 1996, remission is the default remedy. The court may set aside an award only where remission…
3
13 Feb 2015
[2015] EWHC 269 (TCC)
In a battle of forms, standard terms become contractual only where the party relying on them gives reasonable notice and makes its intention objectively clear.…
8
3 Feb 2015
[2015] EWHC 152 (TCC)
Declaratory relief may be granted where there is a live dispute arising from specific existing facts and the declaration will have practical utility, including…
2 Feb 2015
[2015] EWHC 949 (TCC)
Courts will rarely restrain payment under an on-demand bond. Intervention is justified only where there is a seriously arguable case of fraud known to the…
5
22 Jan 2015
[2015] EWHC 70 (TCC)
A JCT final certificate may be challenged only in proceedings commenced within the contractual 28-day period, subject to the specific protection for…
3
21 Jan 2015
[2015] EWHC 96 (TCC)
In adjudication enforcement proceedings, a dispute crystallises when a claim is expressly rejected or, depending on the contractual context, when the…
2
19 Jan 2015
[2015] EWHC 58 (TCC)
In an oral framework agreement for property development, “build costs” ordinarily comprise direct labour and materials and site-specific preliminaries. They do…
16 Jan 2015
[2015] EWHC 30 (TCC)
On an application for summary judgment, the court must determine whether the claim has a realistic prospect of success without conducting a mini-trial. A short…
1
16 Jan 2015
[2015] EWHC 27 (TCC)
For limitation purposes, deliberate concealment requires more than negligent advice. Under section 32(2) of the Limitation Act 1980, the claimant must show a…
15 Jan 2015
[2015] EWHC 33 (TCC)
Indemnity costs require conduct that takes the case out of the ordinary run and is generally unreasonable to a high degree. Losing a case, advancing a strongly…
2
14 Jan 2015
[2015] EWHC 47 (TCC)
A party wall award incorporating a method statement must be complied with strictly. An obstruction includes material created by the works themselves, where the…
14 Jan 2015
[2015] EWHC 187 (TCC)
Preliminary issues concerning the meaning and effect of a settlement, waiver or release should be ordered only where they can sensibly be tried separately and…
23 Jan 2014
[2015] EWHC 73 (TCC)
Failure by an unsuccessful tenderer to trigger the statutory suspension under regulation 47G does not automatically break the chain of causation or bar…