| Date | Case | Cited by |
|---|---|---|
| 21 Dec 2016 |
[2016] EWHC 3348 (TCC)
Costs are determined by the overall justice of the litigation. The general rule that costs follow the event does not require an automatic reduction merely…
|
1 |
| 21 Dec 2016 |
[2016] EWHC 3291 (TCC)
An amendment will be refused where the proposed allegation has no real prospect of success. A main contractor is not vicariously liable for the negligence of…
|
|
| 21 Dec 2016 |
[2016] EWHC 3233 (TCC)
Where damages are payable in a foreign currency, the court may express the judgment in sterling if that currency most accurately reflects where the claimant’s…
|
2 |
| 20 Dec 2016 |
[2016] EWHC 3326 (TCC)
For the purposes of the second Francovich condition, a contracting authority’s failure to award a procurement contract to the tenderer whose bid was the most…
|
4 |
| 15 Dec 2016 |
[2016] EWHC 3180 (TCC)
A certificate of non-completion under a construction contract is cancelled when an extension of time is granted, including where the extension is granted after…
|
1 |
| 28 Nov 2016 |
[2016] EWHC 3045 (TCC)
Early specific disclosure in procurement proceedings is exceptional and fact-sensitive. The court must balance the unsuccessful tenderer’s need for prompt…
|
|
| 25 Nov 2016 |
[2016] EWHC 3007 (TCC)
An adjudicator cannot ordinarily determine whether a contract exists at all where one party has clearly reserved its jurisdictional objection. Agreement to the…
|
2 |
| 18 Nov 2016 |
[2016] EWHC 2946 (TCC)
In deciding costs under Civil Procedure Rules 1998, Part 44.2, the court starts with the unsuccessful party paying the successful party’s costs, but must…
|
|
| 11 Nov 2016 |
[2016] EWHC 3092 (TCC)
An application for early specific disclosure requires a proper basis for disclosure before close of pleadings, demonstrated by an important or significant…
|
5 |
| 10 Nov 2016 |
[2016] EWHC 2863 (TCC)
A settlement offer referring expressly to Part 36 should, where possible, be construed as an effective Part 36 offer. The fact that it was made before…
|
|
| 9 Nov 2016 |
[2016] EWHC 2800 (TCC)
In a competing-theories causation case, the court may analyse and eliminate possible causes. It must nevertheless stand back and decide whether the claimant’s…
|
|
| 3 Nov 2016 |
[2016] EWHC 2764 (TCC)
Joinder of a new defendant requires a dispute or connected issue falling within CPR 19.2(2), and a claimant cannot be compelled to litigate against a party…
|
3 |
| 1 Nov 2016 |
[2016] EWHC 3596 (TCC)
Challenges under Arbitration Act 1996 section 68 are concerned with serious procedural irregularity and substantial injustice, not with re-evaluating evidence…
|
|
| 27 Oct 2016 |
[2016] EWHC 2614 (TCC)
Contractual dispute-resolution provisions are ordinarily enforceable, and court proceedings brought in breach of them will usually be stayed. A party is not…
|
1 |
| 26 Oct 2016 |
[2016] EWHC 2626 (TCC)
In an application to lift the automatic suspension of a public procurement contract award, the court applied an approach akin to American Cyanamid. The…
|
1 |
| 25 Oct 2016 |
[2016] EWHC 2509 (TCC)
A court should generally recognise a simple contract where parties have instructed and performed work, even though they contemplated a later formal agreement.…
|
1 |
| 19 Oct 2016 |
[2016] EWHC 2500 (TCC)
In a split trial, costs need not await the assessment of damages. The court may defer liability costs where there is a real possibility that the claimant will…
|
1 |
| 17 Oct 2016 |
[2016] EWHC 2511 (TCC)
Where proceedings are issued without abusive conduct, an underpayment of the issue fee does not prevent the claim from being “brought” for limitation purposes…
|
3 |
| 13 Oct 2016 |
[2016] EWHC 3082 (TCC)
An adjournment should be granted where late disclosure of material documents places the opposing party in an impossible position when preparing for trial. In…
|
|
| 7 Oct 2016 |
[2016] EWHC 2062 (TCC)
A contractor supplying fabricated structures must achieve the contractual standard of workmanship, not merely exercise reasonable skill and care in following…
|
|
| 6 Oct 2016 |
[2016] EWHC 2045 (TCC)
A project monitor retained by a lender must exercise reasonable care and skill in checking drawdown applications, monitoring progress and variations, and…
|
1 |
| 3 Oct 2016 |
[2016] EWHC 2368 (TCC)
Adjudicators’ decisions are enforceable despite errors of fact, law or arithmetic, provided the adjudicator decided the dispute referred and did not re-decide…
|
|
| 29 Sep 2016 |
[2016] EWHC 2295 (TCC)
A letter of intent may create a binding interim contract while the parties negotiate a later replacement contract. Work performed under that letter is not, by…
|
2 |
| 22 Sep 2016 |
[2016] EWHC 2616 (TCC)
The statutory payment regime under the Housing Grants, Construction and Regeneration Act 1996 regulates cash flow. It does not ordinarily determine the…
|
1 |
| 13 Sep 2016 |
[2016] EWHC 2283 (TCC)
Adjudication decisions will ordinarily be enforced summarily because adjudication provides interim finality. The court will decline enforcement for breach of…
|
3 |
| 1 Sep 2016 |
[2016] EWHC 2232 (TCC)
Adjudication decisions under the Construction Act are binding and enforceable on an interim basis until the underlying dispute is finally determined. A party…
|
|
| 31 Aug 2016 |
[2016] EWHC 2191 (TCC)
A contractual dispute-resolution clause limits the court to questions of law arising from the dispute referred to adjudication. On a de novo construction of a…
|
2 |
| 26 Aug 2016 |
[2016] EWHC 2171 (TCC)
The court has a wide discretion to impose conditions when permitting a party to rely on replacement expert evidence. Disclosure of the first expert’s report…
|
4 |
| 16 Aug 2016 |
[2016] EWHC 3901 (TCC)
Adjudicators’ decisions are ordinarily enforced on an interim basis, even where the adjudicator may have made an error of fact, law or procedure. The court may…
|
|
| 5 Aug 2016 |
[2016] EWHC 2945 (TCC)
An adjudicator’s decision is enforceable where the parties objectively agreed an extension of time, even if one party maintained a jurisdictional reservation.…
|
|
| 3 Aug 2016 |
[2016] EWHC 2032 (TCC)
A settlement requires acceptance of an offer on its stated terms. A response which proposes different terms, leaves material matters unresolved, or…
|
|
| 3 Aug 2016 |
[2016] EWHC 2031 (TCC)
A claim previously decided cannot generally be reopened by recasting it or relying on changed circumstances. Claims arising from a later, distinct breach may…
|
|
| 2 Aug 2016 |
[2016] EWHC 1924 (TCC)
A party may confer jurisdiction on an expert determination by agreement, waiver or estoppel arising from words and conduct, even where the contract does not…
|
4 |
| 29 Jul 2016 |
[2016] EWHC 1988 (TCC)
In a public procurement challenge, the court’s role is supervisory. It must not re-mark tenders, but may intervene where a contracting authority has made a…
|
18 |
| 27 Jul 2016 |
[2016] EWHC 1949 (TCC)
A professional is negligent where the advice given falls outside the range reasonably available to a competent member of that profession. In structural…
|
|
| 27 Jul 2016 |
[2016] EWHC 1946 (TCC)
On an application to enforce an adjudicator’s decision, the court identifies the dispute by analysing the notice of adjudication, referral and decision…
|
|
| 21 Jul 2016 |
[2016] EWHC 1807 (TCC)
Where a claim has been properly brought within the limitation period, an application to amend the claim form to increase its value is governed principally by…
|
5 |
| 4 Jul 2016 |
[2016] EWHC 1669 (TCC)
Section 82 of the New Roads and Street Works Act 1991 imposes strict liability for expenses reasonably incurred in repairing damage to apparatus in the street.…
|
|
| 1 Jul 2016 |
[2016] EWHC 1589 (TCC)
On a summary judgment application to enforce an adjudicator’s decision, the court must refuse judgment where the contractual basis for the adjudicator’s…
|
|
| 29 Jun 2016 |
[2016] EWHC 1498 (TCC)
A term may be implied into a detailed commercial agreement only where it is necessary to give the agreement commercial or practical coherence, or where it is…
|
|
| 13 Jun 2016 |
[2016] EWHC 1235 (TCC)
For summary judgment, the claimant must show that the defence has no real prospect of success. A defence is unsuitable for summary determination where disputed…
|
1 |
| 10 Jun 2016 |
[2016] EWHC 1333 (TCC)
In construing a construction contract, the court must ascertain what reasonable parties would have understood from the language read in its commercial context.…
|
2 |
| 6 Jun 2016 |
[2016] EWHC 1286 (TCC)
A solicitor or barrister is required to perform the tasks falling within the agreed retainer and to give advice reasonably incidental to those tasks. The scope…
|
|
| 27 May 2016 |
[2016] EWHC 975 (TCC)
Forum non conveniens cannot justify staying proceedings against a defendant domiciled in England where Owusu v Jackson applies. The court nevertheless retains…
|
4 |
| 27 May 2016 |
[2016] EWHC 1393 (TCC)
On an application to lift an automatic suspension in public procurement proceedings, damages are assessed by reference to the interests of the party seeking…
|
4 |
| 27 May 2016 |
[2016] EWHC 1248 (TCC)
In a civil claim based on competing explanations, the claimant retains the burden of proving its case on the balance of probabilities. The court may analyse…
|
|
| 23 May 2016 |
[2016] EWHC 1148 (TCC)
An adjudication clause covering disputes arising under or in connection with a construction subcontract may extend to a dispute about whether the parties…
|
3 |
| 4 May 2016 |
[2016] EWHC 902 (TCC)
Under a business sale agreement transferring responsibility for construction liabilities, liability for defects depended on the contractual wording. Actual…
|
|
| 28 Apr 2016 |
[2016] EWHC 905 (TCC)
Under a construction sub-contract providing for revised or further revised periods of completion, an extension of time operates by revising the existing…
|
|
| 15 Apr 2016 |
[2016] EWHC 806 (TCC)
On an appeal on a question of law from an arbitrator, the court accepts the arbitrator’s factual findings. It intervenes on mixed questions of fact and law…
|
2 |
| 14 Apr 2016 |
[2016] EWHC 792 (TCC)
An adjudicator may decide an issue on a basis for which neither party expressly contended, provided the relevant material was before the parties and the…
|
5 |
| 6 Apr 2016 |
[2016] EWHC 771 (TCC)
A procurement for enforcement agency services was a services concession contract and was therefore outside the Public Contract Regulations 2015. A claim…
|
|
| 5 Apr 2016 |
[2016] EWHC 133 (TCC)
A statutory sewerage undertaker may owe a common-law duty in nuisance where the complaint concerns operational failures, such as inadequate maintenance or…
|
2 |
| 23 Mar 2016 |
[2016] EWHC 590 (TCC)
In an insurance policy excluding avoidance except for “deliberate or fraudulent non-disclosure”, deliberate non-disclosure means an intentional failure to…
|
5 |
| 18 Mar 2016 |
[2016] EWHC 607 (TCC)
A specifically drafted contractual regime for liquidated damages may operate independently of a general employer’s claims procedure. The court must construe…
|
|
| 17 Mar 2016 |
[2016] EWHC 1852 (TCC)
The scope of an adjudication reference may extend beyond the precise wording of the notice. A defence may widen the ambit of the dispute where it responds to…
|
|
| 16 Mar 2016 |
[2016] EWHC 557 (TCC)
Under a construction contract incorporating a statutory interim-payment regime, a contractor’s application must be an unambiguous statement of the sum…
|
7 |
| 14 Mar 2016 |
[2016] EWHC 531 (TCC)
Contractual provisions must be construed as a coherent whole. The court identifies the meaning reasonably conveyed by the language in its documentary, factual…
|
3 |
| 11 Mar 2016 |
[2016] EWHC 488 (TCC)
Costs budgeting is a prospective case-management exercise rather than a detailed assessment in advance. The court should use a broad, impressionistic approach…
|
|
| 24 Feb 2016 |
[2016] EWHC 357 (TCC)
In a construction contract, responsibility for obtaining planning permission is ordinarily implied to rest primarily with the employer, because the employer…
|
|
| 18 Feb 2016 |
[2016] EWHC 317 (TCC)
An adjudicator’s jurisdiction is determined by the nature, scope and extent of the dispute identified in the notice of adjudication. Where a notice raises the…
|
5 |
| 15 Feb 2016 |
[2016] EWHC 285 (TCC)
In adjudication enforcement proceedings, a dispute will ordinarily crystallise when a claim has remained unaccepted for a reasonable period. Outstanding…
|
1 |
| 15 Feb 2016 |
[2016] EWHC 241 (TCC)
Where a construction contract provides an adequate payment mechanism, the payment provisions of the contract govern the payment dates. If the payer fails to…
|
|
| 15 Feb 2016 |
[2016] EWHC 222 (TCC)
A construction payment amendment must be construed, where reasonably possible, so that it complies with the Housing Grants, Construction and Regeneration Act…
|
5 |
| 12 Feb 2016 |
[2016] EWHC 238 (TCC)
An adjudicator appointed under the Scheme for Construction Contracts may adjudicate more than one dispute at the same time only with the consent of all parties…
|
1 |
| 11 Feb 2016 |
[2016] EWHC 236 (TCC)
A non-exclusive English jurisdiction clause creates a strong prima facie case for retaining English jurisdiction. The party seeking to avoid that contractual…
|
|
| 5 Feb 2016 |
[2016] EWHC 199 (TCC)
In determining the contracting party to an oral agreement, the court applies an objective test. The person whose words or conduct form the agreement is the…
|
|
| 5 Feb 2016 |
[2016] EWHC 195 (TCC)
A contractual reference to a 10-year NHBC warranty does not ordinarily create a limitation period. Its meaning depends on the language of the clause and the…
|
2 |
| 4 Feb 2016 |
[2016] EWHC 167 (TCC)
A Part 36 offer need not reflect an outcome which the court could technically order. In a binary liability case, an offer to accept a discounted proportion of…
|
7 |
| 3 Feb 2016 |
[2016] EWHC 168 (TCC)
Where parties to a construction contract agree the amounts and intervals of interim payments, that agreement governs the payment regime. The payment provisions…
|
6 |
| 27 Jan 2016 |
[2016] EWHC 166 (TCC)
Whether a demand under an on-demand guarantee satisfies any formal requirements depends on the proper construction of the guarantee itself. General…
|
|
| 25 Jan 2016 |
[2016] EWHC 81 (TCC)
In deciding whether an adjudicator approached issues with a closed mind, the court must consider all relevant circumstances known when the challenge is…
|
|
| 20 Jan 2016 |
[2016] EWHC 76 (TCC)
A party may contract on another party’s written standard terms of business even though only some of those terms are incorporated. A contractual provision…
|
1 |
| 15 Jan 2016 |
[2016] EWHC 40 (TCC)
A contract for professional services requires objectively ascertainable agreement, sufficient certainty, an intention to create legal relations and…
|