High Court: Technology and Construction Court judgments, 2016

74 judgments, newest first. Open any case for its summary, the legal points it decides and how later courts have treated it.

Date Case Cited by
21 Dec 2016
[2016] EWHC 3348 (TCC)
Costs are determined by the overall justice of the litigation. The general rule that costs follow the event does not require an automatic reduction merely…
1
21 Dec 2016
[2016] EWHC 3291 (TCC)
An amendment will be refused where the proposed allegation has no real prospect of success. A main contractor is not vicariously liable for the negligence of…
21 Dec 2016
[2016] EWHC 3233 (TCC)
Where damages are payable in a foreign currency, the court may express the judgment in sterling if that currency most accurately reflects where the claimant’s…
2
20 Dec 2016
[2016] EWHC 3326 (TCC)
For the purposes of the second Francovich condition, a contracting authority’s failure to award a procurement contract to the tenderer whose bid was the most…
4
15 Dec 2016
[2016] EWHC 3180 (TCC)
A certificate of non-completion under a construction contract is cancelled when an extension of time is granted, including where the extension is granted after…
1
28 Nov 2016
[2016] EWHC 3045 (TCC)
Early specific disclosure in procurement proceedings is exceptional and fact-sensitive. The court must balance the unsuccessful tenderer’s need for prompt…
25 Nov 2016
[2016] EWHC 3007 (TCC)
An adjudicator cannot ordinarily determine whether a contract exists at all where one party has clearly reserved its jurisdictional objection. Agreement to the…
2
18 Nov 2016
[2016] EWHC 2946 (TCC)
In deciding costs under Civil Procedure Rules 1998, Part 44.2, the court starts with the unsuccessful party paying the successful party’s costs, but must…
11 Nov 2016
[2016] EWHC 3092 (TCC)
An application for early specific disclosure requires a proper basis for disclosure before close of pleadings, demonstrated by an important or significant…
5
10 Nov 2016
[2016] EWHC 2863 (TCC)
A settlement offer referring expressly to Part 36 should, where possible, be construed as an effective Part 36 offer. The fact that it was made before…
9 Nov 2016
[2016] EWHC 2800 (TCC)
In a competing-theories causation case, the court may analyse and eliminate possible causes. It must nevertheless stand back and decide whether the claimant’s…
3 Nov 2016
[2016] EWHC 2764 (TCC)
Joinder of a new defendant requires a dispute or connected issue falling within CPR 19.2(2), and a claimant cannot be compelled to litigate against a party…
3
1 Nov 2016
[2016] EWHC 3596 (TCC)
Challenges under Arbitration Act 1996 section 68 are concerned with serious procedural irregularity and substantial injustice, not with re-evaluating evidence…
27 Oct 2016
[2016] EWHC 2614 (TCC)
Contractual dispute-resolution provisions are ordinarily enforceable, and court proceedings brought in breach of them will usually be stayed. A party is not…
1
26 Oct 2016
[2016] EWHC 2626 (TCC)
In an application to lift the automatic suspension of a public procurement contract award, the court applied an approach akin to American Cyanamid. The…
1
25 Oct 2016
[2016] EWHC 2509 (TCC)
A court should generally recognise a simple contract where parties have instructed and performed work, even though they contemplated a later formal agreement.…
1
19 Oct 2016
[2016] EWHC 2500 (TCC)
In a split trial, costs need not await the assessment of damages. The court may defer liability costs where there is a real possibility that the claimant will…
1
17 Oct 2016
[2016] EWHC 2511 (TCC)
Where proceedings are issued without abusive conduct, an underpayment of the issue fee does not prevent the claim from being “brought” for limitation purposes…
3
13 Oct 2016
[2016] EWHC 3082 (TCC)
An adjournment should be granted where late disclosure of material documents places the opposing party in an impossible position when preparing for trial. In…
7 Oct 2016
[2016] EWHC 2062 (TCC)
A contractor supplying fabricated structures must achieve the contractual standard of workmanship, not merely exercise reasonable skill and care in following…
6 Oct 2016
[2016] EWHC 2045 (TCC)
A project monitor retained by a lender must exercise reasonable care and skill in checking drawdown applications, monitoring progress and variations, and…
1
3 Oct 2016
[2016] EWHC 2368 (TCC)
Adjudicators’ decisions are enforceable despite errors of fact, law or arithmetic, provided the adjudicator decided the dispute referred and did not re-decide…
29 Sep 2016
[2016] EWHC 2295 (TCC)
A letter of intent may create a binding interim contract while the parties negotiate a later replacement contract. Work performed under that letter is not, by…
2
22 Sep 2016
[2016] EWHC 2616 (TCC)
The statutory payment regime under the Housing Grants, Construction and Regeneration Act 1996 regulates cash flow. It does not ordinarily determine the…
1
13 Sep 2016
[2016] EWHC 2283 (TCC)
Adjudication decisions will ordinarily be enforced summarily because adjudication provides interim finality. The court will decline enforcement for breach of…
3
1 Sep 2016
[2016] EWHC 2232 (TCC)
Adjudication decisions under the Construction Act are binding and enforceable on an interim basis until the underlying dispute is finally determined. A party…
31 Aug 2016
[2016] EWHC 2191 (TCC)
A contractual dispute-resolution clause limits the court to questions of law arising from the dispute referred to adjudication. On a de novo construction of a…
2
26 Aug 2016
[2016] EWHC 2171 (TCC)
The court has a wide discretion to impose conditions when permitting a party to rely on replacement expert evidence. Disclosure of the first expert’s report…
4
16 Aug 2016
[2016] EWHC 3901 (TCC)
Adjudicators’ decisions are ordinarily enforced on an interim basis, even where the adjudicator may have made an error of fact, law or procedure. The court may…
5 Aug 2016
[2016] EWHC 2945 (TCC)
An adjudicator’s decision is enforceable where the parties objectively agreed an extension of time, even if one party maintained a jurisdictional reservation.…
3 Aug 2016
[2016] EWHC 2032 (TCC)
A settlement requires acceptance of an offer on its stated terms. A response which proposes different terms, leaves material matters unresolved, or…
3 Aug 2016
[2016] EWHC 2031 (TCC)
A claim previously decided cannot generally be reopened by recasting it or relying on changed circumstances. Claims arising from a later, distinct breach may…
2 Aug 2016
[2016] EWHC 1924 (TCC)
A party may confer jurisdiction on an expert determination by agreement, waiver or estoppel arising from words and conduct, even where the contract does not…
4
29 Jul 2016
[2016] EWHC 1988 (TCC)
In a public procurement challenge, the court’s role is supervisory. It must not re-mark tenders, but may intervene where a contracting authority has made a…
18
27 Jul 2016
[2016] EWHC 1949 (TCC)
A professional is negligent where the advice given falls outside the range reasonably available to a competent member of that profession. In structural…
27 Jul 2016
[2016] EWHC 1946 (TCC)
On an application to enforce an adjudicator’s decision, the court identifies the dispute by analysing the notice of adjudication, referral and decision…
21 Jul 2016
[2016] EWHC 1807 (TCC)
Where a claim has been properly brought within the limitation period, an application to amend the claim form to increase its value is governed principally by…
5
4 Jul 2016
[2016] EWHC 1669 (TCC)
Section 82 of the New Roads and Street Works Act 1991 imposes strict liability for expenses reasonably incurred in repairing damage to apparatus in the street.…
1 Jul 2016
[2016] EWHC 1589 (TCC)
On a summary judgment application to enforce an adjudicator’s decision, the court must refuse judgment where the contractual basis for the adjudicator’s…
29 Jun 2016
[2016] EWHC 1498 (TCC)
A term may be implied into a detailed commercial agreement only where it is necessary to give the agreement commercial or practical coherence, or where it is…
13 Jun 2016
[2016] EWHC 1235 (TCC)
For summary judgment, the claimant must show that the defence has no real prospect of success. A defence is unsuitable for summary determination where disputed…
1
10 Jun 2016
[2016] EWHC 1333 (TCC)
In construing a construction contract, the court must ascertain what reasonable parties would have understood from the language read in its commercial context.…
2
6 Jun 2016
[2016] EWHC 1286 (TCC)
A solicitor or barrister is required to perform the tasks falling within the agreed retainer and to give advice reasonably incidental to those tasks. The scope…
27 May 2016
[2016] EWHC 975 (TCC)
Forum non conveniens cannot justify staying proceedings against a defendant domiciled in England where Owusu v Jackson applies. The court nevertheless retains…
4
27 May 2016
[2016] EWHC 1393 (TCC)
On an application to lift an automatic suspension in public procurement proceedings, damages are assessed by reference to the interests of the party seeking…
4
27 May 2016
[2016] EWHC 1248 (TCC)
In a civil claim based on competing explanations, the claimant retains the burden of proving its case on the balance of probabilities. The court may analyse…
23 May 2016
[2016] EWHC 1148 (TCC)
An adjudication clause covering disputes arising under or in connection with a construction subcontract may extend to a dispute about whether the parties…
3
4 May 2016
[2016] EWHC 902 (TCC)
Under a business sale agreement transferring responsibility for construction liabilities, liability for defects depended on the contractual wording. Actual…
28 Apr 2016
[2016] EWHC 905 (TCC)
Under a construction sub-contract providing for revised or further revised periods of completion, an extension of time operates by revising the existing…
15 Apr 2016
[2016] EWHC 806 (TCC)
On an appeal on a question of law from an arbitrator, the court accepts the arbitrator’s factual findings. It intervenes on mixed questions of fact and law…
2
14 Apr 2016
[2016] EWHC 792 (TCC)
An adjudicator may decide an issue on a basis for which neither party expressly contended, provided the relevant material was before the parties and the…
5
6 Apr 2016
[2016] EWHC 771 (TCC)
A procurement for enforcement agency services was a services concession contract and was therefore outside the Public Contract Regulations 2015. A claim…
5 Apr 2016
[2016] EWHC 133 (TCC)
A statutory sewerage undertaker may owe a common-law duty in nuisance where the complaint concerns operational failures, such as inadequate maintenance or…
2
23 Mar 2016
[2016] EWHC 590 (TCC)
In an insurance policy excluding avoidance except for “deliberate or fraudulent non-disclosure”, deliberate non-disclosure means an intentional failure to…
5
18 Mar 2016
[2016] EWHC 607 (TCC)
A specifically drafted contractual regime for liquidated damages may operate independently of a general employer’s claims procedure. The court must construe…
17 Mar 2016
[2016] EWHC 1852 (TCC)
The scope of an adjudication reference may extend beyond the precise wording of the notice. A defence may widen the ambit of the dispute where it responds to…
16 Mar 2016
[2016] EWHC 557 (TCC)
Under a construction contract incorporating a statutory interim-payment regime, a contractor’s application must be an unambiguous statement of the sum…
7
14 Mar 2016
[2016] EWHC 531 (TCC)
Contractual provisions must be construed as a coherent whole. The court identifies the meaning reasonably conveyed by the language in its documentary, factual…
3
11 Mar 2016
[2016] EWHC 488 (TCC)
Costs budgeting is a prospective case-management exercise rather than a detailed assessment in advance. The court should use a broad, impressionistic approach…
24 Feb 2016
[2016] EWHC 357 (TCC)
In a construction contract, responsibility for obtaining planning permission is ordinarily implied to rest primarily with the employer, because the employer…
18 Feb 2016
[2016] EWHC 317 (TCC)
An adjudicator’s jurisdiction is determined by the nature, scope and extent of the dispute identified in the notice of adjudication. Where a notice raises the…
5
15 Feb 2016
[2016] EWHC 285 (TCC)
In adjudication enforcement proceedings, a dispute will ordinarily crystallise when a claim has remained unaccepted for a reasonable period. Outstanding…
1
15 Feb 2016
[2016] EWHC 241 (TCC)
Where a construction contract provides an adequate payment mechanism, the payment provisions of the contract govern the payment dates. If the payer fails to…
15 Feb 2016
[2016] EWHC 222 (TCC)
A construction payment amendment must be construed, where reasonably possible, so that it complies with the Housing Grants, Construction and Regeneration Act…
5
12 Feb 2016
[2016] EWHC 238 (TCC)
An adjudicator appointed under the Scheme for Construction Contracts may adjudicate more than one dispute at the same time only with the consent of all parties…
1
11 Feb 2016
[2016] EWHC 236 (TCC)
A non-exclusive English jurisdiction clause creates a strong prima facie case for retaining English jurisdiction. The party seeking to avoid that contractual…
5 Feb 2016
[2016] EWHC 199 (TCC)
In determining the contracting party to an oral agreement, the court applies an objective test. The person whose words or conduct form the agreement is the…
5 Feb 2016
[2016] EWHC 195 (TCC)
A contractual reference to a 10-year NHBC warranty does not ordinarily create a limitation period. Its meaning depends on the language of the clause and the…
2
4 Feb 2016
[2016] EWHC 167 (TCC)
A Part 36 offer need not reflect an outcome which the court could technically order. In a binary liability case, an offer to accept a discounted proportion of…
7
3 Feb 2016
[2016] EWHC 168 (TCC)
Where parties to a construction contract agree the amounts and intervals of interim payments, that agreement governs the payment regime. The payment provisions…
6
27 Jan 2016
[2016] EWHC 166 (TCC)
Whether a demand under an on-demand guarantee satisfies any formal requirements depends on the proper construction of the guarantee itself. General…
25 Jan 2016
[2016] EWHC 81 (TCC)
In deciding whether an adjudicator approached issues with a closed mind, the court must consider all relevant circumstances known when the challenge is…
20 Jan 2016
[2016] EWHC 76 (TCC)
A party may contract on another party’s written standard terms of business even though only some of those terms are incorporated. A contractual provision…
1
15 Jan 2016
[2016] EWHC 40 (TCC)
A contract for professional services requires objectively ascertainable agreement, sufficient certainty, an intention to create legal relations and…