| Date | Case | Cited by |
|---|---|---|
| 21 Dec 2017 |
[2017] EWHC 3389 (TCC)
In a regulated procurement, tender documents must state the evaluation criteria and the consequences of failing a criterion with sufficient clarity to permit…
|
6 |
| 20 Dec 2017 |
[2017] EWHC 3286 (TCC)
A performance bond drafted as secondary liability may nevertheless create liability for an unpaid contractual debt arising after the contractor’s insolvency. A…
|
3 |
| 12 Dec 2017 |
[2017] EWHC 3235 (TCC)
Where a construction contract provides that a notified figure becomes binding unless challenged within a specified period, the notice must clearly identify the…
|
1 |
| 7 Dec 2017 |
[2017] EWHC 3173 (TCC)
Contractual provisions must be interpreted objectively, by considering the natural and usual meaning of the language in its contractual and commercial context.…
|
1 |
| 6 Dec 2017 |
[2017] EWHC 3092 (TCC)
An appellate court will interfere with a case-management decision where the first-instance judge erred in law, failed to consider relevant matters, or reached…
|
|
| 30 Nov 2017 |
[2017] EWHC 3073 (TCC)
A contractual obligation is an indemnity, rather than a guarantee, where its proper construction imposes a primary obligation on the promisor, even if the…
|
2 |
| 30 Nov 2017 |
[2017] EWHC 3055 (TCC)
A challenge under section 67 of the Arbitration Act 1996 concerns substantive jurisdiction, not the correctness of a tribunal’s decision on contractual…
|
|
| 29 Nov 2017 |
[2017] EWHC 3066 (TCC)
Where a construction contract contains a sufficiently broad extension-of-time mechanism, delay caused by prevention, late possession and variations should…
|
|
| 28 Nov 2017 |
[2017] EWHC 3046 (TCC)
Where Civil Procedure Rules 1998, rule 3.13 permits the court to order otherwise, a written timetable issued by the court office may constitute such an order.…
|
|
| 28 Nov 2017 |
[2017] EWHC 2979 (TCC)
A modifying agreement must be construed in its contractual context. An obligation to use “fullest endeavours” to achieve a stage by a date is not an absolute…
|
|
| 9 Nov 2017 |
[2017] EWHC 2829 (TCC)
A supplier of hired electrical equipment may owe continuing contractual and statutory obligations where the agreement requires equipment to remain available…
|
1 |
| 2 Nov 2017 |
[2017] EWHC 2751 (TCC)
Substitution of a defendant is appropriate where the wrong party was joined because of that party’s conduct and substitution enables the real dispute to be…
|
|
| 31 Oct 2017 |
[2017] EWHC 2667 (TCC)
In a public procurement challenge, a contracting authority is required to seek clarification only in exceptional or limited circumstances. The tender must…
|
2 |
| 31 Oct 2017 |
[2017] EWHC 2633 (TCC)
Where a contractual termination power is expressly made subject to a further clause, that clause may operate as a condition precedent to termination. The…
|
|
| 18 Oct 2017 |
[2017] EWHC 2574 (TCC)
An architect retained to provide a full design service must identify and take account of the client’s key requirements and constraints, including the project…
|
|
| 12 Oct 2017 |
[2017] EWHC 2849 (TCC)
An adjudicator’s decision is binding on an interim basis and will ordinarily be enforced summarily, even where the adjudicator may have made an error of fact…
|
|
| 11 Oct 2017 |
[2017] EWHC 2450 (TCC)
Part 8 is appropriate only where the question is unlikely to involve a substantial dispute of fact and is framed with sufficient precision to permit a precise…
|
8 |
| 6 Oct 2017 |
[2017] EWHC 2472 (TCC)
Indemnity costs require conduct that is unreasonable to a high degree and takes the case out of the norm. A weak but arguable claim will not usually suffice…
|
5 |
| 5 Oct 2017 |
[2017] EWHC 2456 (TCC)
Under the Scheme for Construction Contracts, an adjudicator’s appointment is time-limited. The power to resign “at any time” ends when the applicable deadline…
|
|
| 2 Oct 2017 |
[2017] EWHC 2414 (TCC)
Parties may agree how concurrent delay is to affect extensions of time, subject to statutory restrictions that do not apply to the agreed allocation of delay…
|
|
| 29 Sep 2017 |
[2017] EWHC 2395 (TCC)
A party may unilaterally withdraw a dispute from adjudication and refer the same, or substantially the same, dispute to a further adjudication. The absence of…
|
1 |
| 29 Sep 2017 |
[2017] EWHC 2394 (TCC)
An extension of time to challenge an arbitration award is exceptional. The court must give substantial weight to the statutory policy of speedy finality and…
|
|
| 8 Sep 2017 |
[2017] EWHC 2425 (TCC)
Where a valid payment notice has been given and no pay less notice served, the sum identified by an adjudicator is payable and must be enforced. Alleged…
|
|
| 8 Sep 2017 |
[2017] EWHC 2392 (TCC)
In a procurement challenge, a claimant must plead its case within the short timetable required by the Civil Procedure Rules 1998. An application for more time…
|
1 |
| 31 Aug 2017 |
[2017] EWHC 2197 (TCC)
Reliance damages compensate for the loss of the contractual bargain and are not necessarily claims for lost profits, revenue or savings. Wasted expenditure may…
|
4 |
| 30 Aug 2017 |
[2017] EWHC 2196 (TCC)
A contractual provision is void for uncertainty only where the court cannot identify the parties’ objective agreement or cannot safely prefer one equally…
|
2 |
| 23 Aug 2017 |
[2017] EWHC 2178 (TCC)
Where contractual documents are expressly incorporated into a principal agreement, they will ordinarily form part of one contractual scheme. Payment provisions…
|
|
| 2 Aug 2017 |
[2017] EWHC 2130 (TCC)
Relief from sanctions for late service of a costs budget requires application of the three-stage Denton v TH White Ltd approach. A ten-day delay is capable of…
|
1 |
| 26 Jul 2017 |
[2017] EWHC 2299 (TCC)
The court may determine liability-trial costs before the final resolution of split litigation where the parties need certainty and the costs can fairly be…
|
|
| 26 Jul 2017 |
[2017] EWHC 1889 (TCC)
Summary judgment should be refused where the defendant has an arguable defence and the court cannot conclude that there is no real prospect of successfully…
|
|
| 25 Jul 2017 |
[2017] EWHC 1781 (TCC)
An adjudicator’s agreement may arise by conduct where a party participates in an adjudication and thereby requests the adjudicator to act, even while…
|
|
| 21 Jul 2017 |
[2017] EWHC 1867 (TCC)
Where a procurement claim is subject to the time limits in regulation 92 of the Public Contracts Regulations 2015, the court may extend time by up to three…
|
4 |
| 21 Jul 2017 |
[2017] EWHC 1824 (TCC)
On an application to lift an automatic procurement suspension, the court applies the American Cyanamid Co v Ethicon Limited [1975] AC 396 approach. Once there…
|
11 |
| 21 Jul 2017 |
[2017] EWHC 1813 (TCC)
A retrospective application for an extension of time to serve a document is governed by the same principles as an application for relief from sanctions. The…
|
|
| 14 Jul 2017 |
[2017] EWHC 25 (TCC)
A design-and-build contract may impose several cumulative obligations concerning the same materials. Compliance with a specified testing standard does not…
|
2 |
| 14 Jul 2017 |
[2017] EWHC 2082 (TCC)
Section 2 of the Third Parties (Rights against Insurers) Act 2010 is engaged where a claimant claims transferred rights against an insurer, even though the…
|
|
| 12 Jul 2017 |
[2017] EWHC 1763 (TCC)
Under an NEC3 construction contract, the employer could not impose a more stringent welding and testing standard than the parties had agreed. Defects had to be…
|
6 |
| 12 Jul 2017 |
[2017] EWHC 1667 (TCC)
A monitoring surveyor’s duty is to exercise the skill and care reasonably expected of a competent monitoring surveyor in the circumstances. The duty commonly…
|
4 |
| 4 Jul 2017 |
[2017] EWHC 1579 (TCC)
An application to lift a stay is governed by the overriding objective and the requirements of justice. The applicant bears the burden of showing that lifting…
|
1 |
| 29 Jun 2017 |
[2017] EWHC 1555 (TCC)
On an interlocutory limitation application, claims should be struck out only where it is plain and obvious that they are statute-barred. A standstill agreement…
|
2 |
| 27 Jun 2017 |
[2017] EWHC 1521 (TCC)
On an application to lift an automatic suspension in procurement proceedings, the court applies the American Cyanamid principles flexibly and asks whether it…
|
5 |
| 26 Jun 2017 |
[2017] EWHC 1486 (TCC)
For tort claims based on fraud, limitation is postponed only until the claimant discovers the precise deceit relied on, or could have discovered it with…
|
|
| 23 Jun 2017 |
[2017] EWHC 1523 (TCC)
For summary judgment, a set-off or counterclaim does not automatically prevent relief. The court must assess whether the defence has a realistic prospect of…
|
1 |
| 23 Jun 2017 |
[2017] EWHC 1500 (TCC)
Extensions of time for challenging an arbitration award are exceptional. The applicant must explain the delay, and delay measured against the statutory 28-day…
|
1 |
| 21 Jun 2017 |
[2017] EWHC 1438 (TCC)
Service of adjudication documents under the Scheme incorporated into a construction contract does not require proof that the recipient actually read or became…
|
|
| 21 Jun 2017 |
[2017] EWHC 1405 (TCC)
In adjudication, the scope of the dispute is determined principally by the notice, read with the relevant background and the first adjudicator’s actual…
|
1 |
| 16 Jun 2017 |
[2017] EWHC 1353 (TCC)
Under section 7(2) of the Party Wall etc. Act 1996, compensation for loss or damage caused by authorised works is assessed by applying ordinary common-law…
|
1 |
| 15 Jun 2017 |
[2017] EWHC 1406 (TCC)
There is no general rule that an application for specific disclosure must, or must not, be heard before an application to lift the automatic suspension in…
|
|
| 8 Jun 2017 |
[2017] EWHC 1364 (TCC)
An oral agreement for waste-removal services may bind a company rather than its owner where the surrounding circumstances, invoicing and payment arrangements…
|
|
| 6 Jun 2017 |
[2017] EWHC 1584 (TCC)
Early disclosure in a procurement challenge must enable an aggrieved tenderer to understand the evaluation actually carried out and to plead its case properly.…
|
1 |
| 31 May 2017 |
[2017] EWHC 1309 (TCC)
A statutory compensation scheme may be the exclusive remedy for injury caused by authorised works, including injury amounting to negligence or nuisance. The…
|
1 |
| 25 May 2017 |
[2017] EWHC 1289 (TCC)
In construing a construction subcontract, the court must ascertain the objective meaning of the language used by reading the contract as a whole. It must…
|
|
| 22 May 2017 |
[2017] EWHC 1509 (TCC)
A court order requiring insurance must be obeyed within the specified time. Difficulties in obtaining access, undertaking remedial works or securing insurance…
|
|
| 19 May 2017 |
[2017] EWHC 1223 (TCC)
When deciding an application to set aside a regularly entered default judgment, the court must first consider whether the defendant has a real prospect of…
|
5 |
| 18 May 2017 |
[2017] EWHC 1148 (TCC)
Service of a claim form and particulars of claim is a reserved legal activity because it forms part of the prosecution of proceedings and is a formal step…
|
2 |
| 12 May 2017 |
[2017] EWHC 1108 (TCC)
Cost budgeting is not a tactical exercise. A party must provide realistic and justified figures when commenting on the opposing party’s budget in Precedent R.…
|
1 |
| 11 May 2017 |
[2017] EWHC 1066 (TCC)
A party to an adjudication cannot ordinarily approbate and reprobate the adjudicator’s decision. Where, without an express reservation of rights, it invites…
|
1 |
| 26 Apr 2017 |
[2017] EWHC 876 (TCC)
Pre-action disclosure under CPR rule 31.16 remains discretionary even where the jurisdictional threshold is satisfied. The existence of the information regime…
|
|
| 11 Apr 2017 |
[2017] EWHC 558 (TCC)
Under an all-risks buildings policy, the insured must prove that loss resulted from a covered event. Accidental damage requires a chance, non-deliberate and…
|
2 |
| 7 Apr 2017 |
[2017] EWHC 767 (TCC)
A wide exclusion clause in a commercial contract may satisfy the reasonableness requirement under the Unfair Contract Terms Act 1977 where the parties have…
|
|
| 5 Apr 2017 |
[2017] EWHC 723 (TCC)
An adjudicator’s jurisdiction is defined by the dispute identified in the notice, read with the referral, the parties’ pre-adjudication assertions, pleadings…
|
3 |
| 4 Apr 2017 |
[2017] EWHC 715 (TCC)
An adjudicator under Housing Grants Construction Regeneration Act 1996 may determine a single dispute arising from one construction contract, even where the…
|
|
| 24 Mar 2017 |
[2017] EWHC 575 (TCC)
Public procurement proceedings are not private merely because they involve commercially sensitive information. The court starts from open justice and public…
|
1 |
| 16 Mar 2017 |
[2017] EWHC 517 (TCC)
An adjudicator’s decision within jurisdiction and reached in broad accordance with natural justice must ordinarily be enforced, despite errors of fact or law.…
|
24 |
| 16 Mar 2017 |
[2017] EWHC 472 (TCC)
Under Arbitration Act 1996, s 68(2)(g), a challenge based on fraud requires cogent evidence of dishonest, reprehensible or unconscionable conduct that…
|
2 |
| 10 Mar 2017 |
[2017] EWHC 464 (TCC)
Where a claimant fails to beat a defendant’s Part 36 offer, the ordinary costs consequences do not automatically justify indemnity costs. The court must…
|
|
| 10 Mar 2017 |
[2017] EWHC 348 (TCC)
Under section 68(2)(d) of the Arbitration Act 1996, a serious irregularity requires a tribunal to have failed to deal with an essential issue that was put to…
|
3 |
| 9 Mar 2017 |
[2017] EWHC 460 (TCC)
Under Civil Procedure Rules 1998, r 44.2, the unsuccessful party will ordinarily pay the successful party’s costs. Departure from that rule requires…
|
|
| 8 Mar 2017 |
[2017] EWHC 914 (TCC)
On an application to strike out, a claim should proceed where it has a real, rather than fanciful, prospect of success. The court should avoid a mini-trial and…
|
|
| 2 Mar 2017 |
[2017] EWHC 343 (TCC)
An actionable interference with a private right of way must be substantial. The question is whether the way can be used substantially as conveniently as when…
|
|
| 28 Feb 2017 |
[2017] EWHC 319 (TCC)
An arbitration agreement is not rendered inoperative merely because parties engage in pre-action correspondence or a court protocol. Abandonment requires an…
|
2 |
| 23 Feb 2017 |
[2017] EWHC 275 (TCC)
On an application for an interim payment, the court must be satisfied on the balance of probabilities that, on the evidence presently available, the claimant…
|
|
| 22 Feb 2017 |
[2017] EWHC 239 (TCC)
Rectification may correct a written contract where the parties shared a continuing intention, expressed that intention outwardly, and the instrument failed to…
|
|
| 17 Feb 2017 |
[2017] EWHC 238 (TCC)
Whether to expedite a procurement challenge is a discretionary case-management decision. The court must assess objective urgency, the procedural history, the…
|
2 |
| 16 Feb 2017 |
[2017] EWHC 189 (TCC)
Under a software licence, authorised use is determined by the contract’s express usage and pricing provisions. Where usage of an integrated system involves…
|
|
| 15 Feb 2017 |
[2017] EWHC 218 (TCC)
The strict approach to confidential information in Prince Jeffri Bolkiah v KPMG does not automatically prevent an expert from later giving evidence for the…
|
1 |
| 14 Feb 2017 |
[2017] EWHC 197 (TCC)
In a dilapidations claim, damages for breach of repairing covenants are capped by the diminution in the value of the reversion under Landlord and Tenant Act…
|
|
| 1 Feb 2017 |
[2017] EWHC 67 (TCC)
An equitable assignment of future contractual rights can arise when the rights come into existence, provided the rights are sufficiently identifiable. Whether…
|
3 |
| 26 Jan 2017 |
[2017] EWHC 87 (TCC)
A contractual liability cap is construed as part of the parties’ commercial allocation of risk. No special restrictive rules apply, but the cap must be clear…
|
|
| 23 Jan 2017 |
[2017] EWHC 62 (TCC)
A statutory sewerage undertaker may owe a common-law duty where its positive act creates a foreseeable risk of flooding, provided the claim does not merely…
|
2 |
| 19 Jan 2017 |
[2017] EWHC 61 (TCC)
A court may permit proceedings to continue during an insolvency moratorium where the applicant shows that the statutory purpose will not be prejudiced, the…
|
1 |
| 18 Jan 2017 |
[2017] EWHC 30 (TCC)
Under Civil Procedure Rules 1998, the unsuccessful party usually pays the successful party’s costs, but the court retains a broad discretion having regard to…
|
|
| 18 Jan 2017 |
[2017] EWHC 15 (TCC)
An interim payment application under a construction contract is valid if it is clearly identifiable, states the sum claimed and gives the basis of calculation.…
|
9 |
| 13 Jan 2017 |
[2017] EWHC 29 (TCC)
A late request for further information should not be refused solely because of delay where it concerns an issue relevant to the fair disposal of the trial and…
|
|
| 13 Jan 2017 |
[2017] EWHC 17 (TCC)
Construction payment notices must be construed objectively in their contractual and factual setting. An interim payment notice is valid where, in substance…
|
3 |