High Court: Technology and Construction Court judgments, 2017

85 judgments, newest first. Open any case for its summary, the legal points it decides and how later courts have treated it.

Date Case Cited by
21 Dec 2017
[2017] EWHC 3389 (TCC)
In a regulated procurement, tender documents must state the evaluation criteria and the consequences of failing a criterion with sufficient clarity to permit…
6
20 Dec 2017
[2017] EWHC 3286 (TCC)
A performance bond drafted as secondary liability may nevertheless create liability for an unpaid contractual debt arising after the contractor’s insolvency. A…
3
12 Dec 2017
[2017] EWHC 3235 (TCC)
Where a construction contract provides that a notified figure becomes binding unless challenged within a specified period, the notice must clearly identify the…
1
7 Dec 2017
[2017] EWHC 3173 (TCC)
Contractual provisions must be interpreted objectively, by considering the natural and usual meaning of the language in its contractual and commercial context.…
1
6 Dec 2017
[2017] EWHC 3092 (TCC)
An appellate court will interfere with a case-management decision where the first-instance judge erred in law, failed to consider relevant matters, or reached…
30 Nov 2017
[2017] EWHC 3073 (TCC)
A contractual obligation is an indemnity, rather than a guarantee, where its proper construction imposes a primary obligation on the promisor, even if the…
2
30 Nov 2017
[2017] EWHC 3055 (TCC)
A challenge under section 67 of the Arbitration Act 1996 concerns substantive jurisdiction, not the correctness of a tribunal’s decision on contractual…
29 Nov 2017
[2017] EWHC 3066 (TCC)
Where a construction contract contains a sufficiently broad extension-of-time mechanism, delay caused by prevention, late possession and variations should…
28 Nov 2017
[2017] EWHC 3046 (TCC)
Where Civil Procedure Rules 1998, rule 3.13 permits the court to order otherwise, a written timetable issued by the court office may constitute such an order.…
28 Nov 2017
[2017] EWHC 2979 (TCC)
A modifying agreement must be construed in its contractual context. An obligation to use “fullest endeavours” to achieve a stage by a date is not an absolute…
9 Nov 2017
[2017] EWHC 2829 (TCC)
A supplier of hired electrical equipment may owe continuing contractual and statutory obligations where the agreement requires equipment to remain available…
1
2 Nov 2017
[2017] EWHC 2751 (TCC)
Substitution of a defendant is appropriate where the wrong party was joined because of that party’s conduct and substitution enables the real dispute to be…
31 Oct 2017
[2017] EWHC 2667 (TCC)
In a public procurement challenge, a contracting authority is required to seek clarification only in exceptional or limited circumstances. The tender must…
2
31 Oct 2017
[2017] EWHC 2633 (TCC)
Where a contractual termination power is expressly made subject to a further clause, that clause may operate as a condition precedent to termination. The…
18 Oct 2017
[2017] EWHC 2574 (TCC)
An architect retained to provide a full design service must identify and take account of the client’s key requirements and constraints, including the project…
12 Oct 2017
[2017] EWHC 2849 (TCC)
An adjudicator’s decision is binding on an interim basis and will ordinarily be enforced summarily, even where the adjudicator may have made an error of fact…
11 Oct 2017
[2017] EWHC 2450 (TCC)
Part 8 is appropriate only where the question is unlikely to involve a substantial dispute of fact and is framed with sufficient precision to permit a precise…
8
6 Oct 2017
[2017] EWHC 2472 (TCC)
Indemnity costs require conduct that is unreasonable to a high degree and takes the case out of the norm. A weak but arguable claim will not usually suffice…
5
5 Oct 2017
[2017] EWHC 2456 (TCC)
Under the Scheme for Construction Contracts, an adjudicator’s appointment is time-limited. The power to resign “at any time” ends when the applicable deadline…
2 Oct 2017
[2017] EWHC 2414 (TCC)
Parties may agree how concurrent delay is to affect extensions of time, subject to statutory restrictions that do not apply to the agreed allocation of delay…
29 Sep 2017
[2017] EWHC 2395 (TCC)
A party may unilaterally withdraw a dispute from adjudication and refer the same, or substantially the same, dispute to a further adjudication. The absence of…
1
29 Sep 2017
[2017] EWHC 2394 (TCC)
An extension of time to challenge an arbitration award is exceptional. The court must give substantial weight to the statutory policy of speedy finality and…
8 Sep 2017
[2017] EWHC 2425 (TCC)
Where a valid payment notice has been given and no pay less notice served, the sum identified by an adjudicator is payable and must be enforced. Alleged…
8 Sep 2017
[2017] EWHC 2392 (TCC)
In a procurement challenge, a claimant must plead its case within the short timetable required by the Civil Procedure Rules 1998. An application for more time…
1
31 Aug 2017
[2017] EWHC 2197 (TCC)
Reliance damages compensate for the loss of the contractual bargain and are not necessarily claims for lost profits, revenue or savings. Wasted expenditure may…
4
30 Aug 2017
[2017] EWHC 2196 (TCC)
A contractual provision is void for uncertainty only where the court cannot identify the parties’ objective agreement or cannot safely prefer one equally…
2
23 Aug 2017
[2017] EWHC 2178 (TCC)
Where contractual documents are expressly incorporated into a principal agreement, they will ordinarily form part of one contractual scheme. Payment provisions…
2 Aug 2017
[2017] EWHC 2130 (TCC)
Relief from sanctions for late service of a costs budget requires application of the three-stage Denton v TH White Ltd approach. A ten-day delay is capable of…
1
26 Jul 2017
[2017] EWHC 2299 (TCC)
The court may determine liability-trial costs before the final resolution of split litigation where the parties need certainty and the costs can fairly be…
26 Jul 2017
[2017] EWHC 1889 (TCC)
Summary judgment should be refused where the defendant has an arguable defence and the court cannot conclude that there is no real prospect of successfully…
25 Jul 2017
[2017] EWHC 1781 (TCC)
An adjudicator’s agreement may arise by conduct where a party participates in an adjudication and thereby requests the adjudicator to act, even while…
21 Jul 2017
[2017] EWHC 1867 (TCC)
Where a procurement claim is subject to the time limits in regulation 92 of the Public Contracts Regulations 2015, the court may extend time by up to three…
4
21 Jul 2017
[2017] EWHC 1824 (TCC)
On an application to lift an automatic procurement suspension, the court applies the American Cyanamid Co v Ethicon Limited [1975] AC 396 approach. Once there…
11
21 Jul 2017
[2017] EWHC 1813 (TCC)
A retrospective application for an extension of time to serve a document is governed by the same principles as an application for relief from sanctions. The…
14 Jul 2017
[2017] EWHC 25 (TCC)
A design-and-build contract may impose several cumulative obligations concerning the same materials. Compliance with a specified testing standard does not…
2
14 Jul 2017
[2017] EWHC 2082 (TCC)
Section 2 of the Third Parties (Rights against Insurers) Act 2010 is engaged where a claimant claims transferred rights against an insurer, even though the…
12 Jul 2017
[2017] EWHC 1763 (TCC)
Under an NEC3 construction contract, the employer could not impose a more stringent welding and testing standard than the parties had agreed. Defects had to be…
6
12 Jul 2017
[2017] EWHC 1667 (TCC)
A monitoring surveyor’s duty is to exercise the skill and care reasonably expected of a competent monitoring surveyor in the circumstances. The duty commonly…
4
4 Jul 2017
[2017] EWHC 1579 (TCC)
An application to lift a stay is governed by the overriding objective and the requirements of justice. The applicant bears the burden of showing that lifting…
1
29 Jun 2017
[2017] EWHC 1555 (TCC)
On an interlocutory limitation application, claims should be struck out only where it is plain and obvious that they are statute-barred. A standstill agreement…
2
27 Jun 2017
[2017] EWHC 1521 (TCC)
On an application to lift an automatic suspension in procurement proceedings, the court applies the American Cyanamid principles flexibly and asks whether it…
5
26 Jun 2017
[2017] EWHC 1486 (TCC)
For tort claims based on fraud, limitation is postponed only until the claimant discovers the precise deceit relied on, or could have discovered it with…
23 Jun 2017
[2017] EWHC 1523 (TCC)
For summary judgment, a set-off or counterclaim does not automatically prevent relief. The court must assess whether the defence has a realistic prospect of…
1
23 Jun 2017
[2017] EWHC 1500 (TCC)
Extensions of time for challenging an arbitration award are exceptional. The applicant must explain the delay, and delay measured against the statutory 28-day…
1
21 Jun 2017
[2017] EWHC 1438 (TCC)
Service of adjudication documents under the Scheme incorporated into a construction contract does not require proof that the recipient actually read or became…
21 Jun 2017
[2017] EWHC 1405 (TCC)
In adjudication, the scope of the dispute is determined principally by the notice, read with the relevant background and the first adjudicator’s actual…
1
16 Jun 2017
[2017] EWHC 1353 (TCC)
Under section 7(2) of the Party Wall etc. Act 1996, compensation for loss or damage caused by authorised works is assessed by applying ordinary common-law…
1
15 Jun 2017
[2017] EWHC 1406 (TCC)
There is no general rule that an application for specific disclosure must, or must not, be heard before an application to lift the automatic suspension in…
8 Jun 2017
[2017] EWHC 1364 (TCC)
An oral agreement for waste-removal services may bind a company rather than its owner where the surrounding circumstances, invoicing and payment arrangements…
6 Jun 2017
[2017] EWHC 1584 (TCC)
Early disclosure in a procurement challenge must enable an aggrieved tenderer to understand the evaluation actually carried out and to plead its case properly.…
1
31 May 2017
[2017] EWHC 1309 (TCC)
A statutory compensation scheme may be the exclusive remedy for injury caused by authorised works, including injury amounting to negligence or nuisance. The…
1
25 May 2017
[2017] EWHC 1289 (TCC)
In construing a construction subcontract, the court must ascertain the objective meaning of the language used by reading the contract as a whole. It must…
22 May 2017
[2017] EWHC 1509 (TCC)
A court order requiring insurance must be obeyed within the specified time. Difficulties in obtaining access, undertaking remedial works or securing insurance…
19 May 2017
[2017] EWHC 1223 (TCC)
When deciding an application to set aside a regularly entered default judgment, the court must first consider whether the defendant has a real prospect of…
5
18 May 2017
[2017] EWHC 1148 (TCC)
Service of a claim form and particulars of claim is a reserved legal activity because it forms part of the prosecution of proceedings and is a formal step…
2
12 May 2017
[2017] EWHC 1108 (TCC)
Cost budgeting is not a tactical exercise. A party must provide realistic and justified figures when commenting on the opposing party’s budget in Precedent R.…
1
11 May 2017
[2017] EWHC 1066 (TCC)
A party to an adjudication cannot ordinarily approbate and reprobate the adjudicator’s decision. Where, without an express reservation of rights, it invites…
1
26 Apr 2017
[2017] EWHC 876 (TCC)
Pre-action disclosure under CPR rule 31.16 remains discretionary even where the jurisdictional threshold is satisfied. The existence of the information regime…
11 Apr 2017
[2017] EWHC 558 (TCC)
Under an all-risks buildings policy, the insured must prove that loss resulted from a covered event. Accidental damage requires a chance, non-deliberate and…
2
7 Apr 2017
[2017] EWHC 767 (TCC)
A wide exclusion clause in a commercial contract may satisfy the reasonableness requirement under the Unfair Contract Terms Act 1977 where the parties have…
5 Apr 2017
[2017] EWHC 723 (TCC)
An adjudicator’s jurisdiction is defined by the dispute identified in the notice, read with the referral, the parties’ pre-adjudication assertions, pleadings…
3
4 Apr 2017
[2017] EWHC 715 (TCC)
An adjudicator under Housing Grants Construction Regeneration Act 1996 may determine a single dispute arising from one construction contract, even where the…
24 Mar 2017
[2017] EWHC 575 (TCC)
Public procurement proceedings are not private merely because they involve commercially sensitive information. The court starts from open justice and public…
1
16 Mar 2017
[2017] EWHC 517 (TCC)
An adjudicator’s decision within jurisdiction and reached in broad accordance with natural justice must ordinarily be enforced, despite errors of fact or law.…
24
16 Mar 2017
[2017] EWHC 472 (TCC)
Under Arbitration Act 1996, s 68(2)(g), a challenge based on fraud requires cogent evidence of dishonest, reprehensible or unconscionable conduct that…
2
10 Mar 2017
[2017] EWHC 464 (TCC)
Where a claimant fails to beat a defendant’s Part 36 offer, the ordinary costs consequences do not automatically justify indemnity costs. The court must…
10 Mar 2017
[2017] EWHC 348 (TCC)
Under section 68(2)(d) of the Arbitration Act 1996, a serious irregularity requires a tribunal to have failed to deal with an essential issue that was put to…
3
9 Mar 2017
[2017] EWHC 460 (TCC)
Under Civil Procedure Rules 1998, r 44.2, the unsuccessful party will ordinarily pay the successful party’s costs. Departure from that rule requires…
8 Mar 2017
[2017] EWHC 914 (TCC)
On an application to strike out, a claim should proceed where it has a real, rather than fanciful, prospect of success. The court should avoid a mini-trial and…
2 Mar 2017
[2017] EWHC 343 (TCC)
An actionable interference with a private right of way must be substantial. The question is whether the way can be used substantially as conveniently as when…
28 Feb 2017
[2017] EWHC 319 (TCC)
An arbitration agreement is not rendered inoperative merely because parties engage in pre-action correspondence or a court protocol. Abandonment requires an…
2
23 Feb 2017
[2017] EWHC 275 (TCC)
On an application for an interim payment, the court must be satisfied on the balance of probabilities that, on the evidence presently available, the claimant…
22 Feb 2017
[2017] EWHC 239 (TCC)
Rectification may correct a written contract where the parties shared a continuing intention, expressed that intention outwardly, and the instrument failed to…
17 Feb 2017
[2017] EWHC 238 (TCC)
Whether to expedite a procurement challenge is a discretionary case-management decision. The court must assess objective urgency, the procedural history, the…
2
16 Feb 2017
[2017] EWHC 189 (TCC)
Under a software licence, authorised use is determined by the contract’s express usage and pricing provisions. Where usage of an integrated system involves…
15 Feb 2017
[2017] EWHC 218 (TCC)
The strict approach to confidential information in Prince Jeffri Bolkiah v KPMG does not automatically prevent an expert from later giving evidence for the…
1
14 Feb 2017
[2017] EWHC 197 (TCC)
In a dilapidations claim, damages for breach of repairing covenants are capped by the diminution in the value of the reversion under Landlord and Tenant Act…
1 Feb 2017
[2017] EWHC 67 (TCC)
An equitable assignment of future contractual rights can arise when the rights come into existence, provided the rights are sufficiently identifiable. Whether…
3
26 Jan 2017
[2017] EWHC 87 (TCC)
A contractual liability cap is construed as part of the parties’ commercial allocation of risk. No special restrictive rules apply, but the cap must be clear…
23 Jan 2017
[2017] EWHC 62 (TCC)
A statutory sewerage undertaker may owe a common-law duty where its positive act creates a foreseeable risk of flooding, provided the claim does not merely…
2
19 Jan 2017
[2017] EWHC 61 (TCC)
A court may permit proceedings to continue during an insolvency moratorium where the applicant shows that the statutory purpose will not be prejudiced, the…
1
18 Jan 2017
[2017] EWHC 30 (TCC)
Under Civil Procedure Rules 1998, the unsuccessful party usually pays the successful party’s costs, but the court retains a broad discretion having regard to…
18 Jan 2017
[2017] EWHC 15 (TCC)
An interim payment application under a construction contract is valid if it is clearly identifiable, states the sum claimed and gives the basis of calculation.…
9
13 Jan 2017
[2017] EWHC 29 (TCC)
A late request for further information should not be refused solely because of delay where it concerns an issue relevant to the fair disposal of the trial and…
13 Jan 2017
[2017] EWHC 17 (TCC)
Construction payment notices must be construed objectively in their contractual and factual setting. An interim payment notice is valid where, in substance…
3