| Date | Case | Cited by |
|---|---|---|
| 19 Dec 2014 |
[2014] EWHC 4375 (TCC)
Section 68(2)(d) of the Arbitration Act 1996 addresses serious procedural failures, not whether an arbitral tribunal reached the correct legal or factual…
|
17 |
| 17 Dec 2014 |
[2014] EWHC 4651 (TCC)
On an application to lift the automatic suspension in a public procurement challenge, the court applies the American Cyanamid approach. The claimant must show…
|
|
| 17 Dec 2014 |
[2014] EWHC 4250 (TCC)
An adjudicator must consider substantive defences properly raised by a responding party, including defences not advanced before the adjudication. The…
|
1 |
| 15 Dec 2014 |
[2014] EWHC 4195 (TCC)
For the purposes of the Housing Grants, Construction and Regeneration Act 1996, substantial plant or machinery installed in a building may constitute…
|
3 |
| 12 Dec 2014 |
[2014] EWHC 4796 (TCC)
A contractual procedure requiring an engineer’s decision before arbitration may operate as a condition precedent to arbitral jurisdiction. The condition…
|
|
| 12 Dec 2014 |
[2014] EWHC 4109 (TCC)
Costs incurred in enforcing an adjudicator’s award must be assessed by reference to reasonableness and proportionality. The court should consider the nature…
|
|
| 3 Dec 2014 |
[2014] EWHC 4007 (TCC)
Under a construction contract providing interim payments through a defined notice regime, the contractor’s entitlement during the project arises only through…
|
14 |
| 3 Dec 2014 |
[2014] EWHC 4006 (TCC)
Adjudication provisions in a main contract are not incorporated into a subcontract merely because the subcontract incorporates obligations flowing down the…
|
|
| 28 Nov 2014 |
[2014] EWHC 3968 (TCC)
Under section 1 of the Defective Premises Act 1972, a dwelling is assessed at completion by reference to contemporary standards. Fitness for habitation…
|
7 |
| 28 Nov 2014 |
[2014] EWHC 3933 (TCC)
A manufacturer of a safety device owes a duty to take reasonable care where the device is supplied for use in a foreseeable safety-critical application. That…
|
1 |
| 25 Nov 2014 |
[2014] EWHC 3898 (TCC)
A construction contract may be binding before execution of a formal document if the parties’ words and conduct objectively show agreement on the terms…
|
|
| 21 Nov 2014 |
[2014] EWHC 3847 (TCC)
Costs following a Part 8 claim should reflect the parties’ overall success and the costs generated by particular issues. A purely issue-based order is…
|
|
| 21 Nov 2014 |
[2014] EWHC 3825 (TCC)
A payment notice regime is intended to secure prompt payment in construction disputes. The absence of a Pay Less Notice does not necessarily determine the…
|
|
| 21 Nov 2014 |
[2014] EWHC 3824 (TCC)
For the purposes of the prohibition on repeat adjudications, the relevant comparison is between the dispute and decision actually determined, not every issue…
|
3 |
| 20 Nov 2014 |
[2014] EWHC 3863 (TCC)
The court has a broad discretion to order a losing party to pay the reasonable costs of an interested party. A separate costs order may be justified where that…
|
2 |
| 12 Nov 2014 |
[2014] EWHC 3728 (TCC)
Regulation 30 of the Utilities Contracts Regulations 2006 does not impose a general duty on a utility to investigate every tender which appears unusually low…
|
1 |
| 7 Nov 2014 |
[2014] EWHC 3710 (TCC)
A fraudulent representation made in an application to an adjudicator-nominating body may invalidate the nomination and deprive the adjudicator of jurisdiction.…
|
5 |
| 5 Nov 2014 |
[2014] EWHC 3659 (TCC)
Applications to lift the automatic suspension of a public procurement contract are governed by the American Cyanamid approach. The court should first ask…
|
5 |
| 30 Oct 2014 |
[2014] EWHC 3584 (TCC)
Where a contractual obligation to provide a performance bond has become practically impossible to perform in its original form, the court may, in an…
|
|
| 29 Oct 2014 |
[2014] EWHC 3546 (TCC)
In substantial TCC litigation, the court should ordinarily facilitate ADR through a sensible trial timetable rather than impose a lengthy stay or dedicated ADR…
|
5 |
| 24 Oct 2014 |
[2014] EWHC 3491 (TCC)
Challenges to enforcement of an adjudicator’s decision should succeed only in the plainest cases, where the adjudicator decided a question not referred or…
|
1 |
| 21 Oct 2014 |
[2014] EWHC 4525 (TCC)
An adjudicator’s decision may be enforced despite mistakes of fact or law, including inadvertent procedural errors, unless the error amounts to a sufficiently…
|
1 |
| 17 Oct 2014 |
[2014] EWHC 3380 (TCC)
In adjudication enforcement proceedings, jurisdiction is determined primarily by the Notice of Adjudication, read with the dispute which had crystallised and…
|
|
| 14 Oct 2014 |
[2014] EWHC 3401 (TCC)
In procurement challenges, early specific disclosure should ordinarily provide the essential information and documents needed to assess whether the evaluation…
|
|
| 13 Oct 2014 |
[2014] EWHC 3729 (TCC)
A settlement agreement is assessed objectively. An offer to discontinue proceedings may be accepted by the other party’s payment of the specified sum. A…
|
|
| 10 Oct 2014 |
[2014] EWHC 3243 (TCC)
The court has jurisdiction under Senior Courts Act 1981, section 51, to order a non-party to pay litigation costs. The discretion is exceptional but…
|
1 |
| 10 Oct 2014 |
[2014] EWHC 3193 (TCC)
A contractual dispute resolution clause must be construed so that its adjudication machinery has practical effect. Under the FIDIC provisions considered, a…
|
|
| 9 Oct 2014 |
[2014] EWHC 3675 (TCC)
On an interim injunction application, the court should avoid making final findings on serious, fact-dependent allegations where the evidence is disputed, the…
|
|
| 9 Oct 2014 |
[2014] EWHC 3191 (TCC)
In public procurement, a contracting authority must evaluate tenders objectively, transparently and equally, using disclosed criteria directed to identifying…
|
|
| 3 Oct 2014 |
[2014] EWHC 3148 (TCC)
Refusal to mediate may be unreasonable even where a party reasonably considers that it has a strong case. The court should assess the nature and merits of the…
|
2 |
| 2 Oct 2014 |
[2014] EWHC 3133 (TCC)
Applications to lift an automatic suspension under the Utilities Contracts Regulations 2006 are governed by the two-stage approach in American Cyanamid Co v…
|
12 |
| 23 Sep 2014 |
[2014] EWHC 3042 (TCC)
A third party entitled to enforce contractual terms under the Contracts (Rights of Third Parties) Act 1999 is not thereby entitled to invoke a contractual…
|
4 |
| 8 Sep 2014 |
[2014] EWHC 2956 (TCC)
For a claim under the Consumer Protection Act 1987, a claimant need prove a defect in broad terms; precise identification of the defect is unnecessary. The…
|
|
| 8 Sep 2014 |
[2014] EWHC 2955 (TCC)
Where one commercial agreement is stated to be governed by the terms of another, the referenced terms ordinarily regulate and are incorporated into the later…
|
1 |
| 27 Aug 2014 |
[2014] EWHC 2886 (TCC)
In exercising the discretion on costs, the court must consider all the circumstances, including the parties’ conduct and their relative success on particular…
|
6 |
| 6 Aug 2014 |
[2014] EWHC 2786 (TCC)
In multi-party proceedings, the court has a broad discretion as to costs. It may order an unsuccessful defendant to pay costs incurred in pursuing another…
|
|
| 1 Aug 2014 |
[2014] EWHC 2741 (TCC)
On an application to lift the automatic suspension of a public procurement contract, the court applies the American Cyanamid approach. It asks whether there is…
|
1 |
| 1 Aug 2014 |
[2014] EWHC 2725 (TCC)
Manufacturers of equipment for potentially explosive atmospheres must address foreseeable operating conditions and reasonably anticipated misuse, including…
|
|
| 1 Aug 2014 |
[2014] EWHC 2677 (TCC)
A landlord’s obligations under separate lease schedules may be cumulative. An insurance-reinstatement clause does not restrict a broader obligation to make…
|
|
| 30 Jul 2014 |
[2014] EWHC 2604 (TCC)
Security for costs is discretionary. The court must balance the claimant’s ability to pursue a proper claim against the defendant’s risk of unrecovered costs…
|
4 |
| 28 Jul 2014 |
[2014] EWHC 2595 (TCC)
Where a contract makes practical completion depend on specified completion criteria, the certifier must apply those criteria. A technical or minor departure…
|
|
| 18 Jul 2014 |
[2014] EWHC 2430 (TCC)
An insurance policy protecting purchasers against loss of deposits engages when the developer enters bankruptcy, liquidation or dissolution and has failed to…
|
|
| 10 Jul 2014 |
[2014] EWHC 2217 (TCC)
A valuer is liable only for loss falling within the scope of the duty undertaken. In a lending case, the lender must distinguish loss caused by the valuation…
|
1 |
| 8 Jul 2014 |
[2014] EWHC 2458 (TCC)
A consent order is treated like a judgment, but it determines only the issues actually determined by its terms and necessary effect. It does not automatically…
|
|
| 4 Jul 2014 |
[2014] EWHC 2170 (TCC)
Issue-based costs orders should be made only where the circumstances require them. The court should begin with the general rule that costs follow the event…
|
|
| 3 Jul 2014 |
[2014] EWHC 2212 (TCC)
An architect must exercise the reasonable skill, care and diligence expected of an ordinary competent and skilled architect. Professional judgment remains…
|
|
| 3 Jul 2014 |
[2014] EWHC 2125 (TCC)
A contract may arise from a tender, an instruction to proceed and subsequent performance, even though no formal contract is executed. The court determines…
|
|
| 30 Jun 2014 |
[2014] EWHC 2132 (TCC)
A contractual termination clause making remedial action subjectively satisfactory to one party is subject to implied limits of honesty, good faith…
|
2 |
| 24 Jun 2014 |
[2014] EWHC 2016 (TCC)
A director or employee who performs services through a company incurs personal liability for pure economic loss only where, viewed objectively, words or…
|
14 |
| 20 Jun 2014 |
[2014] EWHC 1973 (TCC)
A statutory compensation code displaces common-law remedies where, on its proper construction, the statutory scheme is comprehensive and the remedies are…
|
1 |
| 13 Jun 2014 |
[2014] EWHC 1881 (TCC)
A costs budget signed by a person who is not a senior legal representative is irregular, but it is not thereby a nullity. CPR 3.14 imposes its automatic…
|
1 |
| 11 Jun 2014 |
[2014] EWHC 1891 (TCC)
A reasonable and prudent landowner is not generally required to engage an arboriculturalist to inspect every tree periodically without a warning sign or other…
|
1 |
| 10 Jun 2014 |
[2014] EWHC 1907 (TCC)
A customer is liable for usage-based telecommunications charges only where the contract makes liability depend on the customer’s use, or where the customer is…
|
|
| 6 Jun 2014 |
[2014] EWHC 2367 (TCC)
Summary judgment requires the court to decide whether the claim has a realistic, rather than fanciful, prospect of success. The court must avoid a mini-trial…
|
|
| 6 Jun 2014 |
[2014] EWHC 1800 (TCC)
Where a successful claimant’s conduct has unnecessarily or unreasonably increased the costs of proceedings, the court may reduce the costs recoverable, taking…
|
|
| 5 Jun 2014 |
[2014] EWHC 1797 (TCC)
Under a building contract, an “appropriate deduction” for defects which the contractor is not to remedy is not necessarily confined to the contract rates or…
|
|
| 23 May 2014 |
[2014] EWHC 1615 (TCC)
On the proper construction of an insolvency termination clause in a partnering contract, a provision stating that the client is not bound to make any further…
|
|
| 16 May 2014 |
[2014] EWHC 1926 (TCC)
Where a court has established a timetable and procedure for experimental evidence, a party cannot ordinarily introduce late experiments or test results shortly…
|
|
| 15 May 2014 |
[2014] EWHC 1533 (TCC)
Summary judgment is inappropriate where the claim depends on materially disputed facts requiring investigation at trial. The court must not conduct a…
|
|
| 15 May 2014 |
[2014] EWHC 1498 (TCC)
In determining whether a procurement claim was commenced in time, the court must construe the claim form as a whole. Only brief details of the nature of the…
|
3 |
| 7 May 2014 |
[2014] EWHC 1644 (TCC)
Completion of a case management information sheet does not satisfy the separate obligation to file and serve a costs budget under the Civil Procedure Rules…
|
2 |
| 30 Apr 2014 |
[2014] EWHC 1344 (TCC)
Recognition and enforcement of a New York Convention award must ordinarily be ordered unless a ground in section 103 of the Arbitration Act 1996 is…
|
10 |
| 16 Apr 2014 |
[2014] EWHC 1028 (TCC)
Under a FIDIC-style construction contract, physical conditions are “Unforeseeable” only if they were not reasonably foreseeable by an experienced contractor at…
|
3 |
| 15 Apr 2014 |
[2014] EWHC 4819 (TCC)
Contractual amendments must be construed objectively and as a whole. Deleting an article containing an adjudication provision does not remove a separate…
|
|
| 15 Apr 2014 |
[2014] EWHC 1088 (TCC)
A construction contract may impose both an obligation to exercise reasonable care and skill and an express obligation to achieve a specified result. Where the…
|
|
| 11 Apr 2014 |
[2014] EWHC 1099 (TCC)
Part 36 is a self-contained and prescriptive costs regime. Where a claimant beats a valid offer, the court should ordinarily order the specified enhancements…
|
2 |
| 8 Apr 2014 |
[2014] EWHC 1058 (TCC)
An adjudication decision is enforceable despite an alleged error of fact or law, provided its terms are sufficiently certain. A party may reserve its…
|
7 |
| 4 Apr 2014 |
[2014] EWHC 940 (TCC)
For the purpose of a contractual conclusive-evidence clause, adjudication proceedings under the Scheme commence when a valid notice of adjudication is given…
|
6 |
| 2 Apr 2014 |
[2014] EWHC 1274 (TCC)
Relief from a procedural sanction will usually be granted where the breach is trivial or insignificant and the application is made promptly. Whether a breach…
|
1 |
| 28 Mar 2014 |
[2014] EWHC 958 (TCC)
In group litigation involving claims governed by Nigerian law, preliminary-issues directions limiting expert evidence must be respected. Additional reports…
|
|
| 27 Mar 2014 |
[2014] EWHC 837 (TCC)
Permission to amend a pleading or withdraw an admission is discretionary. The court must consider all the circumstances and give effect to the overriding…
|
|
| 21 Mar 2014 |
[2014] EWHC 752 (TCC)
Commercial exclusion and limitation clauses are construed by the ordinary principles applicable to contracts. Clear language is applied, even where the result…
|
4 |
| 28 Feb 2014 |
[2014] EWHC 530 (TCC)
For limitation purposes, a negligent subcontractor’s liability may accrue before the main contractor’s liability to the employer is formally quantified. A…
|
4 |
| 28 Feb 2014 |
[2014] EWHC 43 (TCC)
A professional designer may be negligent despite conformity with prevailing industry practice where the practice was adopted without identifying and logically…
|
1 |
| 24 Feb 2014 |
[2014] EWHC 435 (TCC)
Under section 44 of the Arbitration Act 1996, the court may grant urgent interim relief to preserve evidence or assets where the arbitral tribunal has no…
|
|
| 21 Feb 2014 |
[2014] EWHC 352 (TCC)
Parties issuing protective proceedings close to limitation must pursue them promptly and effectively. An extension of time for serving a Claim Form may be…
|
2 |
| 20 Feb 2014 |
[2014] EWHC 375 (TCC)
An insured must prove that a policy condition relating to occupancy was satisfied. A property may be “unoccupied” because it is insufficiently furnished for…
|
1 |
| 14 Feb 2014 |
[2014] EWHC 309 (TCC)
Failure to comply with a costs timetable is a factor in determining costs, but does not justify a reduction where it caused no practical disadvantage and the…
|
|
| 12 Feb 2014 |
[2014] EWHC 284 (TCC)
A costs budget is not a nullity merely because it fails to comply perfectly with the formal requirements for a statement of truth. Filing and exchanging a…
|
1 |
| 11 Feb 2014 |
[2014] EWHC 268 (TCC)
Contract formation depends objectively on what the parties communicated by words or conduct. The parties determine which terms must be agreed before they are…
|
5 |
| 10 Feb 2014 |
[2014] EWHC 244 (TCC)
A challenge under section 68 of the Arbitration Act 1996 is a limited longstop remedy. The court does not review whether an arbitral tribunal reached the…
|
1 |
| 7 Feb 2014 |
[2014] EWHC 280 (TCC)
A JCT adjudication clause permitting referral of disputes arising under the contract does not extend to a claim for damages under Misrepresentation Act 1967. A…
|
1 |
| 7 Feb 2014 |
[2014] EWHC 224 (TCC)
Damage to a chattel causes an immediate direct loss, measured by the diminution in value caused by the damage. Where the chattel can be economically repaired…
|
|
| 4 Feb 2014 |
[2014] EWHC 184 (TCC)
Indemnity costs require conduct that is unreasonable to a high degree and takes the litigation out of the norm. A merely weak or misguided claim or defence…
|
5 |
| 24 Jan 2014 |
[2014] EWHC 10 (TCC)
A letter of intent may create a binding interim construction contract where it identifies the work, performance requirements and remuneration with sufficient…
|
17 |
| 23 Jan 2014 |
[2014] EWHC 54 (TCC)
In adjudication, the scope of the dispute is determined principally by the notice of adjudication, construed against the crystallised dispute between the…
|
5 |
| 15 Jan 2014 |
[2014] EWHC 25 (TCC)
A bespoke professional-services agreement may make payment conditional upon completion of further work beyond the grant of planning permission. Where the…
|
1 |
| 13 Jan 2014 |
[2014] EWHC 589 (TCC)
A claim should be struck out or summarily determined only where it has no real prospect of success. An assignment made in breach of an anti-assignment clause…
|