Kellie & Anor v Wheatley & Lloyd Architects Ltd

[2014] EWHC 2886 (TCC)

Summary

In exercising the discretion on costs, the court must consider all the circumstances, including the parties’ conduct and their relative success on particular issues. A successful party should ordinarily recover its costs where unsuccessful points caused no identifiable additional expense or trial time.

Indemnity costs require conduct or circumstances taking the case out of the norm. Mere weakness of a claim, rejection of reasonable settlement offers, or reliance on evidence later exposed as unsatisfactory will not ordinarily suffice. The assessment basis is distinct from costs management. An approved budget, fixed with proportionality in mind, does not impose an analogous limit on costs assessed on the indemnity basis.

Treatment over time

Cited in 6 later judgments between 2015 and 2023. Applied, followed or approved 2 times, most recently by the High Court in July 2023.

Most often cited for

  1. Indemnity costs may exceed an approved budget but must remain reasonable3 judgments

Factual background

The claimants’ professional negligence claim against the defendant architects had been dismissed in an earlier judgment, [2014] EWHC 2212 (TCC). The court had reserved questions concerning the proportion of the defendant’s costs recoverable, the appropriate basis of assessment, and any further payment on account.

The claimants argued that two unsuccessful defences should reduce the defendant’s recovery. The defendant sought recovery of all costs on the indemnity basis and a further payment on account, relying on the weakness of the claim, the presentation of witness evidence, rejected settlement offers and the length of the trial.

Held

  1. Proportion of costs. Under rules 44.2(4), 44.2(5) and 44.2(6)(a) of the Civil Procedure Rules 1998, the court considered the parties’ overall success, the nature of the issues, their conduct, and whether the unsuccessful points caused identifiable additional cost. The no-loss and limitation defences involved specific legal submissions, but did not materially lengthen the trial or produce any identifiable increase in costs. They therefore did not justify reducing the defendant’s recovery.
  2. Costs management and indemnity assessment. The court respectfully disagreed with the approach in Elvanite Full Circle Ltd v AMEC Earth & Environment (UK) Ltd, which treated an approved costs budget as the starting point for indemnity assessment. Costs management is directed to proportionality on the standard basis. Rule 3.18 does not apply analogously to indemnity assessment, where proportionality is not in issue under rule 44.3(3). The approved budget may be relevant as evidence of expected costs, but it does not create a presumption limiting reasonable costs on the indemnity basis.
  3. Indemnity costs. The discretion is wide, but indemnity costs require conduct or circumstances taking the case outside the norm. Unreasonableness must be high degree; mere error, weakness viewed with hindsight, or rejection of reasonable offers is insufficient. The claim was weak and the evidence unsatisfactory, but it was arguable when pursued. The witness statement was unfortunate but not deliberately misleading or highly unreasonable. The rejected offers and alleged settlement pressure did not satisfy the test.
  4. The defendant was awarded all its costs, to be assessed on the standard basis if not agreed. The claimants were ordered to pay £90,000 on account. The court declined to order a sum exceeding the approved budget merely because the trial lasted five days.

The court’s approach to earlier authorities

Available to signed-in members.

Appellate history

First-instance costs judgment following the dismissal of the claim in [2014] EWHC 2212 (TCC) .

Other judgments in these proceedings

2 judgments in these proceedings, earliest first. Linked by the shared court number 0BS90655, and by appeals.

  1. 3 July 2014Kellie & Anor v Wheatley & Lloyd Architects Ltd[2014] EWHC 2212 (TCC) · High Court (Technology and Construction Court)
  2. 27 August 2014Kellie & Anor v Wheatley & Lloyd Architects Ltd[2014] EWHC 2886 (TCC) · High Court (Technology and Construction Court) · this judgment

Cases on related points

Of these 8 cases: 3 cited with it on the same point; 5 related in other ways.

Cited together forIndemnity costs may exceed an approved budget but must remain reasonable

  1. Three Rivers District Council & Ors v The Governor & Company of the Bank of England[2006] EWHC 816 (Comm) · High Court (Commercial Court)Cited together in 4 later judgments
  2. Excelsior Commercial & Industrial Holdings Limited v Salisbury Hammer Aspden & Johnson (a firm)[2002] EWCA Civ 879 · Court of Appeal (Civil Division)Cited together in 5 later judgments

+1 more for signed-in readers

Other related cases

  1. Bank of Ireland (Governors and Company of) & Anor v Watts Group Plc[2017] EWHC 2472 (TCC) · High Court (Technology and Construction Court)Cited together in 3 later judgments

+4 more for signed-in readers

Key cases cited

17 authorities cited.

Sign in to see how the court treated each authority. A free account is enough.

Cases citing this case

6 later cases · 2 positive · 2 neutral · 2 caution

Most senior citing decisions:

Sign in for the full treatment table. A free account is enough.