Bunge SA v Nidera BV

[2015] UKSC 43

Summary

Contract damages compensate the injured party for the value of the performance actually lost. Following an accepted anticipatory repudiation, a court may consider a non-price contingency which subsequent events show would lawfully have prevented performance or extinguished the loss. This principle applies to one-off sales as well as period or instalment contracts.

A contractual damages formula may depart from the common-law measure, but its scope depends on construction. A formula based on the contract price and the goods’ market value does not, without clear language, exclude other considerations affecting actual loss. A supervening export prohibition may therefore reduce damages to a nominal sum where the contract would never have been performed.

Treatment over time

Cited in 35 later judgments between 2015 and 2026, including 7 in the Supreme Court and Privy Council. Applied, followed or approved 24 times, most recently by the High Court in July 2026.

Most often cited for

  1. Damages compensate for the position lost through contractual non-performance12 judgments
  2. Available-market valuation reflects mitigation, but later events may show no compensable loss8 judgments
  3. Damages clauses are not presumed arbitrary and their scope depends on construction4 judgments
  4. Mitigation limits causation to loss the claimant could reasonably have avoided4 judgmentsobiter
  5. The value of contractual performance differs from the contract’s value as an asset3 judgments

Factual background

Bunge SA agreed to sell Nidera BV a cargo of Russian wheat under a contract incorporating GAFTA Form 49. Before the shipment period, Russia announced an export embargo. The sellers prematurely purported to cancel under the prohibition clause. The buyers accepted that act as a repudiation. The embargo nevertheless remained in force throughout the contractual shipment period.

The first-tier GAFTA tribunal found a repudiation but awarded no substantial damages because the contract would ultimately have been cancelled. The GAFTA Appeal Board instead awarded US$3,062,500 under the default clause. Hamblen J dismissed the sellers’ appeal in [2013] EWHC 84 (Comm); [2013] 1 Lloyd’s Rep 621. The Court of Appeal affirmed that decision in [2013] EWCA Civ 1628; [2014] 1 Lloyd’s Rep 404.

The Supreme Court had to decide whether the GAFTA default clause excluded the common-law compensatory principle and whether that principle applied to a one-off sale.

Held

Lord Sumption delivered the leading judgment, with which Lord Neuberger, Lord Mance and Lord Clarke agreed. Lord Toulson gave separate reasons, also agreed by those three Justices.

  1. The appeal was allowed unanimously. The Appeal Board’s award of substantial damages was varied by substituting nominal damages of US$5. The parties were directed to make written submissions about the Board’s costs award and the costs of the subsequent proceedings.

  2. The fundamental common-law principle is compensation for the contractual performance actually lost. Under The Golden Victory [2007] UKHL 12; [2007] 2 AC 353, contingencies known by the date of assessment must be considered where they show that the contract would lawfully have ended or become incapable of performance. The contingency need not have been inevitable when the repudiation was accepted. The principle applies to one-off contracts as well as contracts involving successive performance. The contrary suggested distinction in Lord Scott’s dicta was explained as referring to the ordinary case of a readily replaceable sale.

  3. The market-price measure and the effect of a non-price contingency are distinct questions. Sections 50 and 51 of the Sale of Goods Act 1979 provide a prima facie technique for valuing the goods or services that should have been delivered. They do not value the contract as an independently marketable asset. A market comparison is appropriate only where a true substitute contract is reasonably available and the comparison measures the financial disadvantage caused by the breach.

  4. A damages clause may prescribe a fixed or mechanical measure which differs from the common law. There is no presumption that it must reproduce the common-law result. In the absence of clear words, however, it should not be construed as producing an arbitrary recovery unrelated to any reasonable approximation of loss. Whether such a clause is an exhaustive code is a question of construction.

  5. GAFTA clause 20 was a complete code only for determining the relevant market price or value. The words requiring damages to be “based on” the difference between that value and the contract price did not require that difference to be awarded where no loss was suffered. The clause neither addressed nor excluded supervening non-price events. This construction was consistent with The Selda [1998] 1 Lloyd’s Rep 416 and Novasen SA v Alimenta SA [2013] 1 Lloyd’s Rep 647.

  6. The export embargo would have prevented shipment and cancelled the contract even without the premature repudiation. The buyers purchased no substitute goods and consequently lost nothing. Lord Toulson added that the sellers’ immediate genuine offer to restore the original bargain also answered the claim under the compensatory principle, although mitigation was not argued before the Supreme Court.

The court’s approach to earlier authorities

Available to signed-in members.

Appellate history

  1. United Kingdom Supreme Court: In [2015] UKSC 43 , allowed the sellers’ appeal and varied the Appeal Board’s award by substituting nominal damages of US$5.
  2. Court of Appeal: In [2013] EWCA Civ 1628 ; [2014] 1 Lloyd’s Rep 404, affirmed Hamblen J’s dismissal of the sellers’ appeal.
  3. Commercial Court: Hamblen J dismissed the material challenges to the Appeal Board’s award in [2013] EWHC 84 (Comm) ; [2013] 1 Lloyd’s Rep 621.
  4. GAFTA Appeal Board: Reversed the first-tier tribunal on damages and awarded the buyers US$3,062,500 under clause 20.
  5. First-tier GAFTA tribunal: Held that the sellers had repudiated the contract prematurely but awarded no substantial damages because the embargo would ultimately have cancelled the contract.

Appeal route

  1. Appealed from · 12 December 2013Bunge SA v Nidera BV[2013] EWCA Civ 1628 Court of Appeal (Civil Division)Partly reversedAppeal allowed unanimously; appeal board award varied by substituting nominal damages of us$5
  2. This judgment · 1 July 2015 [2015] UKSC 43 United Kingdom Supreme Court

Other judgments in these proceedings

3 judgments in these proceedings, earliest first. Linked by appeals and by the court numbers the judgments share.

  1. 29 January 2013Bunge SA v Nidera BV[2013] EWHC 84 (Comm) · High Court (Commercial Court)
  2. 12 December 2013Bunge SA v Nidera BV[2013] EWCA Civ 1628 · Court of Appeal (Civil Division)
  3. 1 July 2015Bunge SA v Nidera BV[2015] UKSC 43 · Supreme Court · this judgment

Often cited alongside this case

Of these 8 cases: 2 cited with it on 2 different points; 5 cited alongside it for other points; 1 related in other ways.

Cited together forAvailable-market valuation reflects mitigation, but later events may show no compensable loss

  1. Golden Strait Corporationv.Nippon Yusen Kubishka Kaisha[2007] UKHL 12 · House of LordsAlso cited together for: Damages compensate for the position lost through contractual non-performanceCited together in 18 later judgments

Cited together forDamages clauses are not presumed arbitrary and their scope depends on construction

  1. Novasen SA v Alimenta SA[2013] EWHC 345 (Comm) · High Court (Commercial Court)Cited together in 3 later judgments

Cited alongside it for other points

5 related cases for signed-in readers

Other related cases

  1. Classic Maritime Inc v Limbungan Makmur SDN BHD & Anor[2019] EWCA Civ 1102 · Court of Appeal (Civil Division)Cited together in 3 later judgments

Key cases cited

17 authorities cited.

Sign in to see how the court treated each authority. A free account is enough.

Cases citing this case