Case details
Summary
Adjudication decisions are ordinarily enforced summarily where the adjudicator decided the referred issues within jurisdiction and broadly complied with natural justice. A party generally must pay first and pursue the substantive dispute later. The narrow exceptions include an admitted error and a short, self-contained issue about the timing, categorisation or description of a payment application or notice, where it would be unconscionable for the court to ignore the issue on summary judgment. Contractual wording will not make a payment application invalid or impose a condition precedent unless it uses sufficiently clear language. A contract must be construed as a whole. Guidance concerning specific dates under materially different contract wording does not govern another contract.
Factual background
J Tomlinson Ltd sought summary judgment to enforce an adjudicator’s decision awarding approximately £1.246 million in respect of an interim payment application under a subcontract for electrical works. Balfour Beatty resisted enforcement, arguing that the application was invalid because it had not been posted and emailed in the contractually specified manner and had been submitted prematurely.
The parties did not challenge the adjudicator’s jurisdiction or allege a material breach of natural justice. The court therefore considered the established limits on resisting adjudication enforcement and, additionally, the contractual construction issues.
Held
- Enforcement principle. Summary judgment was granted for J Tomlinson Ltd in the sum awarded by the adjudicator. The adjudicator had decided the referred issues, acted broadly in accordance with natural justice, and the defendant’s challenge did not fall within a recognised exception.
- Adjudication has the statutory purpose of securing interim cash flow. The general rule is that a party must comply with an adjudicator’s decision and pursue final determination of the substantive dispute later. The merits of the underlying dispute ordinarily do not obstruct enforcement.
- The narrow exception concerning the timing, categorisation or description of a payment application or notice applies only within the carefully controlled approach identified in Hutton Construction Ltd v Wilson Properties (London) Ltd [2017] BLR 344. A proposed final determination normally requires a prompt CPR Part 8 claim, and the issue must be short and self-contained, require no oral evidence, and be one which it would be unconscionable for the court to ignore. Those conditions were not met here.
- The appendix wording that applications “should” be issued by post with copies by email gave guidance but did not impose a condition precedent. Read with clauses 21A and 41.2, hand delivery could constitute valid service. The contract had to be construed as a whole, and clearer wording would have been required to invalidate the application.
- The appendix provision concerning further valuation dates did not require later applications to be made only on particular dates. Read with clause 21A(5), it was insufficiently clear to alter the payment regime in that way.
- Leeds City Council v Waco UK Ltd [2015] EWHC 1400 (TCC) concerned materially different JCT Design and Build 2005 wording and therefore did not assist Balfour Beatty. The substantive factual dispute about delivery remained open for later proceedings.
The court’s approach to earlier authorities
This feature is available to zoomLaw Pro members.
Key cases cited
This feature is available to zoomLaw Pro members.
Cases citing this case
This feature is available to zoomLaw Pro members.