| Date | Case | Cited by |
|---|---|---|
| 31 Dec 2020 |
[2020] EWHC 3583 (TCC)
Under section 110(1)(a) of the Housing Grants, Construction & Regeneration Act 1996, the question is whether the payment mechanism in the particular…
|
|
| 18 Dec 2020 |
[2020] EWHC 3511 (TCC)
An agreement expressly made subject to contract and without prejudice will not normally become binding merely because the parties act upon it. Payments…
|
|
| 18 Dec 2020 |
[2020] EWHC 3491 (TCC)
For a civil recovery order, the claimant must establish on the balance of probabilities that the property was obtained through unlawful conduct and that the…
|
|
| 17 Dec 2020 |
[2020] EWHC 3804 (TCC)
An adjudicator appointed under an admitted construction contract may decide whether later dealings were variations of that contract or separate contracts only…
|
|
| 17 Dec 2020 |
[2020] EWHC 3417 (TCC)
Where an amendment effectively abandons a distinct cause of action, the court may order the amending party to pay both the costs of and caused by the amendment…
|
2 |
| 15 Dec 2020 |
[2020] EWHC 3419 (TCC)
Extrapolation from representative sampling is permissible in principle in professional negligence and construction claims. The claimant must still prove, on…
|
2 |
| 11 Dec 2020 |
[2020] EWHC 3404 (TCC)
Permission to amend after expiry of limitation requires the proposed new claim to arise from the same or substantially the same facts as the existing claim.…
|
1 |
| 11 Dec 2020 |
[2020] EWHC 3393 (TCC)
A contract for interior design services is construed according to its own terms. Where the contract provides for estimates to be accepted before becoming…
|
|
| 11 Dec 2020 |
[2020] EWHC 3392 (TCC)
Where parties achieve mixed procedural outcomes on applications concerning pleadings, the court may order that the relevant costs be costs in the case. That…
|
|
| 11 Dec 2020 |
[2020] EWHC 3389 (TCC)
Construction contracts are governed by ordinary contractual principles. Whether a document described as an estimate creates a fixed-price contract, a cost-plus…
|
|
| 8 Dec 2020 |
[2020] EWHC 3354 (TCC)
A VAT refund obtained by a trader under a statutory reimbursement scheme, supported by an undertaking to repay the customer who bore the VAT, may be held on a…
|
|
| 3 Dec 2020 |
[2020] EWHC 3609 (TCC)
Permission for judicial review requires an arguable case deserving full investigation. Derogations from ordinary public procurement procedures require strict…
|
|
| 3 Dec 2020 |
[2020] EWHC 3314 (TCC)
Adjudication decisions are enforced unless the adjudicator decided a question outside the reference or acted in a manner that was obviously unfair. A referring…
|
4 |
| 3 Dec 2020 |
[2020] EWHC 3293 (TCC)
Extensions of time for serving Particulars of Claim should promote a properly pleaded case while allowing reasonable time for investigation and any Pre-Action…
|
|
| 19 Nov 2020 |
[2020] EWHC 3281 (TCC)
Where limitation is an essential part of a jurisdiction challenge, the court may determine limitation and jurisdiction together as preliminary issues. It need…
|
|
| 17 Nov 2020 |
[2020] EWHC 3082 (TCC)
In a wholly video-conducted civil hearing, the court may permit parties, witnesses and other authorised persons to attend remotely from outside England and…
|
2 |
| 13 Nov 2020 |
[2020] EWHC 3028 (TCC)
An interim payment application under a construction subcontract must be clear in substance, form and intent. It must identify the sum claimed, the basis of…
|
|
| 9 Nov 2020 |
[2020] EWHC 2930 (TCC)
Abuse of process may arise where proceedings are pursued in parallel with closely related foreign group litigation, creating oppressive duplication, a serious…
|
3 |
| 6 Nov 2020 |
[2020] EWHC 2958 (TCC)
In a procurement challenge, summary judgment may be granted where the claimant has a cast-iron case on breach and no real prospect of avoiding an order setting…
|
|
| 28 Oct 2020 |
[2020] EWHC 3069 (TCC)
Under CPR 3.1(3), the court may make continued participation in proceedings conditional on payment of security and may specify strike-out as the consequence of…
|
|
| 21 Oct 2020 |
[2020] EWHC 3066 (TCC)
On an application to continue an interim injunction, the court applies the American Cyanamid principles. There must be a serious issue to be tried; damages…
|
|
| 20 Oct 2020 |
[2020] EWHC 2777 (TCC)
A court cannot revisit a sealed and unappealed order unless the order authorises reconsideration or an applicable general jurisdiction is engaged. Where an…
|
|
| 16 Oct 2020 |
[2020] EWHC 2744 (TCC)
A revision to an approved costs budget may be justified by a significant development: an event, circumstance or step going beyond what was expressly or…
|
|
| 7 Oct 2020 |
[2020] EWHC 2865 (TCC)
For a proprietary interim claim, the court applies the familiar requirements of a serious issue to be tried, the balance of convenience, and whether it is just…
|
|
| 24 Sep 2020 |
[2020] EWHC 2537 (TCC)
A contractual reference to assigning a subcontract ordinarily transfers the assignor’s accrued and future rights, unless clear words limit the assignment. It…
|
3 |
| 23 Sep 2020 |
[2020] EWHC 2521 (TCC)
A lease covenant requiring premises to be delivered up in good and substantial repair and condition may require works extending beyond repair strictly so…
|
1 |
| 18 Sep 2020 |
[2020] EWHC 2484 (TCC)
Signed timesheets are primary evidence of hours worked where a labour-supply contract provides for invoicing by reference to them, but they are not conclusive…
|
1 |
| 18 Sep 2020 |
[2020] EWHC 2471 (TCC)
A party cannot introduce a substantial new issue at the eleventh hour merely because the supporting evidence was already before the court. A skeleton argument…
|
|
| 14 Sep 2020 |
[2020] EWHC 2451 (TCC)
A company in insolvent liquidation may adjudicate and may, in principle, obtain summary enforcement of an adjudicator’s decision. Enforcement depends on…
|
|
| 11 Sep 2020 |
[2020] EWHC 2430 (TCC)
Permission to amend a statement of case should be refused where the proposed claim does not have real prospects of success and lacks a coherent pleaded causal…
|
|
| 11 Sep 2020 |
[2020] EWHC 2387 (TCC)
A Part 36 offer must comply with the mandatory requirements of Civil Procedure Rules 1998 Part 36, but an ambiguity in an otherwise genuine Part 36 offer may…
|
3 |
| 4 Sep 2020 |
[2020] EWHC 2308 (TCC)
A contractual retention remains retention money unless the contract clearly provides otherwise. Where the contract specifies when it may be withheld, the…
|
|
| 1 Sep 2020 |
[2020] EWHC 2353 (TCC)
Permission to appeal an arbitral award under section 69 of the Arbitration Act 1996 requires an identified question of law and satisfaction of the statutory…
|
2 |
| 28 Aug 2020 |
[2020] EWHC 2338 (TCC)
A request for the appointment of an adjudicator under the Scheme must follow the notice of adjudication. A request made first cannot validly found the…
|
1 |
| 27 Aug 2020 |
[2020] EWHC 2738 (TCC)
Economic duress is not established merely because a party uses lawful commercial pressure. Where the party applying pressure honestly believes, in good faith…
|
|
| 24 Aug 2020 |
[2020] EWHC 2306 (TCC)
Where a judgment debtor obtains a stay of execution pending appeal, costs of the stay application may properly be treated as costs in the appeal where both…
|
|
| 14 Aug 2020 |
[2020] EWHC 2444 (TCC)
Permission to amend a statement of case shortly before trial requires a heavy burden to be discharged. The applicant must explain the delay, show that the…
|
1 |
| 14 Aug 2020 |
[2020] EWHC 2211 (TCC)
Under CPR r 19.6, representative proceedings require the representative and represented parties to have the same interest. Common issues of fact or law are…
|
|
| 7 Aug 2020 |
[2020] EWHC 2159 (TCC)
A stay of execution pending appeal is exceptional. The court must first determine whether enforcement would stifle an effective appeal and must then exercise a…
|
|
| 4 Aug 2020 |
[2020] EWHC 2226 (TCC)
When claims concerning the same defects are brought against different defendants, the starting point may be a joint trial to avoid duplicated proceedings and…
|
|
| 3 Aug 2020 |
[2020] EWHC 2128 (TCC)
In assessing costs after a substantial but incomplete recovery, the successful party is identified by examining who won in substance and reality, rather than…
|
3 |
| 30 Jul 2020 |
[2020] EWHC 2049 (TCC)
In determining the scope of a common-law duty of care for economic loss, the court must consider the contractual nexus, or absence of one, together with the…
|
|
| 29 Jul 2020 |
[2020] EWHC 2047 (TCC)
Summary assessment of costs is a global assessment, rather than an item-by-item detailed assessment. The court must allow costs that are proportionate and…
|
1 |
| 24 Jul 2020 |
[2020] EWHC 1982 (TCC)
A failure to prevent an unknown third party causing property damage is ordinarily a pure omission and does not give rise to liability in negligence. The…
|
|
| 23 Jul 2020 |
[2020] EWHC 1965 (TCC)
An adjudicator’s valuation may be temporarily binding even where the adjudicator lacked jurisdiction to order payment to the responding party. The court may…
|
1 |
| 22 Jul 2020 |
[2020] EWHC 1971 (TCC)
Expert determination clauses must be construed according to the contract’s language and structure. The expert may determine factual matters necessary to…
|
|
| 17 Jul 2020 |
[2020] EWHC 1803 (TCC)
For a procurement damages claim, the claimant must establish on the balance of probabilities that it was an economic operator and had a material interest in…
|
|
| 15 Jul 2020 |
[2020] EWHC 1862 (TCC)
A party’s failure to pay an adjudication award and judgment may justify a stay of later proceedings, particularly where the conduct is deliberate, persistent…
|
1 |
| 10 Jul 2020 |
[2020] EWHC 1856 (TCC)
Strike-out is an exceptional remedy. Under CPR r.3.4(2)(a), the court considers whether the pleaded case discloses a legally recognisable claim or defence…
|
2 |
| 7 Jul 2020 |
[2020] EWHC 1801 (TCC)
Where an individual contracts with another party, the individual is the contracting party unless the document or admissible extrinsic evidence makes clear that…
|
|
| 25 Jun 2020 |
[2020] EWHC 164 (TCC)
On an application for strike-out or summary judgment, the court must not conduct a mini-trial. A claim should proceed where factual disputes may determine the…
|
|
| 25 Jun 2020 |
[2020] EWHC 1626 (TCC)
For the purposes of section 105(2)(c)(i) of the Housing Grants, Construction and Regeneration Act 1996, the relevant question is whether power generation is…
|
|
| 24 Jun 2020 |
[2020] EWHC 1646 (TCC)
On a defendant’s application for summary judgment, the court must decide whether the claim has a realistic, rather than fanciful, prospect of success. It must…
|
1 |
| 18 Jun 2020 |
[2020] EWHC 1581 (TCC)
A long-term PFI contract may be a relational contract, but an implied duty of good faith cannot contradict detailed express provisions or require a party to…
|
3 |
| 17 Jun 2020 |
[2020] EWHC 1591 (TCC)
For summary judgment, the court asks whether the claim has a real, rather than fanciful, prospect of success. It must avoid a mini-trial, while rejecting…
|
|
| 17 Jun 2020 |
[2020] EWHC 1568 (TCC)
In a public procurement, a contracting authority may allocate substantial, uncertain or exogenous commercial risks to bidders, particularly where the…
|
6 |
| 15 Jun 2020 |
[2020] EWHC 1523 (TCC)
Design life, suitability and maintenance provisions in a design-and-build contract may impose strict contractual obligations, rather than duties of reasonable…
|
|
| 5 Jun 2020 |
[2020] EWHC 1414 (TCC)
After expiry of the limitation period, substitution of a claimant is governed by Civil Procedure Rules 1998 Part 19.5 where the proposed claimant is a…
|
4 |
| 5 Jun 2020 |
[2020] EWHC 1413 (TCC)
A dispute may crystallise through silence where a contractual claim has been adequately notified, the respondent is obliged to respond within a specified…
|
|
| 29 May 2020 |
[2020] EWHC 1374 (TCC)
Disclosure under PD51U must be directed to the issues in dispute and must remain reasonable and proportionate. There is no presumption in favour of Extended…
|
2 |
| 27 May 2020 |
[2020] EWHC 1310 (TCC)
In assessing costs, comparison with the opposing party’s costs may be informative when considering whether the costs claimed are prima facie excessive.…
|
|
| 27 May 2020 |
[2020] EWHC 1309 (TCC)
Cost budgets should be assessed by reference to proportionality and the issues genuinely requiring determination. Where written closing submissions are…
|
4 |
| 22 May 2020 |
[2020] EWHC 985 (TCC)
A professional surveyor must exercise reasonable skill and care within the scope of the service agreed. Choosing a HomeBuyer Report rather than a building…
|
1 |
| 22 May 2020 |
[2020] EWHC 2443 (TCC)
In a terminal dilapidations claim, disclosure must be reasonable and proportionate to the issues requiring determination. The court should order only…
|
|
| 22 May 2020 |
[2020] EWHC 1302 (TCC)
Anonymity requires strict justification because it derogates from open justice. Personal concerns about internet searches were insufficient, although omitting…
|
1 |
| 20 May 2020 |
[2020] EWHC 1285 (TCC)
An award of interest is discretionary and should fairly compensate a claimant for being deprived of money that ought to have been received. Interest on…
|
|
| 18 May 2020 |
[2020] EWHC 1232 (TCC)
A supplier undertaking design work for components intended to operate within a wider system must take reasonable care to ensure that the components can be…
|
|
| 13 May 2020 |
[2020] EWHC 1190 (TCC)
An application for pre-action disclosure under CPR Part 31.16 requires satisfaction of a jurisdictional threshold and then a separate discretionary assessment.…
|
2 |
| 11 May 2020 |
[2020] EWHC 1159 (TCC)
Summary judgment and strike out are exceptional remedies where the pleaded case depends on disputed facts. A claim has a real prospect of success if it carries…
|
|
| 7 May 2020 |
[2020] EWHC 1120 (TCC)
A party dissatisfied with an adjudicator’s decision must ordinarily comply with it and argue the merits later. A Part 8 claim may prevent enforcement only…
|
|
| 6 May 2020 |
[2020] EWHC 1018 (TCC)
Under the Public Contracts Regulations 2015, a breach which causes loss or a risk of loss is actionable when the economic operator knows, or ought to know, the…
|
3 |
| 4 May 2020 |
[2020] EWHC 1305 (TCC)
Adjudication exists to secure interim cash flow. An adjudicator’s decision will ordinarily be enforced by summary judgment where the adjudicator had…
|
4 |
| 1 May 2020 |
[2020] EWHC 1057 (TCC)
The threshold for indemnity costs is high. They should be ordered only where the conduct or circumstances take the case outside the norm. Serious allegations…
|
1 |
| 29 Apr 2020 |
[2020] EWHC 1483 (TCC)
Adjudication decisions are ordinarily enforced summarily where the adjudicator decided the referred issues within jurisdiction and broadly complied with…
|
|
| 24 Apr 2020 |
[2020] EWHC 972 (TCC)
A logistics provider responsible for goods and distribution services must assess reasonably foreseeable risks, including unauthorised entry, arson and fire…
|
6 |
| 21 Apr 2020 |
[2020] EWHC 945 (TCC)
Payment of an adjudicator’s fees does not, without more, establish an election to accept the decision as valid. The court must assess the objective inference…
|
2 |
| 21 Apr 2020 |
[2020] EWHC 944 (TCC)
Adjudication decisions are ordinarily enforced summarily because adjudication provides a rapid, interim resolution of construction disputes. A stay of…
|
3 |
| 21 Apr 2020 |
[2020] EWHC 943 (TCC)
Under CPR rule 19.5, substitution after expiry of the limitation period is available where the original claim cannot properly continue without the new party…
|
3 |
| 21 Apr 2020 |
[2020] EWHC 785 (TCC)
In procurement proceedings, an amendment is not a new claim merely because it expands the factual enquiry. The question is whether the core breach remains the…
|
|
| 20 Apr 2020 |
[2020] EWHC 928 (TCC)
Applications affected by the Covid-19 pandemic must be determined by reference to the overriding objective, the importance of continuing the administration of…
|
|
| 3 Apr 2020 |
[2020] EWHC 809 (TCC)
An independent expert may owe a fiduciary duty of loyalty to the client where the retainer includes extensive litigation or arbitration advice and support, in…
|
|
| 2 Apr 2020 |
[2020] EWHC 2854 (TCC)
An adjudicator’s jurisdiction depends on the contractual or statutory adjudication mechanism actually agreed by the parties. A notice need not expressly…
|
|
| 2 Apr 2020 |
[2020] EWHC 1320 (TCC)
Interlocutory injunctions preventing an adjudication are exceptional. They should be granted only in very rare and clear cases, such as where the adjudication…
|
|
| 30 Mar 2020 |
[2020] EWHC 1328 (TCC)
Where the statutory or procedural conditions for security for costs are satisfied, the court must decide whether security is just having regard to all the…
|
1 |
| 27 Mar 2020 |
[2020] EWHC 749 (TCC)
In group litigation, the parties’ ordinary choice of solicitors and counsel is qualified by the need for efficient, proportionate and coherent management of…
|
2 |
| 27 Mar 2020 |
[2020] EWHC 738 (TCC)
A consequential case-management hearing may address an issue closely connected with an earlier judgment, but fairness may require the issue to be adjourned…
|
|
| 13 Mar 2020 |
[2020] EWHC 970 (TCC)
Service of a claim form at a company’s relevant place is effective where the documents are left at the correct address. Handing them to a receptionist at that…
|
|
| 12 Mar 2020 |
[2020] EWHC 941 (TCC)
Payment provisions in a construction contract must be construed with the contractual terms and supplemented by the Scheme for Construction Contracts only to…
|
3 |
| 11 Mar 2020 |
[2020] EWHC 847 (TCC)
For the purpose of adjudication, a notice is given when it comes to the addressee’s attention, or on the contractually deemed date of service, rather than…
|
|
| 2 Mar 2020 |
[2020] EWHC 459 (TCC)
For limitation purposes, a single oil spill causing continuing consequential damage ordinarily constitutes one nuisance, not a continuing nuisance, unless the…
|
7 |
| 28 Feb 2020 |
[2020] EWHC 468 (TCC)
A guarantee must be construed according to its wording and as a whole. A bond framed as a performance guarantee, requiring breach and contractual establishment…
|
2 |
| 28 Feb 2020 |
[2020] EWHC 448 (TCC)
A contracting authority may abandon a procurement exercise at any stage unless contract, statute or procurement law imposes a restriction. The decision remains…
|
3 |
| 27 Feb 2020 |
[2020] EWHC 796 (TCC)
An insolvent company is not automatically barred from bringing adjudications merely because its claims and counterclaims arise under several contracts.…
|
|
| 25 Feb 2020 |
[2020] EWHC 387 (TCC)
Expert evidence may be excluded where an expert’s lack of independence makes the evidence inadmissible, but exclusion is a serious and proportionate response.…
|
|
| 14 Feb 2020 |
[2020] EWHC 968 (TCC)
A demand guarantee must be construed objectively, using both textual and contextual analysis. Where competing constructions exist, the court may prefer the…
|
|
| 11 Feb 2020 |
[2020] EWHC 760 (TCC)
A settlement offer is construed objectively from its wording and the relevant factual matrix. Where an offer refers to payment of the costs of the litigation…
|
|
| 7 Feb 2020 |
[2020] EWHC 223 (TCC)
In an amended FIDIC-style construction contract, responsibility for site and subsurface conditions remained with the contractor where the contract contained a…
|
1 |
| 5 Feb 2020 |
[2020] EWHC 192 (TCC)
A later claim is not necessarily an abuse merely because it could have been brought in earlier proceedings. The court must ask whether it should have been…
|
1 |
| 4 Feb 2020 |
[2020] EWHC 497 (TCC)
Summary judgment may enforce an adjudicator’s decision even where the defendant takes no part in the enforcement proceedings, provided service and jurisdiction…
|
|
| 31 Jan 2020 |
[2020] EWHC 1947 (TCC)
Where an adjudicator has jurisdiction and has complied with natural justice, the decision should ordinarily be enforced under the pay now, argue later…
|
|
| 23 Jan 2020 |
[2020] EWHC 90 (TCC)
An arbitration clause may be incorporated into a construction contract by a sufficiently wide reference to a quotation that included the supplier’s standard…
|
1 |
| 17 Jan 2020 |
[2020] EWHC 401 (TCC)
In a shorter trial, expert evidence must remain within the real issues defined by the statements of case and their context. A general allegation putting a…
|
|
| 17 Jan 2020 |
[2020] EWHC 19 (TCC)
On an application for strike out or summary judgment, a pleaded duty of care claim may be rejected where the facts cannot establish sufficient proximity, an…
|
|
| 7 Jan 2020 |
[2020] EWHC 4 (TCC)
Contractual documents must be construed as a whole, considering their language, context and commercial consequences. Where vesting certificates provide for…
|