Summary
A long-term PFI contract may be a relational contract, but an implied duty of good faith cannot contradict detailed express provisions or require a party to surrender a negotiated contractual benefit. Contractual acceptance tests must be applied according to their express terms, including requirements to test different operating modes. Approval of facility modifications does not relieve the contractor from performance obligations or planning requirements. The waste hierarchy is flexible and permits reasonable departures justified by the best overall environmental outcome. A contractual right to terminate is not subject to an automatic promptness requirement, although it may be lost by clear waiver by election. Where a contract treats deliberate diversion of waste as a compensation event, liability turns on intentional diversion rather than blameworthiness.
Factual background
Essex County Council contracted with UBB Waste (Essex) Ltd for the design, construction and operation of a mechanical biological waste-treatment facility. The facility failed to obtain an Acceptance Test Certificate by the contractual longstop date. UBB alleged design and performance issues were caused or aggravated by waste composition, the Authority’s refusal to approve or accommodate modifications, and the suspension of waste deliveries during an asbestos scare. The Authority sought declarations, damages and confirmation of its contractual right to terminate. UBB counterclaimed for declarations, compensation and an extension of time. The principal issues concerned contractual construction, implied duties of good faith and co-operation, the operation of acceptance tests, planning permission, composition testing, termination and compensation events.
Held
- Acceptance tests. The contract required the facility to pass the Acceptance Tests in both Bio-Stabilisation Mode and SRF Mode. The facility had to satisfy the Throughput, Recovery, BMW reduction, Recyclate and SRF quality requirements in accordance with the contractual method statements. The QSRF bypass could not be counted towards the contractual Throughput Test because the test concerned waste fed into the pre-processing module and the bio-stabilisation line. The original facility could not pass the Throughput or BMW reduction tests. The modified facility could not pass the Throughput, Recovery or BMW reduction tests even if the QSRF line were operated.
- Good faith and relational contract. The 25-year PFI contract was a paradigm relational contract and contained an implied duty of good faith. The duty was objective and context-sensitive. Dishonesty was sufficient but not necessary; the question was whether conduct was commercially unacceptable to reasonable and honest people. The duty could not require the Authority to abandon expressly negotiated performance standards, agree to replace the BMc test without adequate safeguards, or accept modifications that undermined the express testing regime.
- Discretion and modifications. The Authority was entitled to insist on testing in both modes and to reject modifications which would have a detrimental effect on the performance guarantees. Approval under schedule 9 required UBB to implement approved modifications but did not relieve it of its contractual obligations. The QSRF modifications involving mass diversion of waste breached planning condition 2 and could not be operated without revised planning permission. Modifications 3, 4 and 5 were contractually permitted, subject to the planning position.
- Composition and compensation. Composition results had to be assessed using the rolling annual average. An Impact and Remedy Report was not triggered merely because raw quarterly data fell below the Band A threshold. The waste did not fall into Band B until the fourth quarter of 2016. The Authority was not then in breach for failing to conduct an earlier Options Review, and UBB failed to establish causation between any composition issue and its inability to pass the tests.
- Termination and asbestos diversion. There was no implied term requiring prompt exercise of the right to terminate for failure to obtain the Acceptance Test Certificate. The right could nevertheless be lost by clear waiver by election. It had not been lost while the facility remained incapable of passing the tests. The Authority was entitled to terminate as at 13 June 2019. Under clause 21.2.5, wilfully allowing diversion meant an intentional or deliberate act, without a requirement of blameworthiness. The Authority had not wilfully directed diversion but had wilfully allowed it by taking no action to persuade its contractor to continue deliveries. UBB was entitled to £745,234 compensation for the asbestos-related interruption. The Authority was awarded £9,038,428 damages for unauthorised QSRF operation, with continuing losses of £99,563 per month.
The court’s approach to earlier authorities
Available to signed-in members.
Key cases cited
22 authorities cited.
- London Borough of Lambeth v Secretary of State for Housing, Communities and Local Government and others [2019] UKSC 33
- Trump International Golf Club Scotland Ltd v Scottish Ministers [2015] UKSC 74
- Marks and Spencer plc v BNP Paribas Securities Services Trust Company (Jersey) Limited and another [2015] UKSC 72
- Arnold v Britton and others [2015] UKSC 36
- Braganza v BP Shipping Limited and another [2015] UKSC 17
- MSC Mediterranean Shipping Company SA v Cottonex Anstalt [2016] EWCA Civ 789
- Mid Essex Hospital Services NHS Trust v Compass Group UK and Ireland Ltd (t/a Medirest) [2013] EWCA Civ 200
- Skrytek v Secretary of State for Communities and Local Government [2013] EWCA Civ 1 231
- Lomas & Ors v JFB Firth Rixson Inc & Ors [2012] EWCA Civ 419
- Crosstown Music Company 1,LLC v Rive Droite Music Ltd & Ors [2010] EWCA Civ 1222
- Tele2 International Card Company SA & Ors v Post Office Ltd [2009] EWCA Civ 9
- CMA CGM SA v Beteiligungs-KG MS Northern Pioneer Schiffahrtsgesellschaft mbH & Co [2002] EWCA Civ 1878
- Excelsior Commercial & Industrial Holdings Limited v Salisbury Hammer Aspden & Johnson (a firm) [2002] EWCA Civ 879
- Bates & Ors v Post Office Ltd ((No.3) "Common Issues") [2019] EWHC 606 (QB)
- Protreat Ltd, R (On the Application Of) v The Environment Agency [2018] EWHC 1983 (Admin)
- Sheikh Tahnoon Bin Saeed Bin Shakhboot Al Nehayan v Kent [2018] EWHC 333 (Comm)
- Gestmin SGPS SA v Credit Suisse (UK) Ltd & Anor [2013] EWHC 3560 (Comm)
- Yam Seng PTE Ltd v International Trade Corporation Ltd [2013] EWHC 111 (QB)
- MOTOR OIL HELLAS (CORINTH) REFINERIES S.A. v. SHIPPING CORPORATION OF INDIA (THE “KANCHENJUNGA”) [1990] 1 Lloyd's Rep 391
- ARMAGAS LTD. v. MUNDOGAS S.A. (THE "OCEAN FROST") [1985] 1 Lloyd's Rep 1
- BP Refinery (Westernport) Pty Ltd v. Shire of Hastings 1977) 180 CLR 266 (PC
- Cape of Good Hope Motor Ship Co Ltd v Ministry of Agriculture, Fisheries and Food (Reardon Smith Line Ltd v Ministry of Agriculture, Fisheries and Food, Carlton Steamship Co Ltd v Ministry of Agriculture, Fisheries and Food) [1963] AC 691
Sign in to see how the court treated each authority. A free account is enough.
Cases citing this case
3 later cases · 3 positive
Most senior citing decisions:
- Svella Connect Limited v Virgin Media Limited [2026] EWHC 2223 (TCC) followed
- Portobello Productions Limited v Sunnymarch Limited [2022] EWHC 3014 (Ch) followed
- Westfields Homes Ltd & Anor v Keay Homes (Windrush) Ltd [2020] EWHC 3368 (Ch) applied
Sign in for the full treatment table. A free account is enough.