| Date | Case | Cited by |
|---|---|---|
| 20 Dec 2019 |
[2019] EWHC 3585 (TCC)
On an application to lift an automatic suspension in a procurement challenge, the court applies the American Cyanamid approach. It asks whether there is a…
|
6 |
| 19 Dec 2019 |
[2019] EWHC 3526 (TCC)
An indemnity costs order requires conduct or circumstances taking the case outside the norm. The court must consider all the circumstances, including the…
|
|
| 17 Dec 2019 |
[2019] EWHC 3488 (TCC)
Where parties’ conduct temporarily prevents reliance on a contractual deadline, the resulting estoppel may postpone the start of the contractual period without…
|
|
| 16 Dec 2019 |
[2019] EWHC 3482 (TCC)
Part 8 declaratory relief is discretionary. In adjudication-related proceedings, the court should grant declarations only where the issue can fairly be…
|
|
| 2 Dec 2019 |
[2019] EWHC 3225 (TCC)
An agreement may contain separate offers, some capable of acceptance and others amounting only to invitations to negotiate. Whether a contract was formed, and…
|
|
| 22 Nov 2019 |
[2019] EWHC 3337 (TCC)
A trial date in the Technology and Construction Court should be vacated only in exceptional circumstances. Increased disclosure volume will not ordinarily…
|
|
| 18 Nov 2019 |
[2019] EWHC 3060 (TCC)
A contractual assessment clause permitting recovery of overpayments may operate alongside the interim-payment and final-account machinery in a construction…
|
2 |
| 15 Nov 2019 |
[2019] EWHC 3727 (TCC)
Where a contract provides a termination payment, the client cannot avoid that payment by making termination inevitable through selling the relevant property…
|
|
| 11 Nov 2019 |
[2019] EWHC 3028 (TCC)
Where a claimant beats its own Part 36 offer, the prescribed consequences ordinarily follow unless it would be unjust to impose them. The regime is intended to…
|
|
| 31 Oct 2019 |
[2019] EWHC 3210 (TCC)
Where a claimant’s Civil Procedure Rules 1998 Part 36 offer is at least as advantageous as the judgment obtained, the prescribed consequences should follow…
|
|
| 31 Oct 2019 |
[2019] EWHC 2846 (TCC)
A contractual obligation must be construed in its factual context at the time of agreement. A party cannot use anticipated difficulties in obtaining a future…
|
|
| 30 Oct 2019 |
[2019] EWHC 2922 (TCC)
On an application to adjourn a fixed trial, the court must balance the legitimate expectation that the fixture will be maintained against the risk of an unfair…
|
|
| 15 Oct 2019 |
[2019] EWHC 2722 (TCC)
In commercial litigation, the party receiving a substantial payment will ordinarily be treated as the overall successful party for costs purposes. The starting…
|
|
| 10 Oct 2019 |
[2019] EWHC 3589 (TCC)
In procurement proceedings involving an automatic suspension, an awarding authority seeking discharge should provide sufficiently detailed reasons and…
|
1 |
| 10 Oct 2019 |
[2019] EWHC 2651 (TCC)
An adjudication decision obtained by a company in insolvent liquidation will ordinarily be unenforceable because adjudication is incompatible with insolvency…
|
6 |
| 10 Oct 2019 |
[2019] EWHC 2601 (TCC)
A dispute for adjudication crystallises when the claim has been communicated and the responding party has had a reasonable opportunity to consider it, and it…
|
|
| 2 Oct 2019 |
[2019] EWHC 2547 (TCC)
In a hybrid construction contract, the parties may agree one payment regime covering both construction and non-construction operations. A payment notice need…
|
2 |
| 25 Sep 2019 |
[2019] EWHC 2497 (TCC)
Under a joint venture agreement reflecting an NEC target-cost contract, interim reimbursement of a party’s properly identified Works Part Costs is not subject…
|
|
| 24 Sep 2019 |
[2019] EWHC 2504 (TCC)
In a summary assessment of costs, recoverable costs are limited to costs reasonably and proportionately incurred and reasonable and proportionate in amount.…
|
3 |
| 22 Aug 2019 |
[2019] EWHC 2188 (TCC)
Contractual rights constitute possessions under Article 1 of the First Protocol only where they have an identifiable and readily realisable monetary value. A…
|
|
| 16 Aug 2019 |
[2019] EWHC 2246 (TCC)
A contractual tiered dispute-resolution clause may create an enforceable condition precedent to court proceedings. The procedure must be expressed in mandatory…
|
3 |
| 13 Aug 2019 |
[2019] EWHC 2216 (TCC)
Damages for breach of warranty in a share purchase agreement may be assessed by the reduction in the value of the acquired companies resulting from the breach…
|
|
| 13 Aug 2019 |
[2019] EWHC 2212 (TCC)
Under section 103(5) of the Arbitration Act 1996, enforcement of a New York Convention award may be adjourned while the outcome of foreign setting-aside…
|
1 |
| 13 Aug 2019 |
[2019] EWHC 2211 (TCC)
Challenges under the Public Contracts Regulations 2015 must be brought within the prescribed period once the economic operator knows, or ought to know, that…
|
|
| 8 Aug 2019 |
[2019] EWHC 2360 (TCC)
For the purposes of the Housing Grants Construction and Regeneration Act 1996, delivery of materials is excluded from “construction operations” unless the…
|
|
| 8 Aug 2019 |
[2019] EWHC 2184 (TCC)
Settlement agreements made by an agent acting for a financially pressured employer remain enforceable unless fraud, bribery, dishonest assistance, undue…
|
|
| 7 Aug 2019 |
[2019] EWHC 2170 (TCC)
In adjudication enforcement proceedings, an adjudicator’s error in addressing evidence or a sub-issue will ordinarily not make the decision unenforceable if…
|
4 |
| 31 Jul 2019 |
[2019] EWHC 2109 (TCC)
A professional designer responsible for structural fill and associated drainage must design the works as an integrated system, including the consequences of…
|
|
| 31 Jul 2019 |
[2019] EWHC 2047 (TCC)
Public-law challenges to the validity of administrative decisions must generally be brought promptly by judicial review. That principle does not convert an…
|
1 |
| 30 Jul 2019 |
[2019] EWHC 2078 (TCC)
An application made before expiry of the permitted period to extend time for complying with a court order is governed by Civil Procedure Rules 1998, rule…
|
3 |
| 26 Jul 2019 |
[2019] EWHC 2050 (TCC)
The first ground for a declaration of ineffectiveness under the Public Contracts Regulations 2015 is concerned with whether the required prior contract notice…
|
|
| 17 Jul 2019 |
[2019] EWHC 1876 (TCC)
On an application to enforce an adjudicator’s decision by summary judgment, the respondent need only show a real prospect of success. That means a prospect…
|
|
| 9 Jul 2019 |
[2019] EWHC 1787 (TCC)
A notice of adjudication must be construed objectively as a whole, against its contractual setting, and by asking how it would have informed a reasonable…
|
1 |
| 8 Jul 2019 |
[2019] EWHC 1769 (TCC)
In construing a contractual payment provision, the natural and ordinary meaning of default was a failure to comply with a contractual obligation. The court…
|
1 |
| 28 Jun 2019 |
[2019] EWHC 1659 (TCC)
A contractual choice of court clause may operate alongside adjudication and arbitration provisions where the contract does not clearly replace those…
|
1 |
| 28 Jun 2019 |
[2019] EWHC 1647 (TCC)
Costs of an interim application ordinarily follow the party that substantially succeeds, assessed by reference to the relief obtained and the circumstances…
|
|
| 27 Jun 2019 |
[2019] EWHC 1588 (TCC)
For limitation under section 14A of the Limitation Act 1980, knowledge concerns the damage claimed and the broad facts linking it to the defendant’s act or…
|
|
| 25 Jun 2019 |
[2019] EWHC 1591 (TCC)
In adjudication enforcement proceedings, the court will ordinarily enforce an adjudicator’s decision under the statutory construction adjudication scheme. A…
|
5 |
| 17 Jun 2019 |
[2019] EWHC 1315 (TCC)
In an application to lift the automatic suspension of a public procurement, the court applies the Public Contracts Regulations 2015 and the American Cyanamid…
|
7 |
| 10 Jun 2019 |
[2019] EWHC 1432 (TCC)
Security for costs against a counterclaiming defendant depends on the substance of the dispute, not merely the form of the pleadings. A counterclaim is not a…
|
|
| 24 May 2019 |
[2019] EWHC 1291 (TCC)
A contracting authority has a broad discretion to abandon a procurement before contract award. That discretion does not, without clear statutory authority…
|
4 |
| 17 May 2019 |
[2019] EWHC 1205 (TCC)
A company voluntary arrangement may bind a creditor without preventing the company from pursuing or defending claims. However, where an adjudicator’s decision…
|
2 |
| 15 May 2019 |
[2019] EWHC 1229 (TCC)
Cause of action estoppel and merger bar a second action based on the same cause of action. The comparison concerns the causes of action, not the particular…
|
7 |
| 13 May 2019 |
[2019] EWHC 1612 (TCC)
An adjudicator’s decision should ordinarily be enforced by summary judgment while it remains valid and enforceable. The court will not examine whether the…
|
|
| 10 May 2019 |
[2019] EWHC 1188 (TCC)
An adjudicator may reach conclusions on programme logic, the critical path and an extension of time where those matters arise from the dispute referred and the…
|
2 |
| 9 May 2019 |
[2019] EWHC 1134 (TCC)
A builder ordinarily owes no tortious duty to a purchaser in respect of the cost of repairing defective work where the loss is pure economic loss. The proposed…
|
|
| 8 May 2019 |
[2019] EWHC 1152 (TCC)
An adjudicator’s decision will ordinarily be enforced by summary judgment. The court does not reconsider its merits. Resistance is confined to exceptional…
|
|
| 3 May 2019 |
[2019] EWHC 1192 (TCC)
Part 7 adjudication-enforcement proceedings should ordinarily be dealt with promptly, even where related Part 8 proceedings concern the same adjudication or…
|
|
| 17 Apr 2019 |
[2019] EWHC 996 (TCC)
Adjudication decisions are ordinarily enforced summarily under the statutory construction adjudication scheme, reflecting the principle of temporary finality…
|
|
| 17 Apr 2019 |
[2019] EWHC 989 (TCC)
A contractual notice deeming defects to have been made good may conclusively end the contractual defects-liability machinery without conclusively determining…
|
|
| 17 Apr 2019 |
[2019] EWHC 945 (TCC)
Whether works amount to substantial demolition is a question of fact and degree. It is not necessary that every part of a building be removed. Removing enough…
|
|
| 15 Apr 2019 |
[2019] EWHC 2134 (TCC)
Enforcement of an adjudicator’s decision will ordinarily follow the pay now, litigate later principle. The court will not reconsider the adjudicator’s…
|
|
| 5 Apr 2019 |
[2019] EWHC 831 (TCC)
A professional negligence claim concerning construction cost overruns requires proof that the professional fell below the standard of reasonable competence and…
|
|
| 2 Apr 2019 |
[2019] EWHC 819 (TCC)
Applications to amend are governed by a single balancing exercise. The court must decide whether the injustice to the applicant if permission is refused…
|
4 |
| 29 Mar 2019 |
[2019] EWHC 747 (TCC)
In adjudication enforcement proceedings, fraud may provide a defence only where it is a real defence to the adjudicated claim. Fraud must be supported by clear…
|
1 |
| 29 Mar 2019 |
[2019] EWHC 1155 (TCC)
A preliminary issue should ordinarily concern a question of law decided on agreed or assumed facts. The procedure is unsuitable where deciding the issue…
|
1 |
| 14 Mar 2019 |
[2019] EWHC 526 (TCC)
In assessing costs after a substantial damages claim produces a much smaller recovery, the court must identify the successful party by examining the litigation…
|
1 |
| 13 Mar 2019 |
[2019] EWHC 593 (TCC)
Contractual dispute-resolution provisions must be construed as a whole. Where a contract creates a specific and mandatory procedure for interface disputes, a…
|
|
| 13 Mar 2019 |
[2019] EWHC 574 (TCC)
Contractual performance representations concerning industrial machinery are construed in their commercial and factual context. A throughput representation may…
|
1 |
| 11 Mar 2019 |
[2019] EWHC 565 (TCC)
Contractual notice provisions are construed by their wording and commercial purpose. A notice need not plead every detail, but must identify the nature and…
|
7 |
| 8 Mar 2019 |
[2019] EWHC 711 (TCC)
The Technology and Construction Court will intervene in an ongoing adjudication by injunction or declaration only in rare or exceptional circumstances. A…
|
|
| 8 Mar 2019 |
[2019] EWHC 495 (TCC)
In successive adjudications, the critical comparison is between what the first adjudicator actually decided and what is later referred. A later dispute is not…
|
3 |
| 1 Mar 2019 |
[2019] EWHC 435 (TCC)
Contract formation is determined objectively from the parties’ words and conduct. A binding construction contract may arise even though only one party has…
|
|
| 28 Feb 2019 |
[2019] EWHC 515 (TCC)
In procurement challenges, an unsuccessful tenderer should promptly receive essential information and documents showing how the evaluation was actually carried…
|
1 |
| 27 Feb 2019 |
[2019] EWHC 549 (TCC)
Where procurement proceedings are governed by a statutory notice requirement, the claimant must identify the actual alleged breach by reference to the…
|
|
| 27 Feb 2019 |
[2019] EWHC 454 (TCC)
An architect providing design and project-management services must establish and maintain a sufficiently clear written brief. Design development and material…
|
|
| 27 Feb 2019 |
[2019] EWHC 442 (TCC)
A contract requiring joint implementation of software and related services may carry an implied duty of co-operation where performance cannot occur without…
|
|
| 26 Feb 2019 |
[2019] EWHC 369 (TCC)
Indemnity costs require conduct or circumstances taking the case out of the norm. Unreasonableness must be at a high degree; conduct that is merely wrong…
|
|
| 20 Feb 2019 |
[2019] EWHC 318 (TCC)
An employer required to make an immediate payment under the Housing Grants, Construction and Regeneration Act 1996 after failing to serve a Payment Notice or…
|
5 |
| 15 Feb 2019 |
[2019] EWHC 257 (TCC)
Costs remain discretionary despite the general rule that they follow success. The court may make a group or proportionate costs order where legally separate…
|
1 |
| 11 Feb 2019 |
[2019] EWHC 419 (TCC)
Where procurement proceedings concern an urgent public interest issue and an early decision is required, the court may order an expedited trial, even though…
|
|
| 7 Feb 2019 |
[2019] EWHC 205 (TCC)
Interest on damages is compensatory. It reflects the claimant’s loss from being kept out of money that ought to have been paid, rather than the defendant’s…
|
1 |
| 5 Feb 2019 |
[2019] EWHC 384 (TCC)
On an application to enforce an adjudicator’s decision, the court applies the ordinary CPR 24.2 test. Jurisdictional objections may be decided summarily where…
|
|
| 4 Feb 2019 |
[2019] EWHC 169 (TCC)
An adjudicator may correct a decision under the statutory slip rule where the correction removes a clerical or arithmetical error and gives effect to the…
|
2 |
| 31 Jan 2019 |
[2019] EWHC 142 (TCC)
A repairing covenant may require reinstatement, replacement or renewal where necessary, including remediation of inherent or design defects. Disrepair is…
|
3 |
| 30 Jan 2019 |
[2019] EWHC 234 (TCC)
Adjudication-related proceedings do not automatically qualify for the expedited procedure used for adjudication enforcement. A party must not issue overlapping…
|
1 |
| 30 Jan 2019 |
[2019] EWHC 140 (TCC)
A building warranty policy covering flats and common parts may require the insurer to meet the reasonable cost of permanent remedial works, even where the…
|
1 |
| 29 Jan 2019 |
[2019] EWHC 413 (TCC)
In adjudication enforcement proceedings, a party that wishes to challenge jurisdiction must raise the objection appropriately and clearly. A vague general…
|
|
| 29 Jan 2019 |
[2019] EWHC 136 (TCC)
In construction adjudication, a dispute about the valuation of a final account may be referred before any entitlement to payment has arisen. A fair hearing is…
|
|
| 28 Jan 2019 |
[2019] EWHC 187 (TCC)
On an application for interim injunctive relief, the court may order both preservation and delivery up of data where there is a serious issue to be tried and…
|
|
| 21 Jan 2019 |
[2019] EWHC 141 (TCC)
A partnership may be named in adjudication proceedings by the business name under which it contracted and carried on business. The absence of the partners’…
|
|
| 18 Jan 2019 |
[2019] EWHC 61 (TCC)
In procurement, equal treatment does not require identical treatment of bidders whose relevant competitive positions differ. A difference must be assessed in…
|
3 |
| 16 Jan 2019 |
[2019] EWHC 206 (TCC)
Summary judgment or strike-out should be granted only where the claim is fanciful, discloses no viable cause of action, or can be resolved confidently without…
|
|
| 9 Jan 2019 |
[2019] EWHC 3139 (TCC)
A contractual change to the address for payment applications must be effected in accordance with the contract and communicated in a manner that objectively…
|