High Court: Technology and Construction Court judgments, 2019

84 judgments, newest first. Open any case for its summary, the legal points it decides and how later courts have treated it.

Date Case Cited by
20 Dec 2019
[2019] EWHC 3585 (TCC)
On an application to lift an automatic suspension in a procurement challenge, the court applies the American Cyanamid approach. It asks whether there is a…
6
19 Dec 2019
[2019] EWHC 3526 (TCC)
An indemnity costs order requires conduct or circumstances taking the case outside the norm. The court must consider all the circumstances, including the…
17 Dec 2019
[2019] EWHC 3488 (TCC)
Where parties’ conduct temporarily prevents reliance on a contractual deadline, the resulting estoppel may postpone the start of the contractual period without…
16 Dec 2019
[2019] EWHC 3482 (TCC)
Part 8 declaratory relief is discretionary. In adjudication-related proceedings, the court should grant declarations only where the issue can fairly be…
2 Dec 2019
[2019] EWHC 3225 (TCC)
An agreement may contain separate offers, some capable of acceptance and others amounting only to invitations to negotiate. Whether a contract was formed, and…
22 Nov 2019
[2019] EWHC 3337 (TCC)
A trial date in the Technology and Construction Court should be vacated only in exceptional circumstances. Increased disclosure volume will not ordinarily…
18 Nov 2019
[2019] EWHC 3060 (TCC)
A contractual assessment clause permitting recovery of overpayments may operate alongside the interim-payment and final-account machinery in a construction…
2
15 Nov 2019
[2019] EWHC 3727 (TCC)
Where a contract provides a termination payment, the client cannot avoid that payment by making termination inevitable through selling the relevant property…
11 Nov 2019
[2019] EWHC 3028 (TCC)
Where a claimant beats its own Part 36 offer, the prescribed consequences ordinarily follow unless it would be unjust to impose them. The regime is intended to…
31 Oct 2019
[2019] EWHC 3210 (TCC)
Where a claimant’s Civil Procedure Rules 1998 Part 36 offer is at least as advantageous as the judgment obtained, the prescribed consequences should follow…
31 Oct 2019
[2019] EWHC 2846 (TCC)
A contractual obligation must be construed in its factual context at the time of agreement. A party cannot use anticipated difficulties in obtaining a future…
30 Oct 2019
[2019] EWHC 2922 (TCC)
On an application to adjourn a fixed trial, the court must balance the legitimate expectation that the fixture will be maintained against the risk of an unfair…
15 Oct 2019
[2019] EWHC 2722 (TCC)
In commercial litigation, the party receiving a substantial payment will ordinarily be treated as the overall successful party for costs purposes. The starting…
10 Oct 2019
[2019] EWHC 3589 (TCC)
In procurement proceedings involving an automatic suspension, an awarding authority seeking discharge should provide sufficiently detailed reasons and…
1
10 Oct 2019
[2019] EWHC 2651 (TCC)
An adjudication decision obtained by a company in insolvent liquidation will ordinarily be unenforceable because adjudication is incompatible with insolvency…
6
10 Oct 2019
[2019] EWHC 2601 (TCC)
A dispute for adjudication crystallises when the claim has been communicated and the responding party has had a reasonable opportunity to consider it, and it…
2 Oct 2019
[2019] EWHC 2547 (TCC)
In a hybrid construction contract, the parties may agree one payment regime covering both construction and non-construction operations. A payment notice need…
2
25 Sep 2019
[2019] EWHC 2497 (TCC)
Under a joint venture agreement reflecting an NEC target-cost contract, interim reimbursement of a party’s properly identified Works Part Costs is not subject…
24 Sep 2019
[2019] EWHC 2504 (TCC)
In a summary assessment of costs, recoverable costs are limited to costs reasonably and proportionately incurred and reasonable and proportionate in amount.…
3
22 Aug 2019
[2019] EWHC 2188 (TCC)
Contractual rights constitute possessions under Article 1 of the First Protocol only where they have an identifiable and readily realisable monetary value. A…
16 Aug 2019
[2019] EWHC 2246 (TCC)
A contractual tiered dispute-resolution clause may create an enforceable condition precedent to court proceedings. The procedure must be expressed in mandatory…
3
13 Aug 2019
[2019] EWHC 2216 (TCC)
Damages for breach of warranty in a share purchase agreement may be assessed by the reduction in the value of the acquired companies resulting from the breach…
13 Aug 2019
[2019] EWHC 2212 (TCC)
Under section 103(5) of the Arbitration Act 1996, enforcement of a New York Convention award may be adjourned while the outcome of foreign setting-aside…
1
13 Aug 2019
[2019] EWHC 2211 (TCC)
Challenges under the Public Contracts Regulations 2015 must be brought within the prescribed period once the economic operator knows, or ought to know, that…
8 Aug 2019
[2019] EWHC 2360 (TCC)
For the purposes of the Housing Grants Construction and Regeneration Act 1996, delivery of materials is excluded from “construction operations” unless the…
8 Aug 2019
[2019] EWHC 2184 (TCC)
Settlement agreements made by an agent acting for a financially pressured employer remain enforceable unless fraud, bribery, dishonest assistance, undue…
7 Aug 2019
[2019] EWHC 2170 (TCC)
In adjudication enforcement proceedings, an adjudicator’s error in addressing evidence or a sub-issue will ordinarily not make the decision unenforceable if…
4
31 Jul 2019
[2019] EWHC 2109 (TCC)
A professional designer responsible for structural fill and associated drainage must design the works as an integrated system, including the consequences of…
31 Jul 2019
[2019] EWHC 2047 (TCC)
Public-law challenges to the validity of administrative decisions must generally be brought promptly by judicial review. That principle does not convert an…
1
30 Jul 2019
[2019] EWHC 2078 (TCC)
An application made before expiry of the permitted period to extend time for complying with a court order is governed by Civil Procedure Rules 1998, rule…
3
26 Jul 2019
[2019] EWHC 2050 (TCC)
The first ground for a declaration of ineffectiveness under the Public Contracts Regulations 2015 is concerned with whether the required prior contract notice…
17 Jul 2019
[2019] EWHC 1876 (TCC)
On an application to enforce an adjudicator’s decision by summary judgment, the respondent need only show a real prospect of success. That means a prospect…
9 Jul 2019
[2019] EWHC 1787 (TCC)
A notice of adjudication must be construed objectively as a whole, against its contractual setting, and by asking how it would have informed a reasonable…
1
8 Jul 2019
[2019] EWHC 1769 (TCC)
In construing a contractual payment provision, the natural and ordinary meaning of default was a failure to comply with a contractual obligation. The court…
1
28 Jun 2019
[2019] EWHC 1659 (TCC)
A contractual choice of court clause may operate alongside adjudication and arbitration provisions where the contract does not clearly replace those…
1
28 Jun 2019
[2019] EWHC 1647 (TCC)
Costs of an interim application ordinarily follow the party that substantially succeeds, assessed by reference to the relief obtained and the circumstances…
27 Jun 2019
[2019] EWHC 1588 (TCC)
For limitation under section 14A of the Limitation Act 1980, knowledge concerns the damage claimed and the broad facts linking it to the defendant’s act or…
25 Jun 2019
[2019] EWHC 1591 (TCC)
In adjudication enforcement proceedings, the court will ordinarily enforce an adjudicator’s decision under the statutory construction adjudication scheme. A…
5
17 Jun 2019
[2019] EWHC 1315 (TCC)
In an application to lift the automatic suspension of a public procurement, the court applies the Public Contracts Regulations 2015 and the American Cyanamid…
7
10 Jun 2019
[2019] EWHC 1432 (TCC)
Security for costs against a counterclaiming defendant depends on the substance of the dispute, not merely the form of the pleadings. A counterclaim is not a…
24 May 2019
[2019] EWHC 1291 (TCC)
A contracting authority has a broad discretion to abandon a procurement before contract award. That discretion does not, without clear statutory authority…
4
17 May 2019
[2019] EWHC 1205 (TCC)
A company voluntary arrangement may bind a creditor without preventing the company from pursuing or defending claims. However, where an adjudicator’s decision…
2
15 May 2019
[2019] EWHC 1229 (TCC)
Cause of action estoppel and merger bar a second action based on the same cause of action. The comparison concerns the causes of action, not the particular…
7
13 May 2019
[2019] EWHC 1612 (TCC)
An adjudicator’s decision should ordinarily be enforced by summary judgment while it remains valid and enforceable. The court will not examine whether the…
10 May 2019
[2019] EWHC 1188 (TCC)
An adjudicator may reach conclusions on programme logic, the critical path and an extension of time where those matters arise from the dispute referred and the…
2
9 May 2019
[2019] EWHC 1134 (TCC)
A builder ordinarily owes no tortious duty to a purchaser in respect of the cost of repairing defective work where the loss is pure economic loss. The proposed…
8 May 2019
[2019] EWHC 1152 (TCC)
An adjudicator’s decision will ordinarily be enforced by summary judgment. The court does not reconsider its merits. Resistance is confined to exceptional…
3 May 2019
[2019] EWHC 1192 (TCC)
Part 7 adjudication-enforcement proceedings should ordinarily be dealt with promptly, even where related Part 8 proceedings concern the same adjudication or…
17 Apr 2019
[2019] EWHC 996 (TCC)
Adjudication decisions are ordinarily enforced summarily under the statutory construction adjudication scheme, reflecting the principle of temporary finality…
17 Apr 2019
[2019] EWHC 989 (TCC)
A contractual notice deeming defects to have been made good may conclusively end the contractual defects-liability machinery without conclusively determining…
17 Apr 2019
[2019] EWHC 945 (TCC)
Whether works amount to substantial demolition is a question of fact and degree. It is not necessary that every part of a building be removed. Removing enough…
15 Apr 2019
[2019] EWHC 2134 (TCC)
Enforcement of an adjudicator’s decision will ordinarily follow the pay now, litigate later principle. The court will not reconsider the adjudicator’s…
5 Apr 2019
[2019] EWHC 831 (TCC)
A professional negligence claim concerning construction cost overruns requires proof that the professional fell below the standard of reasonable competence and…
2 Apr 2019
[2019] EWHC 819 (TCC)
Applications to amend are governed by a single balancing exercise. The court must decide whether the injustice to the applicant if permission is refused…
4
29 Mar 2019
[2019] EWHC 747 (TCC)
In adjudication enforcement proceedings, fraud may provide a defence only where it is a real defence to the adjudicated claim. Fraud must be supported by clear…
1
29 Mar 2019
[2019] EWHC 1155 (TCC)
A preliminary issue should ordinarily concern a question of law decided on agreed or assumed facts. The procedure is unsuitable where deciding the issue…
1
14 Mar 2019
[2019] EWHC 526 (TCC)
In assessing costs after a substantial damages claim produces a much smaller recovery, the court must identify the successful party by examining the litigation…
1
13 Mar 2019
[2019] EWHC 593 (TCC)
Contractual dispute-resolution provisions must be construed as a whole. Where a contract creates a specific and mandatory procedure for interface disputes, a…
13 Mar 2019
[2019] EWHC 574 (TCC)
Contractual performance representations concerning industrial machinery are construed in their commercial and factual context. A throughput representation may…
1
11 Mar 2019
[2019] EWHC 565 (TCC)
Contractual notice provisions are construed by their wording and commercial purpose. A notice need not plead every detail, but must identify the nature and…
7
8 Mar 2019
[2019] EWHC 711 (TCC)
The Technology and Construction Court will intervene in an ongoing adjudication by injunction or declaration only in rare or exceptional circumstances. A…
8 Mar 2019
[2019] EWHC 495 (TCC)
In successive adjudications, the critical comparison is between what the first adjudicator actually decided and what is later referred. A later dispute is not…
3
1 Mar 2019
[2019] EWHC 435 (TCC)
Contract formation is determined objectively from the parties’ words and conduct. A binding construction contract may arise even though only one party has…
28 Feb 2019
[2019] EWHC 515 (TCC)
In procurement challenges, an unsuccessful tenderer should promptly receive essential information and documents showing how the evaluation was actually carried…
1
27 Feb 2019
[2019] EWHC 549 (TCC)
Where procurement proceedings are governed by a statutory notice requirement, the claimant must identify the actual alleged breach by reference to the…
27 Feb 2019
[2019] EWHC 454 (TCC)
An architect providing design and project-management services must establish and maintain a sufficiently clear written brief. Design development and material…
27 Feb 2019
[2019] EWHC 442 (TCC)
A contract requiring joint implementation of software and related services may carry an implied duty of co-operation where performance cannot occur without…
26 Feb 2019
[2019] EWHC 369 (TCC)
Indemnity costs require conduct or circumstances taking the case out of the norm. Unreasonableness must be at a high degree; conduct that is merely wrong…
20 Feb 2019
[2019] EWHC 318 (TCC)
An employer required to make an immediate payment under the Housing Grants, Construction and Regeneration Act 1996 after failing to serve a Payment Notice or…
5
15 Feb 2019
[2019] EWHC 257 (TCC)
Costs remain discretionary despite the general rule that they follow success. The court may make a group or proportionate costs order where legally separate…
1
11 Feb 2019
[2019] EWHC 419 (TCC)
Where procurement proceedings concern an urgent public interest issue and an early decision is required, the court may order an expedited trial, even though…
7 Feb 2019
[2019] EWHC 205 (TCC)
Interest on damages is compensatory. It reflects the claimant’s loss from being kept out of money that ought to have been paid, rather than the defendant’s…
1
5 Feb 2019
[2019] EWHC 384 (TCC)
On an application to enforce an adjudicator’s decision, the court applies the ordinary CPR 24.2 test. Jurisdictional objections may be decided summarily where…
4 Feb 2019
[2019] EWHC 169 (TCC)
An adjudicator may correct a decision under the statutory slip rule where the correction removes a clerical or arithmetical error and gives effect to the…
2
31 Jan 2019
[2019] EWHC 142 (TCC)
A repairing covenant may require reinstatement, replacement or renewal where necessary, including remediation of inherent or design defects. Disrepair is…
3
30 Jan 2019
[2019] EWHC 234 (TCC)
Adjudication-related proceedings do not automatically qualify for the expedited procedure used for adjudication enforcement. A party must not issue overlapping…
1
30 Jan 2019
[2019] EWHC 140 (TCC)
A building warranty policy covering flats and common parts may require the insurer to meet the reasonable cost of permanent remedial works, even where the…
1
29 Jan 2019
[2019] EWHC 413 (TCC)
In adjudication enforcement proceedings, a party that wishes to challenge jurisdiction must raise the objection appropriately and clearly. A vague general…
29 Jan 2019
[2019] EWHC 136 (TCC)
In construction adjudication, a dispute about the valuation of a final account may be referred before any entitlement to payment has arisen. A fair hearing is…
28 Jan 2019
[2019] EWHC 187 (TCC)
On an application for interim injunctive relief, the court may order both preservation and delivery up of data where there is a serious issue to be tried and…
21 Jan 2019
[2019] EWHC 141 (TCC)
A partnership may be named in adjudication proceedings by the business name under which it contracted and carried on business. The absence of the partners’…
18 Jan 2019
[2019] EWHC 61 (TCC)
In procurement, equal treatment does not require identical treatment of bidders whose relevant competitive positions differ. A difference must be assessed in…
3
16 Jan 2019
[2019] EWHC 206 (TCC)
Summary judgment or strike-out should be granted only where the claim is fanciful, discloses no viable cause of action, or can be resolved confidently without…
9 Jan 2019
[2019] EWHC 3139 (TCC)
A contractual change to the address for payment applications must be effected in accordance with the contract and communicated in a manner that objectively…