Summary
Extrapolation from representative sampling is permissible in principle in professional negligence and construction claims. The claimant must still prove, on the balance of probabilities, that the sample supports the inference sought. The sample must be sufficiently representative, and the inference may be defeated by rebuttal evidence or by features showing that the alleged breaches or losses are not comparable. A global claim, without strict attribution of every loss to a specific breach, is also permissible in principle, subject to proof and the evidential difficulties of the particular case. Strike out or summary judgment is appropriate only where the necessary inference is one that no reasonable trial judge could draw.
Factual background
Standard Life brought a professional negligence claim concerning a major building development against members of the design team. It claimed approximately £38.1 million for additional variations and contractor’s loss and expense. Approximately £25.2 million of that sum was based on extrapolation from a sample of about 122 variations and selected delay notices.
The fourth, fifth and sixth defendants applied under the Civil Procedure Rules 1998 to strike out the extrapolated claim or obtain summary judgment. They argued that the sample was unrepresentative, that the pleading did not identify the breaches or causation sufficiently, and that the claim reversed the burden of proof. The central issues were whether extrapolation and a global claim were legally permissible, and whether the pleaded inferences were so untenable that the claim should be disposed of before trial.
Held
- Applications refused. The defendants failed to show that the whole extrapolated claim disclosed no reasonable grounds, was an abuse of process, or had no real prospect of success. The pleading was difficult and untidy, but it was comprehensible and identified the case to be met.
- The court rejected the submission that the claimant had reversed the burden of proof. An invitation to draw inferences from primary facts may place an evidential burden on the defendant, but the legal burden remains with the claimant. The claimant must prove breach and causation on the balance of probabilities.
- Extrapolation from sampling is permissible in principle. It is not confined to cases involving a formally “systemic” breach. The decisive question is whether the sample and the surrounding evidence justify the inference that the same type of negligence caused loss outside the sample. A case involving repeated failures to read, report or control costs may in principle support extrapolation even if there was no operating system that reproduced an identical error.
- Extrapolation is unsuitable where the alleged breach concerns matters outside a defendant’s remit, or where the differences between the sampled and extrapolated work make the proposed inference manifestly impermissible. Some pleaded examples attributing responsibility to SGA or Cundall for matters outside their responsibility were therefore unsustainable. The court could not, however, conclude at the interlocutory stage that every extrapolated item was bad.
- A global claim is permissible in principle, even without strict attribution of every item of loss to a specific breach. The issue is whether the claimant can prove the resulting loss. The loss and expense claim was therefore not demurrable merely because some amounts were not directly linked to individual breaches.
- Proportionality was a material consideration. A trial of thousands of individual variations would be impracticable and disproportionate. The court proposed further sampling, including samples selected by the defendants, fuller tabulation of breach, causation, quantum and apportionment, and a fresh composite pleading. The claimant was warned that new, unpleaded allegations could not be introduced at trial.
The court’s approach to earlier authorities
Available to signed-in members.
Appellate history
First instance decision. No appellate history was stated in the judgment.
Appeal route
- This judgment [2020] EWHC 3419 (TCC) High Court (Technology and Construction Court)
- Appealed to[2021] EWCA Civ 1793
Key cases cited
14 authorities cited.
- O'Brien (Respondent) v. Chief Constable of South Wales Police (Appellant) [2005] UKHL 26
- Laughton v Shalaby [2014] EWCA Civ 1450
- THE ROYAL BROMPTON HOSPITAL NATIONAL HEALTH SERVICE TRUST v HAMMOND AND ORS [2001] Lloyd's Rep PN 526
- Imperial Chemical Industries Ltd v Merit Merrell Technology Ltd [2017] EWHC 1763 (TCC)
- Amey LG Ltd v Cumbria County Council [2016] EWHC 2856 (TCC)
- Walter Lilly & Company Ltd v Mackay & Anor [2012] EWHC 1773 (TCC)
- ACD (Landscape Architects) Ltd v Overall & Anor [2012] EWHC 100 (TCC)
- Pantelli Associates Ltd v Corporate City Developments Number Two Ltd [2010] EWHC 3189 (TCC)
- Towler v Wills [2010] EWHC 1209 (Comm)
- Easyair Ltd (t/a Openair) v Opal Telecom Ltd [2009] EWHC 339 (Ch)
- Nomura International Plc v Granada Group Ltd & Ors [2007] EWHC 642 (Comm)
- Atos Consulting Ltd v Avis Europe Plc [2005] EWHC 982 (TCC)
- Attorney General v Barker [2000] FLR 759
- Sansom v Metcalfe Hambleton [1998] PNLR 542
Sign in to see how the court treated each authority. A free account is enough.
Cases citing this case
2 later cases · 2 positive
Most senior citing decisions:
- David Alan Kyte v McLaren Automotive Limited & Anor [2026] EWHC 1126 (TCC) followed
- Advanced Control Systems Inc v Efacec Engenharia e Sistemas SA [2021] EWHC 573 (TCC) applied
Sign in for the full treatment table. A free account is enough.