Summary
In construing a complex commercial contract, the court must ascertain the parties’ intention from the language used in its contractual and commercial context. An output specification may help define both the scope of the works and the standard to which they must be performed.
Where declarations are sought in the abstract, without particularised breaches, the court should exercise caution. A certificate may be conclusive for specified matters while leaving other contractual obligations capable of breach.
Factual background
The claimant special purpose vehicle and the defendant construction company entered back-to-back agreements for a local authority sheltered-housing PFI project. The dispute concerned the defendant’s obligations for refurbishment works, particularly design life, residual life expectancy, external envelopes and the effect of certificates of availability.
The claimant sought declarations imposing specified future life expectancies and continuing standards. The defendant contended that its refurbishment obligations principally concerned the condition of the dwellings at the dates of the relevant certificates. The court also considered whether the output specification defined the scope of the works and whether certificates were conclusive of all obligations.
Held
The court substantially preferred the defendant’s interpretation and refused the claimant’s declarations insofar as they imposed obligations to undertake works merely to secure specified future residual life expectancies.
- Design life and refurbishment works. Sections 2.9 and 2.10 of Part A of the Output Specification applied to new-build elements, including new-build elements incorporated into refurbishment works. They did not require the defendant to replace sound existing elements, or to carry out otherwise unnecessary works, solely to ensure a specified residual life at the end of the wider project.
- Scope of works. The output specification formed part of the material from which the scope of the works was determined. Its relevance was not limited to prescribing the standard of separately defined works. The scope had to be derived from the construction sub-contract read as a whole and in the context of the related project contracts.
- Certificates of availability. A certificate was conclusive under clause 20.3.3 as to the matters specified there, including achievement of the relevant availability certification requirements at the certificate date. It did not extinguish obligations outside those matters.
- External envelope. The obligations under sections 4.1.7 and 5.1.7 required the refurbishment dwellings to be in the specified condition at the relevant certificate date, without a separate obligation to ensure that condition persisted for a particular further period.
- Declarations. The court declined to make declarations concerning matters no longer in dispute, recording the parties’ agreement instead. The claimant’s declarations were refused where they misstated or incompletely stated the contractual effect. The defendant’s declaration that it did not warrant that the claimant would achieve, or be able to achieve, the handback standard was granted.
The court’s approach to earlier authorities