Indus Powertech Inc. v Echjay Industries Private Limited

[2026] EWHC 1482 (Comm)

Summary

When deciding whether to assess costs summarily, the court may consider both the amount claimed and the complexity of disputes about recoverability. The £250,000 figure in the Commercial Court Guide is a guide, not a limit on the court’s power. Detailed assessment is the default where a claim is very substantial and contested items need closer investigation.

A payment on account of costs should be reasonable in all the circumstances and allow a margin for error in estimating likely recovery. In exercising its discretion over that payment, the court may take account of an opposing party’s current entitlement under a binding arbitration award, even though the award has not been formally recognised for enforcement in England. The court must also consider the risk of double recovery and any continuing uncertainty in the arbitration.

Factual background

Indus Powertech Inc. successfully challenged an arbitration award made in favour of Echjay Industries Private Limited. The court remitted certain issues to the arbitral tribunal. Echjay accepted that it should pay Indus’s costs of the English arbitration claim, while the tribunal would decide the costs of the arbitration itself.

The court had to decide whether to assess Indus’s court costs summarily or order detailed assessment, what payment on account should be made, and whether Echjay could set its undisputed entitlement under the award against the costs payable. The arbitration had not concluded, and the remitted issues and arbitration costs remained unresolved.

Held

Costs of the arbitration claim ordered to be assessed on the standard basis if not agreed. The court proposed a payment on account of £85,000, conditional on a suitable undertaking from Echjay, and declined to make a final declaration about set-off.

  1. Summary assessment was inappropriate. The £250,000 figure in the Commercial Court Guide was a guide to when summary assessment might be suitable, not a limit on the court’s power. Where the costs claimed were very substantial, detailed assessment was the default. Here, the claim approached three times that figure and disputes about the recoverability of particular categories warranted closer investigation ([8]–[10]).

  2. Under rule 44.2(8) of the Civil Procedure Rules 1998, the court ordinarily orders a payment on account when costs are to be assessed later, unless there is good reason otherwise. The payment need not be confined to an irreducible minimum. It should be reasonable in all the circumstances and allow a margin for error in estimating likely recovery: Excalibur Ventures LLC v Texas Keystone Inc [2015] EWHC 566 (Comm). The high hourly rates, possible duplication and disputes about whether certain work constituted costs of the claim justified a substantial allowance against the amount claimed ([11], [15]–[18]).

  3. The court had a wide discretion over the payment on account. It could take account of Echjay’s undisputed current entitlement under the binding award without prior leave to enforce it under section 66 of the Arbitration Act 1996. Formal recognition was required before the court’s enforcement powers became available, but it was not a precondition to considering the award when exercising the costs discretion ([28]–[29], [32]).

  4. The tribunal’s eventual decisions could change the parties’ respective entitlements, and Echjay could not receive the benefit of its award twice. A final declaration about set-off was therefore inappropriate on the limited legal submissions available. The court proposed an allowance for Echjay’s present entitlement when fixing the interim payment, subject to an undertaking protecting against double recovery. The undertaking would need to accommodate later changes, including the result of detailed assessment. Subject to further order, the proposed payment was to be made within 21 days. The court left any substantive set-off issue and future exercise of discretion open ([30]–[35]).

The court’s approach to earlier authorities

Available to signed-in members.

Appellate history

On 10 April 2026 the High Court allowed Indus’s challenge to the arbitration award and remitted certain issues to the tribunal: [2026] EWHC 827 (Comm) . This ruling determined consequential costs matters.

Other judgments in these proceedings

2 judgments in these proceedings, earliest first. Linked by the shared court number CL-2025-000156, and by appeals.

  1. 10 April 2026Indus Powertech Inc v Echjay Industries Private Limited[2026] EWHC 827 (Comm) · High Court (Commercial Court)
  2. 15 June 2026Indus Powertech Inc. v Echjay Industries Private Limited[2026] EWHC 1482 (Comm) · High Court (Commercial Court) · this judgment

Key cases cited

2 authorities cited.

Sign in to see how the court treated each authority. A free account is enough.

Cases citing this case

Available to signed-in members.