Persimmon Homes Limited v Harding Estates (East Anglia) Limited & Anor

[2026] EWHC 2481 (Ch)

Summary

On a summary judgment application, the court may decide a short question of construction where it has the evidence needed for a proper determination and the parties have had an opportunity to address it. It must otherwise avoid a mini-trial and consider evidence reasonably expected to be available at trial.

Whether a communication seeks contractual approval depends on its meaning in its commercial and contractual context. Under an agreement providing a formal procedure for requests and deemed approval, an express written request was required. Progress updates and invitations to comment, accompanied by drawings, did not suffice. An extension of time also depended on a causal connection between the stipulated withholding or delay of approval and the delay to the works.

Factual background

Persimmon Homes Limited bought development land from Harding Estates (East Anglia) Limited. HIM Properties Limited, the owner of nearby land, was also a party to the sale agreement. Persimmon undertook to procure infrastructure and drainage works serving the properties within two years of completion, subject to an extension where unreasonable withholding or delay of a required approval caused delay.

The works were not completed by the contractual deadline. Persimmon sought declarations and an injunction, contending that it was entitled to an extension because approval of a proposed relocation of an attenuation pond had been unreasonably withheld or delayed. It relied on four emails sent to a former contact at Harding and on subsequent communications.

The defendants counterclaimed and applied for summary judgment on liability for failure to complete the works in time. The issues included whether the emails requested approval and whether any withholding or delay of approval caused delay to the works. The application for an interim payment was deferred.

Held

Summary judgment granted on liability. Persimmon had no real prospect of establishing that an entitlement to an extension of time prevented its failure to complete the works by the contractual deadline from being a breach. There was no other compelling reason for the liability issue to be tried. Quantum remained for trial, and the interim payment application was to be determined at a further hearing.

The court applied the summary judgment principles restated in Amershi v Leslie [2023 EWHC 168 (KB). A realistic prospect must have substance, and the court must avoid a mini-trial while considering evidence reasonably expected at trial. A short point of construction may be decided where the necessary evidence is before the court and the parties have had an opportunity to address it: EasyAir Limited (Trading as OpenAir) v Opal Telecom Limited [2009] EWHC 339(Ch).

Whether the highway authority had required, or reasonably required, the proposed pond location was unsuitable for summary determination. It called for investigation and might require expert evidence. The court nevertheless could determine the meaning of the four emails. Read in their commercial and contractual context, they provided progress updates and invited questions or comments; they did not request approval of the pond’s relocation. The proposed location’s appearance in linked drawings did not change their meaning.

The agreement treated approval as a formal matter. Its machinery provided for a further request and deemed approval after a failure to respond. In that context, a request for approval had to be express and in writing. An email could be used, and a request for approval was not a notice subject to the agreement’s separate notice-service provision. Relocation was not routine because it could affect development of the defendants’ retained land.

Separately, Persimmon had no realistic prospect of establishing that unreasonable withholding or delay of approval caused the relevant delay. Contemporaneous correspondence attributed the delay to the highway approval process and showed that the works had continued to be progressed. Persimmon’s failure to complete on time was a distinct breach which Harding had not brought about. The court would hear counsel on consequential relief and the form of order.

The court’s approach to earlier authorities

Available to signed-in members.

Appellate history

The defendants applied for summary judgment on their counterclaim and an interim payment. The court determined the summary judgment application first and deferred the interim payment application to a further hearing.

Cases citing this case

Available to signed-in members.