Summary
For the time limit under section 106(2) of the Procurement Act 2023, constructive knowledge is assessed by reference to a reasonably well-informed and normally diligent tenderer. A supplier cannot rely on its own inactivity to postpone the date when it ought to have known of circumstances giving rise to a claim. The date depends on the circumstances, including the availability of notices and tender documents.
The court may extend time under section 106(3) for a good reason, assessed broadly in all the circumstances. A short delay and the absence of contract award do not themselves explain a failure to issue in time.
In considering interim relief under section 102, the court balances all relevant statutory factors. No factor has automatic priority, and its weight depends on the particular case.
Factual background
Verity Healthcare Limited, a provider of regulated homecare services, challenged a condition in Cambridgeshire County Council’s procurement for a homecare framework. The condition required suppliers to hold a Care Quality Commission rating of Good or above. Verity did not hold that rating and alleged that the condition was disproportionate under section 22 of the Procurement Act 2023.
Verity applied for interim relief. The council applied for strike out or summary judgment, contending that the claim had been issued outside the 30-day period in section 106. The court considered when Verity knew or ought to have known of the circumstances giving rise to its claim, whether time should be extended, and, if necessary, whether interim relief should be granted.
Held
Summary judgment for the defendant. The claim was issued outside the statutory time limit. Verity had actual knowledge of the procurement by 18 July 2026. Although knowledge of a procurement was not necessarily knowledge of the circumstances giving rise to a claim, it was highly probable that its director had also become aware of the challenged condition when he accessed the portal that day. In any event, that was the latest date on which Verity ought to have known of it. The inconsistent and incomplete evidence justified an adverse inference, and there was no realistic prospect that further evidence would establish the asserted later date of knowledge (paras 70–73, 95).
Constructive knowledge under section 106(2) of the Procurement Act 2023 is assessed by the reasonably well-informed and normally diligent tenderer test. On the evidence, such a tenderer ought to have known of the procurement and condition when the tender notice was published on 15 July. Notifications could have been obtained and the condition identified in the linked documents. A contracting authority was not obliged to inform suppliers, including incumbents, which portal it intended to use. Cabinet Office guidance could alert tenderers to the expected approach, but could not determine when knowledge should be attributed in a particular case (paras 74–82).
No application for an extension of time had been made. If one had been pursued, it would have been refused. Section 106(3) calls for the same approach to good reason as the predecessor regulations. The court takes a broad, non-exhaustive view of the circumstances, including why proceedings were not issued in time. Verity had identified its complaint early and could have issued before expiry. The short extension sought and the fact that the contract had not been awarded did not supply a good reason. Delay in awaiting the council’s response did not justify the failure to issue in time (paras 84–94).
The assumed merits of the substantive challenge could not overcome the limitation defence. The court did not determine whether the conduct of the litigation independently justified strike out (paras 96–97).
Interim relief did not arise, but would have been refused. The court doubted whether section 102(1) authorised an order requiring the council to continue the procurement while disapplying the condition. Section 102(2) requires a balance of all relevant factors, with no statutory hierarchy. The court agreed with Parkingeye Ltd v Velindre University NHS Trust [2026] EWHC 1019 (TCC) on those points, but doubted its suggested requirement for a very persuasive countervailing public interest or overriding private interest before an automatic suspension is lifted. Here the claim was arguable but not particularly strong; damages were adequate, and delay would adversely affect the procurement and other suppliers. An application to anonymise individuals was not listed for hearing (paras 98–120, 123).
The court’s approach to earlier authorities
Available to signed-in members.
Appellate history
At first instance, Verity applied for interim relief and the council applied for strike out or summary judgment. A further application for anonymisation was not listed for hearing.
Cases on related points
- Bouygues (U.K.) Limited v Secretary of State for EducationRelies on 3 of the same authorities
- EXCESSION TECHNOLOGIES LIMITED v POLICE DIGITAL SERVICERelies on 2 of the same authorities
- Oracle Security Services Limited v Barts Health NHS Trust & AnorRelies on 2 of the same authorities
1 more related case for signed-in readers. A free account is enough.
Key cases cited
5 authorities cited.
- Begum v Maran (UK) Ltd [2021] EWCA Civ 326
- Parkingeye Limited v Velindre University NHS Trust & Anor [2026] EWHC 1019 (TCC)
- ACCESS FOR LIVING v LONDON BOROUGH OF LEWISHAM [2021] EWHC 3498 (TCC)
- SRCL Ltd v The National Health Service Commissioning Board (NHS) [2018] EWHC 1985 (TCC)
- Mermec UK Ltd v Network Rail Infrastructure Ltd [2011] EWHC 1847 (TCC)
Sign in to see how the court treated each authority. A free account is enough.
Cases citing this case
Available to signed-in members.