| Date | Case | Cited by |
|---|---|---|
| 7 Oct 2026 |
[2026] EWHC 2526 (TCC)
A later claimant’s independent cause of action under the Defective Premises Act 1972 is not barred merely because a closely connected company’s claim for the…
|
|
| 2 Oct 2026 |
[2026] EWHC 2501 (TCC)
The date of a Part 36 offer is not one of its terms. Rule 36.16(2) imposes a default prohibition on telling the trial judge the fact or terms of an offer…
|
|
| 29 Sep 2026 |
[2026] EWHC 2453 (TCC)
A terminal dilapidations claim is assessed first by the common-law cost of work needed to restore the covenanted condition, subject to mitigation and…
|
|
| 15 Sep 2026 |
[2026] EWHC 2319 (TCC)
Subject to jurisdiction and natural justice, the court takes a robust approach to enforcing an adjudicator’s decision. A decision remains binding if the…
|
|
| 3 Sep 2026 |
[2026] EWHC 2279 (TCC)
An application for pre-action disclosure cannot be served out of the jurisdiction against a foreign respondent for documents located abroad unless the…
|
|
| 28 Aug 2026 |
[2026] EWHC 2239 (TCC)
Under section 105(4) of the Procurement Act 2023, a contract award notice which does not provide accurate information is treated as unpublished for set-aside…
|
|
| 26 Aug 2026 |
[2026] EWHC 2223 (TCC)
On an application for summary judgment, the implication of contractual duties of good faith must be addressed by orthodox principles of contractual…
|
|
| 20 Aug 2026 |
[2026] EWHC 2209 (TCC)
In a public procurement, transparency requires tender criteria to be sufficiently clear for a reasonably well-informed and normally diligent tenderer to…
|
|
| 18 Aug 2026 |
[2026] EWHC 2189 (TCC)
Adjudication decisions should be enforced summarily. A court will refuse enforcement only where it is plain that the adjudicator decided a question outside the…
|
|
| 12 Aug 2026 |
[2026] EWHC 2154 (TCC)
An implied tender contract is not automatic and its terms depend on the documents and circumstances. Issuing an invitation to tender may create a limited…
|
|
| 10 Aug 2026 |
[2026] EWHC 2133 (TCC)
Where related proceedings in the Technology and Construction Court and the First-tier Tribunal raise common facts or issues, they may be jointly managed and…
|
|
| 4 Aug 2026 |
[2026] EWHC 2054 (TCC)
A subcontractor cannot enforce a project-bank-account payment clause under the Contracts (Rights of Third Parties) Act 1999 merely because it is a supplier or…
|
|
| 4 Aug 2026 |
[2026] EWHC 2047 (TCC)
For an urgent application supporting arbitration, the court may grant short-term relief under the Arbitration Act 1996 where the tribunal or emergency…
|
|
| 30 Jul 2026 |
[2026] EWHC 2003 (TCC)
On an application for summary judgment, the court must decide whether the claim has a realistic prospect of success and whether there is any other compelling…
|
|
| 27 Jul 2026 |
[2026] EWHC 1931 (TCC)
A contractual reference to developing an API can impose an obligation to make it available where the agreement, read as a whole, treats it as replacing a…
|
|
| 24 Jul 2026 |
[2026] EWHC 1824 (TCC)
An application for payment must satisfy statutory requirements and any more demanding contractual requirements. A self-billing arrangement does not remove the…
|
|
| 21 Jul 2026 |
[2026] EWHC 1845 (TCC)
In a procurement challenge, early specific disclosure is subject to a low but real threshold. The court should examine the pleaded case for relevance…
|
|
| 16 Jul 2026 |
[2026] EWHC 1796 (TCC)
Courts adopt a robust approach to enforcing adjudicators’ decisions by summary judgment. An adjudicator may find that neither party has proved its asserted…
|
|
| 15 Jul 2026 |
[2026] EWHC 1773 (TCC)
An insurer is liable only for insured damage occurring during the policy period and caused by the insured peril as defined by the policy. Earlier movement or…
|
|
| 13 Jul 2026 |
[2026] EWHC 1760 (TCC)
On an application to lift an automatic suspension in a procurement challenge, mere arguability that damages may be inadequate is insufficient. The claimant…
|
|
| 3 Jul 2026 |
[2026] EWHC 1678 (TCC)
Under section 44(3) of the Arbitration Act 1996, urgency is a jurisdictional requirement, and an order must be necessary to preserve evidence or assets. A…
|
|
| 23 Jun 2026 |
[2026] EWHC 1530 (TCC)
Under a contractual final-account conclusivity regime, the relevant statement must first be identified objectively, by reference to the document’s wording…
|
|
| 23 Jun 2026 |
[2026] EWHC 1509 (TCC)
A construction contract must provide a fixed period between the due date and the final date for payment. The due date may depend on an event, but the final…
|
1 |
| 22 Jun 2026 |
[2026] EWHC 1552 (TCC)
On an assessment of damages following default judgment, the claimant must prove the loss by evidence. The assessment proceeds on the basis of the liability…
|
|
| 19 Jun 2026 |
[2026] EWHC 2498 (TCC)
Construction pleadings must state enough facts for the defendant to understand and answer the case, and to prepare for trial. The required detail depends on…
|
|
| 19 Jun 2026 |
[2026] EWHC 1522 (TCC)
A principal may require a former agent to provide access to business documents stored on a personal device, subject to a proportionate process protecting…
|
|
| 12 Jun 2026 |
[2026] EWHC 1406 (TCC)
An adjudicator’s decision will generally be enforced where the adjudicator has addressed the dispute referred, even if the decision is alleged to be legally or…
|
|
| 11 Jun 2026 |
[2026] EWHC 1429 (TCC)
A statement of case must identify the facts, duties, breaches, causation and loss relied on against each defendant. General allegations of statutory…
|
|
| 10 Jun 2026 |
[2026] EWHC 1404 (TCC)
In adjudication enforcement proceedings, a court may refuse enforcement where the adjudicator decides a material issue on a factual or legal basis that neither…
|
1 |
| 5 Jun 2026 |
[2026] EWHC 1354 (TCC)
A post-Grenfell commercial lease requiring a landlord to keep a tall hotel building in good condition may require the removal and replacement of inherently…
|
|
| 28 May 2026 |
[2026] EWHC 1275 (TCC)
Where a pre-construction agreement precedes a later building contract, wording that contractual rights and liabilities are “subsumed into and subject to” the…
|
|
| 26 May 2026 |
[2026] EWHC 1260 (TCC)
Under the Civil Liability (Contribution) Act 1978, contribution requires the parties to be liable for the same damage. A company is not jointly vicariously…
|
|
| 26 May 2026 |
[2026] EWHC 1248 (TCC)
Service of a claim form on a defendant’s solicitors requires clear written notification that the solicitors are instructed to accept service. General conduct…
|
|
| 22 May 2026 |
[2026] EWHC 1311 (TCC)
Indemnity costs require conduct which takes the case out of the norm. The touchstone is unreasonableness to a high degree, rather than mere error or misguided…
|
|
| 21 May 2026 |
[2026] EWHC 1201 (TCC)
A lease may be frustrated only where a supervening event, without default by either party, makes performance radically different from the bargain originally…
|
|
| 19 May 2026 |
[2026] EWHC 1126 (TCC)
A claim alleging contractual breach or negligence must identify the relevant defect, breach or negligent act, and explain how it caused the loss. Alternative…
|
|
| 12 May 2026 |
[2026] EWHC 1238 (TCC)
On a multi-issue interlocutory application, costs should reflect the parties’ overall success and the conduct that made the application necessary. A party may…
|
|
| 8 May 2026 |
[2026] EWHC 1069 (TCC)
Permission to appeal was refused. A challenge to the exercise of the broad discretion to make a building liability order must identify an error of law…
|
|
| 6 May 2026 |
[2026] EWHC 1057 (TCC)
Part 8 proceedings are unsuitable where the validity and interpretation of contractual payment notices depend materially on disputed or incomplete factual…
|
|
| 1 May 2026 |
[2026] EWHC 1019 (TCC)
Applications to lift the automatic suspension under section 102(2) of the Procurement Act 2023 require a single factual assessment balancing the public…
|
|
| 28 Apr 2026 |
[2026] EWHC 976 (TCC)
Contractual interpretation is a unitary exercise directed to the agreement as a whole. The court should, where possible, give effect to every contractual…
|
|
| 17 Apr 2026 |
[2026] EWHC 891 (TCC)
In a procurement challenge under the Concession Contracts Regulations 2016, the court’s role is supervisory. It must identify a clear and material error…
|
3 |
| 16 Apr 2026 |
[2026] EWHC 885 (TCC)
A binding contract may arise during negotiations marked or begun subject to contract if the parties later expressly or impliedly waive that condition. The…
|
|
| 16 Apr 2026 |
[2026] EWHC 867 (TCC)
On an application to lift the automatic suspension of contract-making in a procurement challenge, the court should ordinarily begin by asking whether damages…
|
|
| 15 Apr 2026 |
[2026] EWHC 884 (TCC)
Costs normally follow the event, but the court may depart from that order where the successful party’s conduct makes departure just. A refusal to mediate is…
|
|
| 1 Apr 2026 |
[2026] EWHC 789 (TCC)
The High Court may make a building liability order before the original company’s relevant liability has been finally established. The order is available where…
|
1 |
| 25 Mar 2026 |
[2026] EWHC 771 (TCC)
Where both parties have addressed the court on interest, the court may depart from an adjudicator’s approach and determine the correct contractual basis…
|
|
| 17 Mar 2026 |
[2026] EWHC 611 (TCC)
On an application for summary judgment, a strong claim will fail where the defendant has a realistically arguable case requiring factual investigation. A…
|
|
| 16 Mar 2026 |
[2026] EWHC 612 (TCC)
In adjudication-enforcement proceedings, the court may consider related Part 8 proceedings only where the issue is short and self-contained, requires no…
|
|
| 16 Mar 2026 |
[2026] EWHC 609 (TCC)
A professional adviser providing information for a lending decision is responsible for losses representing the fruition of the risks against which the advice…
|
|
| 12 Mar 2026 |
[2026] EWHC 561 (TCC)
On an application for summary judgment, the court must decide whether the opposing case has a realistic prospect of success, while avoiding a mini-trial. It…
|
|
| 26 Feb 2026 |
[2026] EWHC 423 (TCC)
Summary judgment may be granted on a short point of law or construction where the court has the necessary evidence and no realistic prospect exists that a…
|
|
| 19 Feb 2026 |
[2026] EWHC 353 (TCC)
Striking out for litigation misconduct is a protective and exceptional remedy. Under Summers v Fairclough Homes Ltd [2012] UKSC 26, the court must ask whether…
|
|
| 19 Feb 2026 |
[2026] EWHC 351 (TCC)
On an application to adjourn a trial, the governing question is whether proceeding would be fair in all the circumstances. The assessment is fact-sensitive and…
|
|
| 16 Feb 2026 |
[2026] EWHC 312 (TCC)
Where negotiations begin subject to contract, that condition ordinarily continues throughout the negotiations. It is removed only by express agreement or by an…
|
|
| 13 Feb 2026 |
[2026] EWHC 232 (TCC)
On an application made before the service period expires, the court has discretion under CPR r 7.6 to extend time for serving a claim form. Inability to serve…
|
|
| 6 Feb 2026 |
[2026] EWHC 220 (TCC)
Where a subcontract is made with joint-venture entities, the constituent companies are not separate contractual “Parties” merely because they sign the deed or…
|
|
| 5 Feb 2026 |
[2026] EWHC 215 (TCC)
Costs budgeting is concerned with approving phase totals falling within the range of reasonable and proportionate costs. It is not a detailed assessment…
|
|
| 5 Feb 2026 |
[2026] EWHC 211 (TCC)
Costs payable by an unsuccessful tenderer in procurement proceedings remain discretionary. An interested party does not obtain costs merely because it won the…
|
|
| 4 Feb 2026 |
[2026] EWHC 228 (TCC)
An intervener directly affected by an injunction application may obtain its reasonable costs where it is properly joined and materially assists the court. The…
|
|
| 4 Feb 2026 |
[2026] EWHC 202 (TCC)
An interim injunction restraining payment under an on-demand performance bond will ordinarily be granted against the issuing bank only where fraud is alleged…
|
|
| 2 Feb 2026 |
[2026] EWHC 155 (TCC)
Where a defendant does not attend trial, the claimant must ordinarily prove its case. The court may strike out the defence, but the absence of adversarial…
|
1 |
| 30 Jan 2026 |
[2026] EWHC 152 (TCC)
Summary enforcement of an adjudicator’s decision is inappropriate where there is a real prospect that the contract relied upon to found the adjudicator’s…
|
|
| 20 Jan 2026 |
[2026] EWHC 78 (TCC)
An assignee of the benefit of a construction contract may refer an assigned claim to adjudication where the contract permits assignment and contains no express…
|
|
| 19 Jan 2026 |
[2026] EWHC 73 (TCC)
In a split trial, the court may make an immediate costs order for a liability stage even though substantial damages remain undecided, particularly where the…
|
|
| 15 Jan 2026 |
[2026] EWHC 61 (TCC)
On an application to lift an automatic suspension in a public procurement, the court should apply the American Cyanamid test. The dissatisfied tenderer bears…
|
1 |
| 13 Jan 2026 |
[2026] EWHC 24 (TCC)
A non-party costs order under Senior Courts Act 1981, section 51, is exceptional only in the sense that it falls outside the ordinary run of litigation. The…
|
|
| 2 Jan 2026 |
[2026] EWHC 8 (TCC)
On an application to lift an automatic suspension in a procurement challenge, the court should not conduct a mini-trial where a serious issue to be tried is…
|
1 |