| Date | Case | Cited by |
|---|---|---|
| 18 Dec 2025 |
[2025] EWHC 3315 (TCC)
Cover for a defect causing a threat of imminent destruction or physical damage requires an objectively realistic risk that the damage will occur sufficiently…
|
|
| 18 Dec 2025 |
[2025] EWHC 3304 (TCC)
An adjudication award will ordinarily be enforced unless the adjudicator decided a question not referred or acted in an obviously unfair manner. An adjudicator…
|
|
| 11 Dec 2025 |
[2025] EWHC 3231 (TCC)
A contractual expert determination is not binding where the expert materially departs from the contractual mandate, including by failing to apply the correct…
|
|
| 8 Dec 2025 |
[2025] EWHC 3209 (TCC)
A freezing order may be continued where the claimant shows a good arguable case, a real risk that enforcement will be frustrated by unjustified dissipation of…
|
|
| 3 Dec 2025 |
[2025] EWHC 3153 (TCC)
An anti-suit injunction restraining a foreign evidence-gathering application may be granted where the application materially interferes with, or prejudices…
|
|
| 28 Nov 2025 |
[2025] EWHC 3143 (TCC)
Summary judgment and strike out are inappropriate where a pleaded contractual claim has a real prospect of success and the proposed grounds depend on disputed…
|
|
| 14 Nov 2025 |
[2025] EWHC 3009 (TCC)
Where an automatic suspension in a procurement challenge is lifted, the successful party will ordinarily recover the costs of that application. The fact that…
|
|
| 14 Nov 2025 |
[2025] EWHC 3002 (TCC)
An agreement to postpone a pre-action meeting does not, without more, extend a court-ordered stay or the time for serving proceedings. A stay cannot be imposed…
|
|
| 14 Nov 2025 |
[2025] EWHC 3001 (TCC)
Under Brazilian environmental law, strict liability applies to a person or entity directly or indirectly responsible for a polluting activity where that…
|
|
| 28 Oct 2025 |
[2025] EWHC 2769 (TCC)
Summary judgment may determine discrete issues, even where the wider claim will proceed to trial, provided the issue is suitable for summary determination. The…
|
|
| 21 Oct 2025 |
[2025] EWHC 2707 (TCC)
In construction payment disputes, a payment schedule may identify the relevant valuation date even if it uses different terminology from the standard-form…
|
|
| 20 Oct 2025 |
[2025] EWHC 2634 (TCC)
On an application to lift an automatic suspension in a procurement challenge, the court must apply the interim-injunction approach required by regulation 96(2)…
|
2 |
| 17 Oct 2025 |
[2025] EWHC 2664 (TCC)
In applications concerning the automatic suspension of a public procurement contract, damages may be inadequate where loss of the contract would probably cause…
|
|
| 9 Oct 2025 |
[2025] EWHC 2581 (TCC)
For defective building work, damages are generally assessed by the reasonable cost of repair or reinstatement. Demolition and rebuilding is an exceptional…
|
|
| 1 Oct 2025 |
[2025] EWHC 2496 (TCC)
Finality generally prevents a judgment being reopened to correct an alleged error arising from a party’s failure to present its case properly, even where the…
|
|
| 25 Sep 2025 |
[2025] EWHC 2429 (TCC)
Private nuisance requires a substantial interference with the ordinary use and enjoyment of land, assessed objectively by reference to an ordinary person in…
|
|
| 8 Sep 2025 |
[2025] EWHC 2258 (TCC)
On summary enforcement of adjudication decisions, a defence must have a realistic prospect of success and carry some degree of conviction; a merely arguable…
|
|
| 29 Aug 2025 |
[2025] EWHC 2213 (TCC)
A judge is not bound by expert evidence, including evidence from a single joint expert. The judge must consider relevant expert evidence and explain any…
|
|
| 19 Aug 2025 |
[2025] EWHC 2173 (TCC)
An adjudicator asked to determine a global valuation may reach an intermediate valuation based on the parties’ evidence and submissions, including a fair and…
|
|
| 31 Jul 2025 |
[2025] EWHC 2037 (TCC)
Summary assessment of costs is ordinarily appropriate, but it may be unsuitable where the costs claimed involve unusual hourly rates, complex and specialist…
|
|
| 31 Jul 2025 |
[2025] EWHC 2030 (TCC)
Part 36 consequences may be applied separately to distinct elements of proceedings. An offer may be a genuine attempt to settle a claim but not a counterclaim…
|
|
| 31 Jul 2025 |
[2025] EWHC 2011 (TCC)
Alternative security for costs by ATE insurance may be accepted where the policy gives the defendant protection equivalent to payment into court. The policy…
|
|
| 18 Jul 2025 |
[2025] EWHC 1815 (TCC)
In a construction adjudication, the statutory obligation to pay a notified sum ordinarily takes priority over a true-value adjudication. A responding party may…
|
|
| 11 Jul 2025 |
[2025] EWHC 1771 (TCC)
On an application to amend, the court must balance the applicant’s interest in determining the real dispute against fairness, proportionality, expedition and…
|
|
| 11 Jul 2025 |
[2025] EWHC 1764 (TCC)
A contractual estimate of the time required for works is not a fixed completion period where the contract describes the programme as indicative. The reasonable…
|
|
| 7 Jul 2025 |
[2025] EWHC 1710 (TCC)
An interested party does not automatically acquire all the rights and obligations of a party under the Civil Procedure Rules. The court must determine, for the…
|
|
| 4 Jul 2025 |
[2025] EWHC 1691 (TCC)
Contractual damages for construction defects are assessed by comparing the actual position with the position that would have existed but for the breaches. Loss…
|
|
| 1 Jul 2025 |
[2025] EWHC 1654 (TCC)
Confidentiality rings in procurement litigation require a fact-sensitive balance between protecting highly sensitive commercial information and enabling the…
|
|
| 27 Jun 2025 |
[2025] EWHC 1677 (TCC)
In deciding whether substantive proceedings should proceed under Part 7 or Part 8, the court should first identify the procedural steps practically required to…
|
|
| 26 Jun 2025 |
[2025] EWHC 1601 (TCC)
A criminal contempt application may disclose reasonable grounds where foreign proceedings are allegedly procured or funded with the specific purpose of…
|
|
| 26 Jun 2025 |
[2025] EWHC 1581 (TCC)
Costs following an application concerning the scope of a freezing injunction are discretionary. The court should consider success, the reasonableness of…
|
|
| 19 Jun 2025 |
[2025] EWHC 1526 (TCC)
An interim payment application under the statutory construction payment regime is valid where it is objectively clear, in substance, form and intent, that…
|
|
| 16 Jun 2025 |
[2025] EWHC 1522 (TCC)
Security for costs is governed by the specific regime in CPR Part 25. An interested party joined to proceedings in that capacity cannot obtain security under…
|
2 |
| 11 Jun 2025 |
[2025] EWHC 1434 (TCC)
An express contractual duty of good faith takes its meaning from the contract and its commercial context. In a joint bidding arrangement, it may require…
|
|
| 10 Jun 2025 |
[2025] EWHC 2005 (TCC)
A jurisdictional challenge to adjudication enforcement which depends on disputed evidence is unsuitable for summary determination where the defendant has a…
|
|
| 4 Jun 2025 |
[2025] EWHC 1354 (TCC)
Requests under Civil Procedure Rules 1998 Part 18 must satisfy two threshold conditions: they must concern a matter in dispute and be strictly confined to…
|
1 |
| 30 May 2025 |
[2025] EWHC 1315 (TCC)
On an application under CPR Parts 3 and 24, pleaded facts are assumed to be true for strike-out purposes, but the court may determine a properly arguable point…
|
|
| 20 May 2025 |
[2025] EWHC 1238 (TCC)
An ATE policy may provide security for costs where it gives real protection against the defendant’s costs not being paid in full. The relevant risk must be…
|
1 |
| 15 May 2025 |
[2025] EWHC 1160 (TCC)
On an application for an interim injunction requiring continued contractual performance, the court should not determine the applicable merits threshold solely…
|
|
| 12 May 2025 |
[2025] EWHC 1134 (TCC)
Costs ordinarily follow the event, but the court may make a different order where the successful party lost a significant issue which caused the unsuccessful…
|
|
| 9 May 2025 |
[2025] EWHC 1122 (TCC)
When enforcing an adjudicator’s decision obtained by a company in liquidation or administration, security must protect the responding party as nearly as…
|
|
| 6 May 2025 |
[2025] EWHC 1058 (TCC)
Where privileged documents have been inadvertently disclosed, permission to use them is governed by an equitable, fact-sensitive assessment. The central…
|
|
| 2 May 2025 |
[2025] EWHC 1063 (TCC)
A costs management order may be made after the date on which budgets were filed. Such an order is not retrospective where it records the court’s assessment of…
|
|
| 28 Apr 2025 |
[2025] EWHC 1010 (TCC)
A duty on a construction professional to review design information may arise during construction even where the original design is incomplete or materially…
|
|
| 24 Apr 2025 |
[2025] EWHC 998 (TCC)
The High Court’s equitable power to grant injunctions is wide, but its exercise remains discretionary and principled. Where unlawful conduct has tainted a…
|
|
| 16 Apr 2025 |
[2025] EWHC 943 (TCC)
Adjudicators’ decisions should generally be enforced unless it is plain that the adjudicator decided a question outside the reference or acted obviously…
|
1 |
| 16 Apr 2025 |
[2025] EWHC 942 (TCC)
A construction contract may be concluded through informal electronic communications where the objective circumstances show agreement on the scope, price and…
|
|
| 9 Apr 2025 |
[2025] EWHC 850 (TCC)
In a professional negligence claim arising from construction defects, an architect’s contractual scope of duty depends primarily on the appointment, read with…
|
|
| 9 Apr 2025 |
[2025] EWHC 831 (TCC)
In a professional negligence claim concerning allegedly defective engineering design, the court assesses the final design, rather than the design process in…
|
|
| 28 Mar 2025 |
[2025] EWHC 744 (TCC)
On an application to lift the automatic suspension of a public procurement contract, the court must apply the established interlocutory adequacy-of-damages…
|
|
| 27 Mar 2025 |
[2025] EWHC 723 (TCC)
In a defective construction claim, the cost of reinstatement is ordinarily the measure of loss where reinstatement is a proportionate and reasonable response.…
|
|
| 25 Mar 2025 |
[2025] EWHC 847 (TCC)
A claim for a mandatory injunction may be particularised by amendment where the relief has always formed part of the pleaded case and the proposed terms are…
|
|
| 25 Mar 2025 |
[2025] EWHC 1505 (TCC)
A settlement agreement may vary an earlier construction contract without replacing it. An adjudication clause in the earlier contract can therefore survive…
|
|
| 20 Mar 2025 |
[2025] EWHC 660 (TCC)
Under CPR 19.6, substitution after expiry of the limitation period remains discretionary, even where the statutory conditions for substitution are satisfied.…
|
|
| 14 Mar 2025 |
[2025] EWHC 594 (TCC)
In construing a construction contract, bespoke risk-allocation provisions must be read with the contract as a whole and according to their ordinary and natural…
|
|
| 13 Mar 2025 |
[2025] EWHC 591 (TCC)
An assignment transfers contractual rights and benefits, but not burdens, obligations or liabilities, unless the transaction amounts to a novation agreed by…
|
1 |
| 11 Mar 2025 |
[2025] EWHC 540 (TCC)
The without prejudice rule does not automatically protect an independent report commissioned from a third party merely because its commissioning was discussed…
|
|
| 10 Mar 2025 |
[2025] EWHC 532 (TCC)
A software licence must be construed according to its wording, context and commercial purpose, but subject to mandatory statutory rights under the Software…
|
|
| 27 Feb 2025 |
[2025] EWHC 434 (TCC)
An information order under section 132 of the Building Safety Act 2022 is ancillary to a possible building liability order. It may be sought before the…
|
2 |
| 26 Feb 2025 |
[2025] EWHC 404 (TCC)
Permission to serve proceedings out of the jurisdiction requires a real, rather than fanciful, prospect of success. The court assesses the proposed pleadings…
|
|
| 24 Feb 2025 |
[2025] EWHC 385 (TCC)
A contractual restriction on assigning the benefit of an appointment may encompass both rights to future performance and accrued rights of action, unless the…
|
|
| 20 Feb 2025 |
[2025] EWHC 354 (TCC)
On an application to lift an automatic suspension in a public procurement, the court applies the American Cyanamid principles. A serious issue requires a claim…
|
3 |
| 6 Feb 2025 |
[2025] EWHC 311 (TCC)
Strike out or summary judgment should not be granted where a claim turns on the construction of a complex contract and the court cannot safely conclude that…
|
|
| 6 Feb 2025 |
[2025] EWHC 310 (TCC)
A party does not establish issue estoppel merely by relying on an argument previously advanced in support of a different issue. Issue estoppel requires the…
|
|
| 5 Feb 2025 |
[2025] EWHC 486 (TCC)
In complex procurement litigation, a party’s inadvertent disclosure of privileged documents must not be permitted to dictate the case-management timetable…
|
|
| 24 Jan 2025 |
[2025] EWHC 100 (TCC)
Under the statutory construction payment regime, a payless notice may be served after receipt of a valid interim payment application and before the period for…
|
|
| 23 Jan 2025 |
[2025] EWHC 108 (TCC)
Permission to amend a statement of case is discretionary and must be determined by applying the overriding objective. A late amendment must have a real, rather…
|
1 |
| 23 Jan 2025 |
[2025] EWHC 105 (TCC)
A registered legal charge created for valuable consideration takes priority over an earlier unprotected interest affecting the charged estate or charge. The…
|
|
| 22 Jan 2025 |
[2025] EWHC 90 (TCC)
A statement of case may be struck out where it is legally unwinnable, or is so vague and incoherent that it impedes the fair and efficient conduct of…
|
|
| 17 Jan 2025 |
[2025] EWHC 63 (TCC)
On an application under regulations 95 and 96(1)(a) of the Public Contracts Regulations 2015, the court must assess the adequacy of damages for both parties…
|
5 |
| 17 Jan 2025 |
[2025] EWHC 285 (TCC)
In costs management, the ordinary starting point remains that costs are in the case. That starting point may be displaced where a party adopts an unrealistic…
|
2 |
| 3 Mar 2023 |
[2025] EWHC 464 (TCC)
An Unless Order takes effect automatically when its terms are not met. Compliance is assessed by asking whether the response was plainly incomplete or…
|
1 |