| Date | Case | Cited by |
|---|---|---|
| 19 Dec 2024 |
[2024] EWHC 3569 (TCC)
A building liability order under section 130 of the Building Safety Act 2022 may be made only in respect of a relevant liability within section 130(3). The…
|
1 |
| 16 Dec 2024 |
[2024] EWHC 3235 (TCC)
For adjudication purposes, a dispute generally crystallises once it can reasonably be inferred that a claim is not admitted. The court should identify the…
|
4 |
| 13 Dec 2024 |
[2024] EWHC 3215 (TCC)
Contractual interest depends on the payment obligations created by the agreement, not on the date when liability is established by judgment. Where the contract…
|
|
| 11 Dec 2024 |
[2024] EWHC 3184 (TCC)
A professional adviser’s contractual and tortious duty is determined objectively by the scope and purpose of the engagement. A planning-related purpose does…
|
|
| 11 Dec 2024 |
[2024] EWHC 3180 (TCC)
Strike-out for disclosure breaches is an exceptional and proportionate remedy. The relevant relief-from-sanctions principles apply, but the court must…
|
|
| 11 Dec 2024 |
[2024] EWHC 3179 (TCC)
A contractual power described as rescission may, on its wording and context, operate as termination rather than rescission ab initio. Termination of a…
|
1 |
| 29 Nov 2024 |
[2024] EWHC 3067 (TCC)
A contractual variation may postpone the commencement of works where the contract defines a variation broadly enough to include a change to the period in which…
|
|
| 28 Nov 2024 |
[2024] EWHC 3059 (TCC)
A preliminary issue should generally be ordered only where it is decisive or potentially decisive, raises a sufficiently precise question, can be tried…
|
|
| 27 Nov 2024 |
[2024] EWHC 3039 (TCC)
On an application to lift the automatic suspension in a regulated procurement, the court applies the American Cyanamid principles. The claimant must show a…
|
1 |
| 18 Nov 2024 |
[2024] EWHC 2903 (TCC)
In a design and build contract, broad obligations concerning design, site conditions, statutory compliance and completion may allocate responsibility for…
|
1 |
| 15 Nov 2024 |
[2024] EWHC 2925 (TCC)
Permission to appeal from a summary judgment decision requires a real prospect of success on at least one proposed ground. An appellate court is unlikely to…
|
|
| 15 Nov 2024 |
[2024] EWHC 2914 (TCC)
Part 36 is a self-contained procedural code. A compliant offer attracts its prescribed costs consequences unless it would be unjust to apply them. The…
|
|
| 6 Nov 2024 |
[2024] EWHC 2800 (TCC)
A claimant seeking to enforce an adjudicator’s award has no general obligation to provide confidential financial information before enforcement proceedings.…
|
|
| 5 Nov 2024 |
[2024] EWHC 3625 (TCC)
Payment of a deposit is a condition precedent to exercising a land option only where the contract, properly construed, makes it an essential constituent of…
|
|
| 22 Oct 2024 |
[2024] EWHC 2890 (TCC)
Insolvency does not create an automatic bar to enforcement of an adjudication award. The court must balance the adjudication regime against the insolvency…
|
|
| 21 Oct 2024 |
[2024] EWHC 2627 (TCC)
Part 8 proceedings are suitable for determining a discrete contractual interpretation issue where the alleged disputed facts are irrelevant to construction of…
|
|
| 10 Oct 2024 |
[2024] EWHC 2575 (TCC)
Without prejudice privilege is principally concerned with inter-party communications genuinely aimed at settling a dispute. It may extend to communications…
|
|
| 3 Oct 2024 |
[2024] EWHC 2516 (TCC)
A court should not reopen or correct matters determined in an earlier judgment where the time for raising the issue has passed and the court has no…
|
|
| 18 Sep 2024 |
[2024] EWHC 2329 (TCC)
On an application for strike-out or summary judgment, the court must distinguish a claim that is legally bound to fail from one requiring factual investigation…
|
|
| 17 Sep 2024 |
[2024] EWHC 2629 (TCC)
Adjudication decisions should be enforced summarily unless a serious breach of natural justice is established. The alleged breach must have made a material…
|
|
| 6 Sep 2024 |
[2024] EWHC 2295 (TCC)
An adjudicator’s allocation of liability for his own fees is ancillary to the adjudication and may be treated differently from the substantive decision. The…
|
|
| 2 Sep 2024 |
[2024] EWHC 2260 (TCC)
A contract may be formed by acceptance of a purchase order which incorporates the buyer’s standard terms. A later invoice referring to the seller’s terms will…
|
|
| 28 Aug 2024 |
[2024] EWHC 2896 (TCC)
A contractual period expressed in months expires on the corresponding calendar date, unless the contract provides otherwise. A provision excluding public…
|
|
| 21 Aug 2024 |
[2024] EWHC 2188 (TCC)
Adjudicators’ decisions requiring payment of a notified sum are ordinarily enforced summarily and without set-off. A party that has not paid the notified sum…
|
|
| 9 Aug 2024 |
[2024] EWHC 2110 (TCC)
Interest claimed as financing costs must be supported by a reasonable assessment of the period and rate for which the loss was incurred. A broad-brush midpoint…
|
|
| 6 Aug 2024 |
[2024] EWHC 2063 (TCC)
For limitation purposes, an insurance claim accrues according to the insured peril identified by construing the policy. Where cover responds to the insured…
|
|
| 1 Aug 2024 |
[2024] EWHC 2025 (TCC)
A judge may correct an internal error in a judgment at any time before the order is sealed, where doing so serves justice and no party has detrimentally relied…
|
1 |
| 25 Jul 2024 |
[2024] EWHC 1929 (TCC)
In adjudication enforcement proceedings, the scope of a referred dispute is identified in broad terms. It is not confined by the referring party’s evidence or…
|
|
| 24 Jul 2024 |
[2024] EWHC 1890 (TCC)
Disclosure directions should be proportionate to the issues, likely evidential value and anticipated cost. A proposed search term may be refused where it is…
|
|
| 23 Jul 2024 |
[2024] EWHC 3204 (TCC)
A preliminary issue should be ordered only where it is likely to reduce the scope of the main trial materially and without creating a risk of inconsistent…
|
|
| 16 Jul 2024 |
[2024] EWHC 1825 (TCC)
An adjudicator’s decision will ordinarily be enforced if made within jurisdiction, subject to limited exceptions. A party’s inaccurate or partial summary of…
|
|
| 5 Jul 2024 |
[2024] EWHC 3449 (TCC)
Issuing proceedings to protect limitation rights is not, by itself, an abuse of process. Abuse arises where the claimant has no known basis for a claim and…
|
|
| 3 Jul 2024 |
[2024] EWHC 1708 (TCC)
For disclosure purposes, practical or de facto control exists where the evidence establishes an arrangement or understanding that a third party will search for…
|
|
| 3 Jul 2024 |
[2024] EWHC 1698 (TCC)
A contractual prohibition on assignment may make a direct assignment of contractual rights ineffective against the debtor. It does not necessarily prevent the…
|
|
| 28 Jun 2024 |
[2024] EWHC 2084 (TCC)
The statutory right to refer a construction dispute to adjudication at any time is broad. The court will restrain an ongoing adjudication only in rare and…
|
1 |
| 21 Jun 2024 |
[2024] EWHC 1560 (TCC)
Section 44(3) of the Arbitration Act 1996 permits urgent orders only where the order sought concerns a matter within section 44(2) and is necessary to preserve…
|
|
| 21 Jun 2024 |
[2024] EWHC 1552 (TCC)
Under a contractual definition of third party income, deductible costs are limited to costs directly incurred in generating the relevant income. Direct costs…
|
|
| 18 Jun 2024 |
[2024] EWHC 1510 (TCC)
A contractual right to supplement a subcontractor’s labour arises only after compliance with the contract’s notice requirements. A party cannot rely on its own…
|
|
| 12 Jun 2024 |
[2024] EWHC 1435 (TCC)
Contractual construction is a unitary and iterative exercise. The court must ascertain the objective meaning of the language in the agreement, read in its…
|
|
| 28 May 2024 |
[2024] EWHC 1713 (TCC)
An adjudicator’s decision is ordinarily enforced despite an error. However, the court may correct an incontrovertible error on a summary enforcement…
|
|
| 23 May 2024 |
[2024] EWHC 1257 (TCC)
Permission to replace an expert is a case-management decision governed by the overriding objective. Serious non-compliance by legal representatives does not…
|
|
| 20 May 2024 |
[2024] EWHC 1687 (TCC)
Permission to issue a late contribution claim may be granted where the proposed contributor already knew that the underlying claim remained live and has…
|
|
| 20 May 2024 |
[2024] EWHC 1686 (TCC)
Costs are governed by the broad discretion in CPR 44.2. The unsuccessful party will usually pay the successful party’s costs, but an issue-based or percentage…
|
2 |
| 20 May 2024 |
[2024] EWHC 1201 (TCC)
For procurement claims under Public Contracts Regulations 2015, the 30-day period in Regulation 92(2) begins with the date of actual or constructive knowledge…
|
1 |
| 20 May 2024 |
[2024] EWHC 1199 (TCC)
A settlement of adjudication enforcement proceedings must be construed according to its wording and commercial context. A release of claims arising from or…
|
|
| 17 May 2024 |
[2024] EWHC 1185 (TCC)
A contractual delay regime must be construed according to its language and commercial context. Relief for an authority-caused delay required proof that the…
|
2 |
| 16 May 2024 |
[2024] EWHC 1159 (TCC)
The power under CPR 8.1(4) is a case-management power exercised in accordance with the overriding objective. The court should consider all relevant…
|
|
| 9 May 2024 |
[2024] EWHC 1237 (TCC)
Where security for costs is ordered in a tranche payable six weeks before trial, and the trial is subsequently postponed, the court may vary the order so that…
|
|
| 9 May 2024 |
[2024] EWHC 1089 (TCC)
An executed construction contract is not ordinarily treated as conditional on funding where the contract contains no such condition and the contemporaneous…
|
|
| 8 May 2024 |
[2024] EWHC 1238 (TCC)
The court may depart from the usual costs order where a successful application has been necessitated by the applicant’s unreasonable conduct. In disclosure…
|
|
| 8 May 2024 |
[2024] EWHC 1088 (TCC)
Strike out is reserved for a statement of case that discloses no legally recognisable claim, is unreasonably vague or incoherent, abuses the court’s process…
|
|
| 2 May 2024 |
[2024] EWHC 1032 (TCC)
An adjudicator’s statutory power to correct a clerical or typographical error is narrow. It permits correction of an accidental error in the expression or…
|
|
| 30 Apr 2024 |
[2024] EWHC 3573 (TCC)
On an application to amend pleadings, the court must identify whether the proposed case introduces a new cause of action by comparing the essential factual…
|
|
| 30 Apr 2024 |
[2024] EWHC 3572 (TCC)
Skeleton arguments in the Technology and Construction Court should be concise, ordinarily no longer than 20 to 25 pages, and should not replace oral…
|
|
| 30 Apr 2024 |
[2024] EWHC 1071 (TCC)
Summary judgment should be refused where the evidence, even if apparently agreed by experts, leaves a real issue as to whether the alleged contractual failure…
|
|
| 29 Apr 2024 |
[2024] EWHC 992 (TCC)
The Part 8 procedure is appropriate where the court is asked to decide a precise question that is unlikely to involve a substantial dispute of fact. Contract…
|
|
| 25 Apr 2024 |
[2024] EWHC 933 (TCC)
A contractual payment schedule that modifies an express payment mechanism takes precedence only where the two arrangements conflict. When the schedule expires…
|
|
| 24 Apr 2024 |
[2024] EWHC 941 (TCC)
An application made before expiry of the time specified in an unless order is an in-time application to extend time under CPR Part 3.1(2)(a), rather than an…
|
|
| 23 Apr 2024 |
[2024] EWHC 921 (TCC)
In a terminal dilapidations claim, the tenant’s liability is assessed by the reasonable cost of works necessary to remedy breaches, subject to mitigation…
|
|
| 18 Apr 2024 |
[2024] EWHC 955 (TCC)
In managing a staged trial, the court may refuse to add further sample agreements where the parties have not had a proper opportunity to assess the…
|
|
| 18 Apr 2024 |
[2024] EWHC 954 (TCC)
A Model C disclosure request is permissible where the documents sought are described with sufficient precision for the disclosing party to identify and search…
|
|
| 18 Apr 2024 |
[2024] EWHC 953 (TCC)
Litigation privilege protects witness interview notes where litigation was reasonably contemplated and the dominant purpose of obtaining the interviews was to…
|
|
| 18 Apr 2024 |
[2024] EWHC 952 (TCC)
An order for extended disclosure may be varied where the applicant establishes that the variation is necessary for the just disposal of the proceedings and…
|
|
| 18 Apr 2024 |
[2024] EWHC 878 (TCC)
Part 8 proceedings are appropriate only where the claim is unlikely to involve a substantial dispute of fact. A claim concerning compliance with contractual…
|
1 |
| 18 Apr 2024 |
[2024] EWHC 1122 (TCC)
An application for disclosure guidance under Practice Direction 57AD is appropriate only where there is a significant, identifiable difference of approach…
|
1 |
| 17 Apr 2024 |
[2024] EWHC 1121 (TCC)
Case-management decisions should be directed to the efficient, fair and proportionate preparation of the issues for trial. Multiple legal representatives may…
|
|
| 16 Apr 2024 |
[2024] EWHC 840 (TCC)
Where construction drawings and specifications are supplied before contracting and are plainly intended to define the work, they may be incorporated into the…
|
|
| 12 Apr 2024 |
[2024] EWHC 802 (TCC)
In determining costs of interlocutory applications, the court assesses which party was substantially successful and applies the usual principle that costs…
|
|
| 5 Apr 2024 |
[2024] EWHC 766 (TCC)
In a regulated procurement, a tenderer must comply with fundamental requirements stated in the tender documents. A contracting authority may reject a…
|
|
| 4 Apr 2024 |
[2024] EWHC 750 (TCC)
Under a termination regime applying where the employer completes the works, a provision referring to the total amount that would have been payable for the…
|
1 |
| 25 Mar 2024 |
[2024] EWHC 667 (TCC)
Under section 1 of the Defective Premises Act 1972, the statutory duty is directed to the outcome that a dwelling is fit for habitation when completed.…
|
2 |
| 21 Mar 2024 |
[2024] EWHC 620 (TCC)
On a strike-out and summary judgment application, the court may decide a short point of law or contractual construction without conducting a mini-trial. A…
|
|
| 21 Mar 2024 |
[2024] EWHC 1190 (TCC)
A claim for a Building Liability Order need not be heard with the underlying claim. However, where such an order is contemplated, it will generally be sensible…
|
2 |
| 15 Mar 2024 |
[2024] EWHC 591 (TCC)
A conclusive evidence clause suspends the evidential effect of a final payment notice where adjudication proceedings are commenced within the contractual…
|
|
| 14 Mar 2024 |
[2024] EWHC 580 (TCC)
When a party fails to pay a judgment debt ordered during ongoing litigation, the court may extend the time for payment and make continuation of the claim…
|
|
| 14 Mar 2024 |
[2024] EWHC 578 (TCC)
A solicitor must have the individual’s consent to commence proceedings concerning that individual’s private rights. Customary authority held by community…
|
|
| 6 Mar 2024 |
[2024] EWHC 485 (TCC)
Where an application substantially fails but exposes a pleading deficiency requiring amendment, the unsuccessful applicant may be ordered to pay the successful…
|
|
| 29 Feb 2024 |
[2024] EWHC 687 (TCC)
Summary judgment is unavailable where the defendant has a real, rather than fanciful, prospect of succeeding on a contractual construction issue. A detailed…
|
|
| 28 Feb 2024 |
[2024] EWHC 423 (TCC)
Confidentiality designations made during disclosure do not determine the treatment of documents at trial. The party seeking continued confidentiality bears the…
|
|
| 20 Feb 2024 |
[2024] EWHC 341 (TCC)
Insurance policy clauses concerning declared trading conditions must be construed in their contractual and statutory context. A statement that particular…
|
|
| 13 Feb 2024 |
[2024] EWHC 297 (TCC)
Disclosure of litigation-funding information may be ordered in support of a prospective non-party costs application. The applicant need not show that the…
|
1 |
| 12 Feb 2024 |
[2024] EWHC 276 (TCC)
A properly arguable environmental clean-up claim should not be summarily dismissed merely because an agreed remediation scheme is substantially complete.…
|
|
| 12 Feb 2024 |
[2024] EWHC 269 (TCC)
Contractual adjudication provisions satisfy the Housing Grants, Construction and Regeneration Act 1996 where, read at the time of contracting, they have the…
|
|
| 9 Feb 2024 |
[2024] EWHC 251 (TCC)
On an application for strike-out or summary judgment, the claimant need show a realistic, rather than fanciful, prospect of success. The court must avoid a…
|
|
| 2 Feb 2024 |
[2024] EWHC 194 (TCC)
Part 8 proceedings may determine disputed factual matters where the court can scrutinise the evidence and conclude that the opposing case has no real prospect…
|
|
| 1 Feb 2024 |
[2024] EWHC 207 (TCC)
Extended disclosure must be tailored to the issue and assessed by reference to what is reasonable and proportionate. Model B is appropriate where the relevant…
|
|
| 1 Feb 2024 |
[2024] EWHC 177 (TCC)
Parties seeking judicial guidance on disclosure issues should identify the precise issue by application notice. They should explain why court guidance is…
|
|
| 31 Jan 2024 |
[2024] EWHC 192 (TCC)
A proposed amendment must plead the claimant’s case with sufficient particularity to enable the opposing party to understand the case it must meet. A general…
|
|
| 12 Jan 2024 |
[2024] EWHC 37 (TCC)
A contractual dispute-resolution clause may make adjudication a condition precedent to litigation where, construed as a whole, it clearly makes court…
|
|
| 12 Jan 2024 |
[2024] EWHC 35 (TCC)
Contractual exclusion and limitation clauses are construed by ordinary principles of contractual interpretation. Clear words may limit liability for deliberate…
|
|
| 11 Jan 2024 |
[2024] EWHC 23 (TCC)
Permission to amend a statement of case depends on the overriding objective and requires a balance between prejudice to the applicant, the opposing parties and…
|
2 |
| 9 Jan 2024 |
[2024] EWHC 10 (TCC)
For adjudication jurisdiction, a referral may contain alternative routes to determining a single disputed claim for payment. The court should adopt a broad…
|