High Court: Technology and Construction Court judgments, 2024

92 judgments, newest first. Open any case for its summary, the legal points it decides and how later courts have treated it.

Date Case Cited by
19 Dec 2024
[2024] EWHC 3569 (TCC)
A building liability order under section 130 of the Building Safety Act 2022 may be made only in respect of a relevant liability within section 130(3). The…
1
16 Dec 2024
[2024] EWHC 3235 (TCC)
For adjudication purposes, a dispute generally crystallises once it can reasonably be inferred that a claim is not admitted. The court should identify the…
4
13 Dec 2024
[2024] EWHC 3215 (TCC)
Contractual interest depends on the payment obligations created by the agreement, not on the date when liability is established by judgment. Where the contract…
11 Dec 2024
[2024] EWHC 3184 (TCC)
A professional adviser’s contractual and tortious duty is determined objectively by the scope and purpose of the engagement. A planning-related purpose does…
11 Dec 2024
[2024] EWHC 3180 (TCC)
Strike-out for disclosure breaches is an exceptional and proportionate remedy. The relevant relief-from-sanctions principles apply, but the court must…
11 Dec 2024
[2024] EWHC 3179 (TCC)
A contractual power described as rescission may, on its wording and context, operate as termination rather than rescission ab initio. Termination of a…
1
29 Nov 2024
[2024] EWHC 3067 (TCC)
A contractual variation may postpone the commencement of works where the contract defines a variation broadly enough to include a change to the period in which…
28 Nov 2024
[2024] EWHC 3059 (TCC)
A preliminary issue should generally be ordered only where it is decisive or potentially decisive, raises a sufficiently precise question, can be tried…
27 Nov 2024
[2024] EWHC 3039 (TCC)
On an application to lift the automatic suspension in a regulated procurement, the court applies the American Cyanamid principles. The claimant must show a…
1
18 Nov 2024
[2024] EWHC 2903 (TCC)
In a design and build contract, broad obligations concerning design, site conditions, statutory compliance and completion may allocate responsibility for…
1
15 Nov 2024
[2024] EWHC 2925 (TCC)
Permission to appeal from a summary judgment decision requires a real prospect of success on at least one proposed ground. An appellate court is unlikely to…
15 Nov 2024
[2024] EWHC 2914 (TCC)
Part 36 is a self-contained procedural code. A compliant offer attracts its prescribed costs consequences unless it would be unjust to apply them. The…
6 Nov 2024
[2024] EWHC 2800 (TCC)
A claimant seeking to enforce an adjudicator’s award has no general obligation to provide confidential financial information before enforcement proceedings.…
5 Nov 2024
[2024] EWHC 3625 (TCC)
Payment of a deposit is a condition precedent to exercising a land option only where the contract, properly construed, makes it an essential constituent of…
22 Oct 2024
[2024] EWHC 2890 (TCC)
Insolvency does not create an automatic bar to enforcement of an adjudication award. The court must balance the adjudication regime against the insolvency…
21 Oct 2024
[2024] EWHC 2627 (TCC)
Part 8 proceedings are suitable for determining a discrete contractual interpretation issue where the alleged disputed facts are irrelevant to construction of…
10 Oct 2024
[2024] EWHC 2575 (TCC)
Without prejudice privilege is principally concerned with inter-party communications genuinely aimed at settling a dispute. It may extend to communications…
3 Oct 2024
[2024] EWHC 2516 (TCC)
A court should not reopen or correct matters determined in an earlier judgment where the time for raising the issue has passed and the court has no…
18 Sep 2024
[2024] EWHC 2329 (TCC)
On an application for strike-out or summary judgment, the court must distinguish a claim that is legally bound to fail from one requiring factual investigation…
17 Sep 2024
[2024] EWHC 2629 (TCC)
Adjudication decisions should be enforced summarily unless a serious breach of natural justice is established. The alleged breach must have made a material…
6 Sep 2024
[2024] EWHC 2295 (TCC)
An adjudicator’s allocation of liability for his own fees is ancillary to the adjudication and may be treated differently from the substantive decision. The…
2 Sep 2024
[2024] EWHC 2260 (TCC)
A contract may be formed by acceptance of a purchase order which incorporates the buyer’s standard terms. A later invoice referring to the seller’s terms will…
28 Aug 2024
[2024] EWHC 2896 (TCC)
A contractual period expressed in months expires on the corresponding calendar date, unless the contract provides otherwise. A provision excluding public…
21 Aug 2024
[2024] EWHC 2188 (TCC)
Adjudicators’ decisions requiring payment of a notified sum are ordinarily enforced summarily and without set-off. A party that has not paid the notified sum…
9 Aug 2024
[2024] EWHC 2110 (TCC)
Interest claimed as financing costs must be supported by a reasonable assessment of the period and rate for which the loss was incurred. A broad-brush midpoint…
6 Aug 2024
[2024] EWHC 2063 (TCC)
For limitation purposes, an insurance claim accrues according to the insured peril identified by construing the policy. Where cover responds to the insured…
1 Aug 2024
[2024] EWHC 2025 (TCC)
A judge may correct an internal error in a judgment at any time before the order is sealed, where doing so serves justice and no party has detrimentally relied…
1
25 Jul 2024
[2024] EWHC 1929 (TCC)
In adjudication enforcement proceedings, the scope of a referred dispute is identified in broad terms. It is not confined by the referring party’s evidence or…
24 Jul 2024
[2024] EWHC 1890 (TCC)
Disclosure directions should be proportionate to the issues, likely evidential value and anticipated cost. A proposed search term may be refused where it is…
23 Jul 2024
[2024] EWHC 3204 (TCC)
A preliminary issue should be ordered only where it is likely to reduce the scope of the main trial materially and without creating a risk of inconsistent…
16 Jul 2024
[2024] EWHC 1825 (TCC)
An adjudicator’s decision will ordinarily be enforced if made within jurisdiction, subject to limited exceptions. A party’s inaccurate or partial summary of…
5 Jul 2024
[2024] EWHC 3449 (TCC)
Issuing proceedings to protect limitation rights is not, by itself, an abuse of process. Abuse arises where the claimant has no known basis for a claim and…
3 Jul 2024
[2024] EWHC 1708 (TCC)
For disclosure purposes, practical or de facto control exists where the evidence establishes an arrangement or understanding that a third party will search for…
3 Jul 2024
[2024] EWHC 1698 (TCC)
A contractual prohibition on assignment may make a direct assignment of contractual rights ineffective against the debtor. It does not necessarily prevent the…
28 Jun 2024
[2024] EWHC 2084 (TCC)
The statutory right to refer a construction dispute to adjudication at any time is broad. The court will restrain an ongoing adjudication only in rare and…
1
21 Jun 2024
[2024] EWHC 1560 (TCC)
Section 44(3) of the Arbitration Act 1996 permits urgent orders only where the order sought concerns a matter within section 44(2) and is necessary to preserve…
21 Jun 2024
[2024] EWHC 1552 (TCC)
Under a contractual definition of third party income, deductible costs are limited to costs directly incurred in generating the relevant income. Direct costs…
18 Jun 2024
[2024] EWHC 1510 (TCC)
A contractual right to supplement a subcontractor’s labour arises only after compliance with the contract’s notice requirements. A party cannot rely on its own…
12 Jun 2024
[2024] EWHC 1435 (TCC)
Contractual construction is a unitary and iterative exercise. The court must ascertain the objective meaning of the language in the agreement, read in its…
28 May 2024
[2024] EWHC 1713 (TCC)
An adjudicator’s decision is ordinarily enforced despite an error. However, the court may correct an incontrovertible error on a summary enforcement…
23 May 2024
[2024] EWHC 1257 (TCC)
Permission to replace an expert is a case-management decision governed by the overriding objective. Serious non-compliance by legal representatives does not…
20 May 2024
[2024] EWHC 1687 (TCC)
Permission to issue a late contribution claim may be granted where the proposed contributor already knew that the underlying claim remained live and has…
20 May 2024
[2024] EWHC 1686 (TCC)
Costs are governed by the broad discretion in CPR 44.2. The unsuccessful party will usually pay the successful party’s costs, but an issue-based or percentage…
2
20 May 2024
[2024] EWHC 1201 (TCC)
For procurement claims under Public Contracts Regulations 2015, the 30-day period in Regulation 92(2) begins with the date of actual or constructive knowledge…
1
20 May 2024
[2024] EWHC 1199 (TCC)
A settlement of adjudication enforcement proceedings must be construed according to its wording and commercial context. A release of claims arising from or…
17 May 2024
[2024] EWHC 1185 (TCC)
A contractual delay regime must be construed according to its language and commercial context. Relief for an authority-caused delay required proof that the…
2
16 May 2024
[2024] EWHC 1159 (TCC)
The power under CPR 8.1(4) is a case-management power exercised in accordance with the overriding objective. The court should consider all relevant…
9 May 2024
[2024] EWHC 1237 (TCC)
Where security for costs is ordered in a tranche payable six weeks before trial, and the trial is subsequently postponed, the court may vary the order so that…
9 May 2024
[2024] EWHC 1089 (TCC)
An executed construction contract is not ordinarily treated as conditional on funding where the contract contains no such condition and the contemporaneous…
8 May 2024
[2024] EWHC 1238 (TCC)
The court may depart from the usual costs order where a successful application has been necessitated by the applicant’s unreasonable conduct. In disclosure…
8 May 2024
[2024] EWHC 1088 (TCC)
Strike out is reserved for a statement of case that discloses no legally recognisable claim, is unreasonably vague or incoherent, abuses the court’s process…
2 May 2024
[2024] EWHC 1032 (TCC)
An adjudicator’s statutory power to correct a clerical or typographical error is narrow. It permits correction of an accidental error in the expression or…
30 Apr 2024
[2024] EWHC 3573 (TCC)
On an application to amend pleadings, the court must identify whether the proposed case introduces a new cause of action by comparing the essential factual…
30 Apr 2024
[2024] EWHC 3572 (TCC)
Skeleton arguments in the Technology and Construction Court should be concise, ordinarily no longer than 20 to 25 pages, and should not replace oral…
30 Apr 2024
[2024] EWHC 1071 (TCC)
Summary judgment should be refused where the evidence, even if apparently agreed by experts, leaves a real issue as to whether the alleged contractual failure…
29 Apr 2024
[2024] EWHC 992 (TCC)
The Part 8 procedure is appropriate where the court is asked to decide a precise question that is unlikely to involve a substantial dispute of fact. Contract…
25 Apr 2024
[2024] EWHC 933 (TCC)
A contractual payment schedule that modifies an express payment mechanism takes precedence only where the two arrangements conflict. When the schedule expires…
24 Apr 2024
[2024] EWHC 941 (TCC)
An application made before expiry of the time specified in an unless order is an in-time application to extend time under CPR Part 3.1(2)(a), rather than an…
23 Apr 2024
[2024] EWHC 921 (TCC)
In a terminal dilapidations claim, the tenant’s liability is assessed by the reasonable cost of works necessary to remedy breaches, subject to mitigation…
18 Apr 2024
[2024] EWHC 955 (TCC)
In managing a staged trial, the court may refuse to add further sample agreements where the parties have not had a proper opportunity to assess the…
18 Apr 2024
[2024] EWHC 954 (TCC)
A Model C disclosure request is permissible where the documents sought are described with sufficient precision for the disclosing party to identify and search…
18 Apr 2024
[2024] EWHC 953 (TCC)
Litigation privilege protects witness interview notes where litigation was reasonably contemplated and the dominant purpose of obtaining the interviews was to…
18 Apr 2024
[2024] EWHC 952 (TCC)
An order for extended disclosure may be varied where the applicant establishes that the variation is necessary for the just disposal of the proceedings and…
18 Apr 2024
[2024] EWHC 878 (TCC)
Part 8 proceedings are appropriate only where the claim is unlikely to involve a substantial dispute of fact. A claim concerning compliance with contractual…
1
18 Apr 2024
[2024] EWHC 1122 (TCC)
An application for disclosure guidance under Practice Direction 57AD is appropriate only where there is a significant, identifiable difference of approach…
1
17 Apr 2024
[2024] EWHC 1121 (TCC)
Case-management decisions should be directed to the efficient, fair and proportionate preparation of the issues for trial. Multiple legal representatives may…
16 Apr 2024
[2024] EWHC 840 (TCC)
Where construction drawings and specifications are supplied before contracting and are plainly intended to define the work, they may be incorporated into the…
12 Apr 2024
[2024] EWHC 802 (TCC)
In determining costs of interlocutory applications, the court assesses which party was substantially successful and applies the usual principle that costs…
5 Apr 2024
[2024] EWHC 766 (TCC)
In a regulated procurement, a tenderer must comply with fundamental requirements stated in the tender documents. A contracting authority may reject a…
4 Apr 2024
[2024] EWHC 750 (TCC)
Under a termination regime applying where the employer completes the works, a provision referring to the total amount that would have been payable for the…
1
25 Mar 2024
[2024] EWHC 667 (TCC)
Under section 1 of the Defective Premises Act 1972, the statutory duty is directed to the outcome that a dwelling is fit for habitation when completed.…
2
21 Mar 2024
[2024] EWHC 620 (TCC)
On a strike-out and summary judgment application, the court may decide a short point of law or contractual construction without conducting a mini-trial. A…
21 Mar 2024
[2024] EWHC 1190 (TCC)
A claim for a Building Liability Order need not be heard with the underlying claim. However, where such an order is contemplated, it will generally be sensible…
2
15 Mar 2024
[2024] EWHC 591 (TCC)
A conclusive evidence clause suspends the evidential effect of a final payment notice where adjudication proceedings are commenced within the contractual…
14 Mar 2024
[2024] EWHC 580 (TCC)
When a party fails to pay a judgment debt ordered during ongoing litigation, the court may extend the time for payment and make continuation of the claim…
14 Mar 2024
[2024] EWHC 578 (TCC)
A solicitor must have the individual’s consent to commence proceedings concerning that individual’s private rights. Customary authority held by community…
6 Mar 2024
[2024] EWHC 485 (TCC)
Where an application substantially fails but exposes a pleading deficiency requiring amendment, the unsuccessful applicant may be ordered to pay the successful…
29 Feb 2024
[2024] EWHC 687 (TCC)
Summary judgment is unavailable where the defendant has a real, rather than fanciful, prospect of succeeding on a contractual construction issue. A detailed…
28 Feb 2024
[2024] EWHC 423 (TCC)
Confidentiality designations made during disclosure do not determine the treatment of documents at trial. The party seeking continued confidentiality bears the…
20 Feb 2024
[2024] EWHC 341 (TCC)
Insurance policy clauses concerning declared trading conditions must be construed in their contractual and statutory context. A statement that particular…
13 Feb 2024
[2024] EWHC 297 (TCC)
Disclosure of litigation-funding information may be ordered in support of a prospective non-party costs application. The applicant need not show that the…
1
12 Feb 2024
[2024] EWHC 276 (TCC)
A properly arguable environmental clean-up claim should not be summarily dismissed merely because an agreed remediation scheme is substantially complete.…
12 Feb 2024
[2024] EWHC 269 (TCC)
Contractual adjudication provisions satisfy the Housing Grants, Construction and Regeneration Act 1996 where, read at the time of contracting, they have the…
9 Feb 2024
[2024] EWHC 251 (TCC)
On an application for strike-out or summary judgment, the claimant need show a realistic, rather than fanciful, prospect of success. The court must avoid a…
2 Feb 2024
[2024] EWHC 194 (TCC)
Part 8 proceedings may determine disputed factual matters where the court can scrutinise the evidence and conclude that the opposing case has no real prospect…
1 Feb 2024
[2024] EWHC 207 (TCC)
Extended disclosure must be tailored to the issue and assessed by reference to what is reasonable and proportionate. Model B is appropriate where the relevant…
1 Feb 2024
[2024] EWHC 177 (TCC)
Parties seeking judicial guidance on disclosure issues should identify the precise issue by application notice. They should explain why court guidance is…
31 Jan 2024
[2024] EWHC 192 (TCC)
A proposed amendment must plead the claimant’s case with sufficient particularity to enable the opposing party to understand the case it must meet. A general…
12 Jan 2024
[2024] EWHC 37 (TCC)
A contractual dispute-resolution clause may make adjudication a condition precedent to litigation where, construed as a whole, it clearly makes court…
12 Jan 2024
[2024] EWHC 35 (TCC)
Contractual exclusion and limitation clauses are construed by ordinary principles of contractual interpretation. Clear words may limit liability for deliberate…
11 Jan 2024
[2024] EWHC 23 (TCC)
Permission to amend a statement of case depends on the overriding objective and requires a balance between prejudice to the applicant, the opposing parties and…
2
9 Jan 2024
[2024] EWHC 10 (TCC)
For adjudication jurisdiction, a referral may contain alternative routes to determining a single disputed claim for payment. The court should adopt a broad…