TNC Group Holdings Limited, R (on the application of) v Secretary of State for Housing, Communities and Local Government

[2026] EWHC 2912 (Admin)

Summary

An application for approval of reserved matters must be received by the local planning authority within the period required by the outline planning permission. Uploading it to the Planning Portal is not itself receipt by the authority. Where the Portal requires a fee to be processed before transmission, the applicant bears the risk of delay in that process.

For electronic communications under the Town and Country Planning (Development Management Procedure) (England) Order 2015, the document must be capable of being accessed by the recipient. An electronic communication received outside the recipient’s business hours is deemed received on the next working day.

A Planning Inspectorate officer may decide administratively that a purported planning appeal is invalid. The statutory provision for inspectors to determine appeals does not reserve that administrative function to them.

Factual background

Wealden District Council, the local planning authority, granted TNC Group Holdings Limited outline permission to replace a care home. A condition required an application for approval of reserved matters within 18 months, ending on 4 March 2025.

TNC uploaded its application to the Planning Portal on the final day. The Portal processed the fee and transmitted the application to the council on 5 March. The council concluded that the application was late and declined to process it. TNC appealed to the Planning Inspectorate against the council’s failure to decide the application, but an Inspectorate case officer rejected the appeal as invalid.

TNC sought judicial review of the officer’s decision. Permission was granted on grounds concerning the timeliness of the application and the officer’s authority to decide validity. Permission was refused on a separate ground alleging that the officer had treated the council’s view of validity as determinative.

Held

The claim was dismissed. The reserved matters application was made on 5 March 2025, after the deadline, and the outline permission had lapsed. The case officer was entitled to reject the purported appeal as invalid.

  1. The application was made when received by the council, its intended recipient. The Planning Portal was a means of transmission, not the council’s agent for receiving applications. The council’s encouragement of its use and the applicant’s loss of control after uploading did not establish agency. The Portal’s terms and communications made clear that it would send the application only after processing the fee and that the applicant bore the risk of processing delay. Although the general statutory provisions did not make receipt of the fee a condition of the application’s validity, the application was not transmitted to the council until 5 March ([10]–[22]).
  2. Independently, article 2(4) of the Town and Country Planning (Development Management Procedure) (England) Order 2015 required the electronically transmitted document to be capable of being accessed by the recipient. The council could not access it before release following clearance of the payment. Under article 2(6), receipt outside the council’s business hours was deemed to occur on the next working day. The claimant’s payment arrangements could not realistically have been completed before the council’s closing time on 4 March ([23]–[27]).
  3. R v Bromley LBC ex parte Sievers and another (1981) 41 P&CR 294 was distinguishable. There, the council’s offices were closed on the final days and the physical application required delivery to an officer. Neither feature applied here. The specific electronic communications provisions superseded the principles of that case for electronic applications. Its observations that any lateness was de minimis were obiter and would not be followed in view of section 93(4)(b) of the Town and Country Planning Act 1990 ([28]–[33]).
  4. Under the principle in Carltona Ltd v Commissioners of Works [1943] 2 ALL ER 560, a minister may act through officers unless a function is reserved to a particular person or class. Paragraph 1 of Schedule 6 to the 1990 Act reserves determination of appeals to inspectors; it does not reserve administrative screening and rejection of invalid appeals. An officer’s decision may be challenged on its merits, including where a doubtful matter should have proceeded to an inspector. The court found no basis for an inspector to extend the time for this application ([34]–[40]).

The court’s approach to earlier authorities

Available to signed-in members.

Appellate history

The Planning Inspectorate case officer rejected the purported appeal as invalid on 15 December 2025. Permission for judicial review was granted on two grounds and refused on a third. The High Court dismissed the claim.

Key cases cited

6 authorities cited.