Summary
Where time for completion of a land sale is not of the essence, termination for non-completion ordinarily requires a notice fixing a reasonable further completion date and making time essential. The no title principle permits immediate termination where the vendor has neither title nor an enforceable right to obtain it. An enforceable contractual right to acquire title suffices despite a disclosed delay in obtaining probate. A purchaser cannot rely on that disclosed contingency alone to terminate without notice.
The Board will not entertain new grounds requiring evidence which the other party had no fair opportunity to address. A claim for relief from forfeiture which should have been pleaded and investigated at trial cannot first be introduced before the Board.
Factual background
Teresa de Silva agreed to buy freehold property from the executor of its former owner’s estate. That contract contemplated delay in obtaining probate and expressly provided that time for completion was not of the essence. She then agreed to sell the property to Dindial’s Hardware Limited, which paid a 10% deposit and received a copy of her purchase contract by the time its own contract was made.
By the contractual completion date, probate had not been obtained and Mrs de Silva had not supplied the required tax receipt and water clearance certificate. Dindial sought repayment of its deposit without serving a notice to complete. Mrs de Silva treated that communication as a repudiation and forfeited the deposit.
The trial judge upheld Dindial’s repayment claim because he considered that Mrs de Silva had a fundamental defect in title. The Court of Appeal reversed that result because she had a contractual right to obtain title. Dindial appealed to the Board, principally contending that the no title principle allowed termination without notice. It also advanced new grounds and sought equitable relief from forfeiture.
Held
The appeal was dismissed. Lord Briggs delivered the Board’s judgment.
Time for completion of a land-sale contract was ordinarily not of the essence unless the parties provided otherwise. Termination for failure to complete required a notice making time essential, fixing a reasonable further completion date, and non-completion by that date. The completion notice principle, supported by Stickney v Keeble [1915] AC 386, applied. The November Contract did not make time essential. The disclosed earlier contract formed part of its context, and the anticipated probate delay reinforced that construction (paras 1, 24–26).
The no title principle permitted a purchaser to treat a contract as discharged where the vendor had neither title nor an enforceable right to obtain it. It concerned a fundamental absence of title, rather than minor deficiencies or removable defects. The Board applied the principle stated in Forrer v Nash (1865) 35 Beav 167 and the relevant dicta in Pips (Leisure Productions) Ltd v Walton (1980) 43 P & CR 415. If the principle applied to common law liabilities, it extended to forfeiture of the deposit as well as damages (paras 27–31).
Mrs de Silva had a contractual right to require conveyance to herself or her nominee. That right was distinct from a mere hope of obtaining title through another person’s discretion. Obtaining probate affected the timing of performance rather than the existence of that right. The adopted dicta also recognised that an enforceable right could suffice even if, exceptionally, it sounded only in damages; that qualification did not arise on the facts (paras 30–31).
The purchaser could not use the disclosed dependence on obtaining probate as itself justifying immediate termination. Wylson v Dunn (1887) 34 Ch D 569 supported that conclusion. There was no fundamental absence of title displacing the requirement for a notice to complete. The purchaser’s purported termination was therefore repudiatory, and the Court of Appeal’s conclusion that the deposit was forfeited stood (paras 17, 29, 31–32).
The Board declined to entertain new grounds concerning financing and currency conversion, or the different form of grant ultimately obtained. Those issues had not been properly raised at trial and might require evidence which the vendor had no fair opportunity to address. Equitable relief from forfeiture should likewise have been pleaded and investigated at trial, even though the purchaser’s initial success made its determination unnecessary. It was too late to seek that relief before the Board. Its substantive availability and merits were left undecided (paras 21–23, 33).
The court’s approach to earlier authorities
Available to signed-in members.
Appellate history
- Privy Council: In [2026] UKPC 39 , dismissed the purchaser’s appeal, leaving the Court of Appeal’s decision and forfeiture of the deposit undisturbed.
- Court of Appeal of the Republic of Trinidad and Tobago: Reversed the trial result. The vendor’s contractual right to obtain title meant that the purchaser had to serve a notice to complete. Its purported termination was repudiatory, entitling the vendor to accept the repudiation and forfeit the deposit.
- High Court: Boodoosingh J upheld the purchaser’s claim to recover the deposit. He considered that a fundamental defect in the vendor’s title entitled the purchaser to terminate without first making time of the essence.
Key cases cited
4 authorities cited.
- Pips (Leisure Productions) Ltd v Walton (1980) 43 P & CR 415
- Stickney v Keeble [1915] AC 386
- Forrer v Nash (1865) 35 Beav 167
- Wylson v Dunn
Sign in to see how the court treated each authority. A free account is enough.