| Date | Case | Cited by |
|---|---|---|
| 22 Dec 2011 |
[2011] EWHC 3464 (TCC)
On an application for security for costs by a company in financial difficulty, the court must first decide whether there is reason to believe that the claimant…
|
1 |
| 21 Dec 2011 |
[2011] EWHC 3941 (TCC)
A contractual definition of subcontractor’s equipment may extend to project documentation where the documents are required to complete the works and do not…
|
|
| 21 Dec 2011 |
[2011] EWHC 3449 (TCC)
A term requiring a construction contractor or subcontractor to proceed regularly and diligently will not ordinarily be implied merely because the contract…
|
|
| 20 Dec 2011 |
[2011] EWHC 3454 (TCC)
An interim injunction may restrain the dissemination of private digital images where the claimant has a reasonable expectation of privacy and is likely to…
|
|
| 15 Dec 2011 |
[2011] EWHC 3362 (TCC)
A party waives privilege in a document referred to in a witness statement where the document, or its contents, is deployed for use in interlocutory or final…
|
|
| 14 Dec 2011 |
[2011] EWHC 3373 (TCC)
Where parties have agreed an express contractual indemnity for costs, the court should ordinarily exercise its costs discretion to reflect that agreement. A…
|
2 |
| 9 Dec 2011 |
[2011] EWHC 3229 (TCC)
A judgment entered administratively on an admission in an acknowledgment of service is irregular where the admission does not fall within specific procedural…
|
|
| 8 Dec 2011 |
[2011] EWHC 3280 (TCC)
Proceedings should be transferred to the Technology and Construction Court where the bulk or preponderance of the issues is technically complex, or where trial…
|
|
| 8 Dec 2011 |
[2011] EWHC 3253 (TCC)
Statutory authority to operate sewage-treatment works does not immunise the operator from nuisance where it fails to conduct the works with all reasonable…
|
1 |
| 6 Dec 2011 |
[2011] EWHC 3191 (TCC)
Where a construction contract contains adjudication provisions that materially fail to comply with Housing Grants, Construction and Regeneration Act 1996, the…
|
3 |
| 25 Nov 2011 |
[2011] EWHC 3496 (TCC)
On an application for security for costs, the threshold condition must first be established. The court must then exercise its discretion by assessing the…
|
|
| 23 Nov 2011 |
[2011] EWHC 2989 (TCC)
An adjudicator may award interest on sums exceeding those certified where the contract permits the adjudicator to open up, review and revise certificates. The…
|
|
| 22 Nov 2011 |
[2011] EWHC 306 (TCC)
In construing a complex services agreement, the court must read individual provisions in the context of the agreement’s overall scheme and relevant background.…
|
|
| 21 Nov 2011 |
[2011] EWHC 3157 (TCC)
For an interim injunction, the court must be satisfied that there is a serious issue to be tried and must assess the adequacy of damages and the balance of…
|
|
| 21 Nov 2011 |
[2011] EWHC 2994 (TCC)
Costs are determined by the overall outcome, while taking account of partial success, conduct and admissible settlement offers. Success on individual issues…
|
|
| 10 Nov 2011 |
[2011] EWHC 2910 (TCC)
In serial adjudications, the question is whether the later reference concerns the same or substantially the same dispute as an earlier one. The court must…
|
3 |
| 4 Nov 2011 |
[2011] EWHC 3070 (TCC)
In deciding whether to adjourn a long trial because of late disclosure, the court must assess whether a fair trial remains possible and whether the affected…
|
|
| 3 Nov 2011 |
[2011] EWHC 2867 (TCC)
An oral joint venture concerning property development must be determined from the parties’ objectively established agreement. Where no agreed time limit or…
|
|
| 3 Nov 2011 |
[2011] EWHC 2847 (TCC)
In a civil claim involving several possible causes of a fire, the claimant must prove the alleged cause on the balance of probabilities. The court is not…
|
1 |
| 3 Nov 2011 |
[2011] EWHC 2846 (TCC)
An adjudicator’s decision may be enforced summarily even where the same dispute is being litigated. A challenge based only on alleged errors in the…
|
1 |
| 27 Oct 2011 |
[2011] EWHC 2722 (TCC)
An adjudicator’s decision may be unenforceable for a serious breach of natural justice without there being a total failure of consideration under the…
|
|
| 25 Oct 2011 |
[2011] EWHC 3519 (TCC)
Whether contractual terms are incorporated by a signed document depends on the document’s objective contractual effect, assessed in its commercial context. The…
|
|
| 20 Oct 2011 |
[2011] EWHC 2695 (TCC)
An oral settlement agreement is determined objectively by analysing the parties’ words and conduct, including relevant subsequent conduct. An existing offer…
|
|
| 20 Oct 2011 |
[2011] EWHC 2694 (TCC)
In commercial litigation, the party obtaining judgment or payment will generally be treated as the overall successful party. The court should begin with the…
|
3 |
| 14 Oct 2011 |
[2011] EWHC 2626 (TCC)
Amendments should generally be permitted so that the real dispute can be adjudicated. The court may refuse an amendment where the resulting prejudice cannot be…
|
|
| 21 Sep 2011 |
[2011] EWHC 2378 (TCC)
A surety is discharged by a variation of the guaranteed contract unless the variation is plainly immaterial, beneficial, or protected by the guarantee. An…
|
1 |
| 12 Sep 2011 |
[2011] EWHC 2332 (TCC)
For the purposes of construction adjudication, a dispute generally arises when a claim or assertion is expressly or implicitly challenged. A dispute may…
|
12 |
| 12 Sep 2011 |
[2011] EWHC 2311 (TCC)
A lead consultant advising on a housing stock transfer must exercise reasonable care and skill to ascertain whether the business plan and proposed gap funding…
|
|
| 31 Aug 2011 |
[2011] EWHC 2153 (TCC)
Where a claimant alleges that goods failed shortly after supply, the timing of the failure does not by itself establish breach of the implied term of…
|
2 |
| 8 Aug 2011 |
[2011] EWHC 2477 (TCC)
An interim injunction requires a serious issue to be tried, damages to be an inadequate remedy, and a balance of convenience favouring relief. The court must…
|
|
| 8 Aug 2011 |
[2011] EWHC 2210 (TCC)
Pre-action disclosure is exceptional. The existence of commercial disputes and a possibility of later litigation is insufficient. There must be a real…
|
|
| 8 Aug 2011 |
[2011] EWHC 2209 (TCC)
Security for costs is discretionary even where defendants advance a counterclaim. The court must examine whether the costs of defending the claim are also…
|
|
| 29 Jul 2011 |
[2011] EWHC 2169 (TCC)
Pre-trial applications should be managed proportionately and should not ordinarily be attached to a pre-trial review without sufficient hearing time. Further…
|
|
| 26 Jul 2011 |
[2011] EWHC 2016 (TCC)
A licensing regulator’s power to vary the terms, provisions or limitations of a wireless telegraphy licence does not ordinarily permit it to substitute a…
|
|
| 25 Jul 2011 |
[2011] EWHC 1947 (TCC)
A contractual time bar should be construed to give it a commercially coherent operation. Where no certificate of practical completion of the services exists…
|
|
| 22 Jul 2011 |
[2011] EWHC 1936 (TCC)
In a commercial “battle of the forms”, the court applies the traditional offer-and-acceptance analysis unless the parties’ documents and conduct establish a…
|
3 |
| 21 Jul 2011 |
[2011] EWHC 1935 (TCC)
Contractual conclusivity provisions may make an adjudicator’s decision conclusive where the contract gives the losing party a defined period to challenge it.…
|
3 |
| 19 Jul 2011 |
[2011] EWHC 1847 (TCC)
In procurement challenges under the Utilities Contracts Regulations 2006, time begins when the unsuccessful tenderer knows the basic facts which would…
|
8 |
| 13 Jul 2011 |
[2011] EWHC 1810 (TCC)
An adjudicator may adopt a legal or factual approach different from that advanced by either party where the issue was before him, the approach arises from the…
|
5 |
| 11 Jul 2011 |
[2011] EWHC 1811 (TCC)
A builder’s contractual obligation to complete a house in a good and workmanlike manner may extend to design and to completion so that the house is fit for…
|
4 |
| 7 Jul 2011 |
[2011] EWHC 1722 (TCC)
In negligence claims concerning defects in a building, the court must assess the structure realistically and avoid artificial subdivision into separate…
|
|
| 6 Jul 2011 |
[2011] EWHC 1679 (TCC)
A party may restart an adjudication where an earlier adjudication became a nullity because no referral was made and no decision was taken. Neither the…
|
|
| 6 Jul 2011 |
[2011] EWHC 1678 (TCC)
An adjudicator’s determination that one party should pay his fees does not itself establish the amount recoverable. Under paragraph 25 of the Scheme for…
|
3 |
| 29 Jun 2011 |
[2011] EWHC 1632 (TCC)
A claimant alleging that fire spread from adjoining premises must prove the relevant causal sequence on the balance of probabilities and show that the loss…
|
2 |
| 24 Jun 2011 |
[2011] EWHC 1622 (TCC)
An indemnifier is not bound by a consent judgment against the party seeking indemnity merely because it knew of the underlying claim, conducted the defence and…
|
|
| 23 Jun 2011 |
[2011] EWHC 1581 (TCC)
Costs under the Civil Procedure Rules remain subject to the court’s broad discretion. The court must consider all material circumstances, including party…
|
1 |
| 17 Jun 2011 |
[2011] EWHC 1561 (TCC)
An adjudicator’s error of law or fact on an issue referred to him does not ordinarily provide a defence to enforcement of his decision. A certified interim…
|
1 |
| 15 Jun 2011 |
[2011] EWHC 1516 (TCC)
Under the Civil Liability (Contribution) Act 1978, a contribution may include a share of costs paid to the injured third party as part of a settlement…
|
3 |
| 15 Jun 2011 |
[2011] EWHC 1379 (TCC)
A lead consultant retained responsibility for coordinating and reviewing specialist subcontractor design where its contract covered the whole design and…
|
|
| 14 Jun 2011 |
[2011] EWHC 1515 (TCC)
Fiduciary duties in a commercial agency relationship depend on the underlying contract and may apply to only particular activities. An agent’s contractual…
|
2 |
| 8 Jun 2011 |
[2011] EWHC 1439 (TCC)
Leave to appeal from an arbitration award under section 69 of the Arbitration Act 1996 requires the statutory conditions to be satisfied. A contractual…
|
|
| 27 May 2011 |
[2011] EWHC 1411 (TCC)
Roaming may amount to carriage of voice or data traffic and to sharing or consolidation of network rights, even where no new physical equipment is installed.…
|
|
| 26 May 2011 |
[2011] EWHC 1352 (TCC)
A guarantee must be construed commercially. Where literal wording produces absurdity or incoherence, it should yield to business common sense. Compliance with…
|
|
| 25 May 2011 |
[2011] EWHC 1356 (TCC)
Under CPR 3.9(1), the court may grant relief from sanctions imposed by a consent order. However, the parties’ agreement is a highly important factor, and the…
|
|
| 25 May 2011 |
[2011] EWHC 1353 (TCC)
In tree-root subsidence claims, liability in nuisance or negligence depends on whether the defendant knew, or ought to have known, of a real and reasonably…
|
|
| 24 May 2011 |
[2011] EWHC 2681 (TCC)
For enforcement of an adjudicator’s decision, jurisdiction is determined by the construction contract and the evidence relied upon, including the parties’…
|
|
| 13 May 2011 |
[2011] EWHC 1199 (TCC)
A claimant acquiring another company’s tort claims may enforce them where the assignment, construed objectively in its factual context, covers the whole claim…
|
|
| 12 May 2011 |
[2011] EWHC 1160 (TCC)
For the purpose of Public Contracts Regulations 2006, proceedings are brought when the court issues the claim form, or potentially when it receives the form…
|
1 |
| 5 May 2011 |
[2011] EWHC 874 (TCC)
For limitation purposes, knowledge under Limitation Act 1980, section 14A, does not require certainty or knowledge that the conduct was legally negligent. The…
|
|
| 4 May 2011 |
[2011] EWHC 1122 (TCC)
A fixed-price building contract may be varied by a later agreement, including an agreement made orally or by conduct. The scope of a lump-sum variation is…
|
|
| 19 Apr 2011 |
[2011] EWHC 972 (TCC)
An adjudication decision may be enforced where the party challenging jurisdiction has no reasonable prospect of proving that the contract was made without…
|
|
| 19 Apr 2011 |
[2011] EWHC 1107 (TCC)
The unsuccessful party will ordinarily pay the successful party’s costs. Departure from that rule requires conduct materially connected with the costs of the…
|
4 |
| 19 Apr 2011 |
[2011] EWHC 1035 (TCC)
A contractual adjudication procedure in a construction contract survives termination or accepted repudiation. Where the Housing Grants, Construction and…
|
|
| 19 Apr 2011 |
[2011] EWHC 1031 (TCC)
In a public procurement, a contracting authority must disclose the award criteria, sub-criteria and weightings which it intends to use where they could affect…
|
2 |
| 19 Apr 2011 |
[2011] EWHC 1003 (TCC)
Environmental legislation and a detailed permit may materially shape common-law nuisance. Where a landfill operator uses land in accordance with its permit…
|
2 |
| 15 Apr 2011 |
[2011] EWHC 918 (TCC)
An arbitration agreement may be made independently of an underlying contract, including on an ad hoc basis. Its formation is determined objectively, using…
|
|
| 14 Apr 2011 |
[2011] EWHC 930 (TCC)
Contractual provisions excluding or limiting damages for delay cannot be circumvented by pleading the same loss as breach of an implied term of reasonable…
|
|
| 8 Apr 2011 |
[2011] EWHC 881 (TCC)
Where an application for security for costs fails, the ordinary starting point is that costs follow the event. A successful party may nevertheless receive less…
|
|
| 7 Apr 2011 |
[2011] EWHC 1234 (TCC)
Contractual adjudication time limits must be construed in their context. A requirement that the referring party send the referral documents within two days of…
|
|
| 31 Mar 2011 |
[2011] EWHC 780 (TCC)
For adjudication under the Housing Grants, Construction and Regeneration Act 1996, the contract and all its terms must be made or evidenced in writing. A…
|
3 |
| 25 Mar 2011 |
[2011] EWHC 813 (TCC)
An adjudicator must determine a defence which is properly raised and materially relevant to the dispute referred. A decision is unenforceable where the…
|
3 |
| 23 Mar 2011 |
[2011] EWHC 657 (TCC)
An on-demand bond ordinarily requires the bank to honour a compliant demand, absent clear evidence of fraud. That principle does not prevent the court…
|
4 |
| 22 Mar 2011 |
[2011] EWHC 661 (TCC)
Under CPR Part 19.6, representative proceedings require the representative and represented persons to have the same interest when the claim is begun. The…
|
2 |
| 21 Mar 2011 |
[2011] EWHC 653 (TCC)
An indemnity costs order is compensatory rather than penal. It requires conduct or circumstances taking the case outside the norm, involving unreasonable…
|
3 |
| 17 Mar 2011 |
[2011] EWHC 549 (TCC)
A contractual satisfactory-quality obligation is construed in its contractual context. Where the contract specifies what software must do, compliance with…
|
1 |
| 16 Mar 2011 |
[2011] EWHC 599 (TCC)
A claimant alleging deceit or negligent misrepresentation must prove reliance on the relevant representation and loss caused by that reliance. A claimant…
|
|
| 23 Feb 2011 |
[2011] EWHC 332 (TCC)
A party preparing a Scott Schedule in construction litigation must present each alleged defect and the recoverable costs attributable to it with sufficient…
|
|
| 22 Feb 2011 |
[2011] EWHC 403 (TCC)
A contractual variation releasing a tenant from a continuing repairing obligation may take immediate effect even though it specifies no commencement date. Its…
|
|
| 18 Feb 2011 |
[2011] EWHC 277 (TCC)
CPR 12.8 prevents default judgment against one defendant where entering judgment would prevent the claim being pursued against another defendant. The rule…
|
|
| 18 Feb 2011 |
[2011] EWHC 269 (TCC)
An adjudicator must comply with natural justice, but a breach arises only where an undisclosed issue is material and decisive, or of considerable potential…
|
1 |
| 9 Feb 2011 |
[2011] EWHC 209 (TCC)
A technical auditor’s duty is defined by the retainer and its commercial context. The auditor does not guarantee defect-free construction or compliance with…
|
|
| 31 Jan 2011 |
[2011] EWHC 123 (TCC)
An on-demand bond must be construed according to its particular wording. Where the bond requires notices or claims supporting the demand, those documents must…
|
1 |
| 27 Jan 2011 |
[2011] EWHC 87 (TCC)
On an application to lift the statutory suspension of a public procurement contract, the court applied the American Cyanamid approach. The claimant had to show…
|
1 |
| 27 Jan 2011 |
[2011] EWHC 66 (TCC)
A supplier of integrated equipment is responsible for ensuring that the equipment complies with the contractual specification and is fit for its intended use…
|
1 |
| 26 Jan 2011 |
[2011] EWHC 43 (TCC)
A party challenging an adjudicator’s jurisdiction must make a clear reservation of its position during the adjudication. A reservation may be established…
|
3 |
| 25 Jan 2011 |
[2011] EWHC 72 (TCC)
In a contribution claim, contractual responsibility for design must be distinguished from an obligation that materials be suitable. An express exclusion of…
|
|
| 17 Jan 2011 |
[2011] EWHC 26 (TCC)
An order for indemnity costs requires conduct or circumstances taking the case outside the norm. A defendant’s Part 36 offer, and the claimant’s failure to…
|
1 |
| 17 Jan 2011 |
[2011] EWHC 19 (TCC)
On a standard costs assessment, CFA success fees and ATE insurance premiums must be reasonable and proportionate when separately assessed. The principal factor…
|
1 |
| 12 Jan 2011 |
[2011] EWHC 27 (TCC)
A professional fee must reflect the value of the services actually provided, including the effect of negligent or incomplete performance. Where a fee is…
|