Telford Homes (Creekside) Ltd v Ampurius Nu Homes Holdings Ltd

[2013] EWCA Civ 577

Summary

Delay in performing an ongoing contractual obligation is repudiatory only where, assessed when termination is purported, its actual and reasonably foreseeable effects deprive the innocent party of the contractual benefit in a manner that goes to the root of the contract. The inquiry requires attention to the benefit bargained for, loss, the adequacy of damages, and whether performance has resumed or is likely to resume. Where time is not of the essence, delay and its commercial uncertainty will ordinarily justify termination only when so prolonged that they frustrate the contract. A breach remedied before termination may cease to support a right to terminate. Renunciation also requires clear words or conduct objectively evincing an intention not to perform essential obligations.

Treatment over time

Cited in 12 later judgments between 2013 and 2026, including 1 in the Privy Council. Applied, followed or approved 10 times, most recently by the High Court in July 2026.

Most often cited for

  1. Repudiatory breach is assessed at termination, considering the intended benefit, breach effects and likely future performance10 judgments
  2. The substantial-benefit test measures breach against the benefit intended under the contract3 judgments

Factual background

The developer agreed to construct four mixed-use blocks and grant the investor four 999-year leases of their commercial units. The agreement contemplated handover in two pairs, with seven months between the target dates. Financial difficulties caused the developer to suspend work on two blocks, although it continued to state that it intended to complete the development.

The investor purported to terminate for repudiatory breach shortly after work on the suspended blocks had resumed, but without knowing of that resumption. The developer then purported to terminate when the investor did not pay a further deposit. Roth J held that the developer's delay was repudiatory. The developer appealed.

The central issue was whether the accrued delay, and the developer's conduct concerning the works and affordable space, entitled the investor to accept a repudiation on the date of its purported termination.

Held

Appeal allowed unanimously. Lewison LJ gave the leading judgment. Tomlinson LJ gave concurring reasons and Longmore LJ agreed with both judgments.

  1. The judge had not given sufficient weight to the principal contractual benefit: four 999-year leasehold interests. A possible increase from seven to thirteen months in the interval between the two staged handovers did not, without findings of material financial consequences, deprive the investor of a substantial part, let alone substantially the whole, of that benefit.
  2. The governing inquiry, derived from Hongkong Fir Shipping Co Ltd v Kawasaki Kisen Kaisha Ltd [1962] 2 QB 26, was the effect of the breach at the date on which termination was purported. It required consideration of accrued loss, foreseeable future loss, the adequacy of damages, the prospect of resumed performance, and the value of the remaining performance.
  3. The delay had caused no actual loss. Any foreseeable additional funding costs were modest and readily compensable. The developer had resumed work before the investor's purported termination, had obtained funding, and remained committed to completing all four blocks. The prior stoppage was therefore no longer indeterminate. Its actual and foreseeable consequences did not frustrate the agreement or amount to a repudiatory breach.
  4. The judge had wrongly treated the position at an earlier point in time as decisive. The principles applied equally to actual and anticipatory breaches. A breach whose repudiatory character depends upon uncertainty may cease to be repudiatory once that uncertainty is removed before acceptance: compare The Hermosa [1982] 1 Lloyd’s Rep 570 and Stocznia Gdanska SA v Latvian Shipping Company [2002] EWCA Civ 889.
  5. The alternative case of renunciation failed. The developer repeatedly asserted an intention to perform and did perform. Its unimplemented communication to the local authority about marketing and affordable space was too slender a basis for the clear conclusion of refusal required by Woodar Investment Development Ltd v Wimpey Construction UK Ltd [1980] 1 WLR 277.

The investor's purported termination was ineffective. The appeal was allowed.

The court’s approach to earlier authorities

Available to signed-in members.

Appellate history

  • Court of Appeal (Civil Division): By [2013] EWCA Civ 577 , the court allowed the developer's appeal and reversed the finding that its delay amounted to a repudiatory breach.
  • High Court, Chancery Division: Roth J held that the developer's delay in carrying out works to two blocks was repudiatory and granted permission to appeal.

Appeal route

  1. Appealed fromNot stated in the judgmentThis appealappeal allowed (unanimous)
  2. This judgment · 23 May 2013 [2013] EWCA Civ 577 Court of Appeal (Civil Division)

Other judgments in these proceedings

2 judgments in these proceedings, earliest first. Linked by the shared court number HC10C04600, and by appeals.

  1. 4 July 2012Ampurius NU Homes Holdings Ltd v Telford Homes (Creekside) Ltd[2012] EWHC 1820 (Ch) · High Court (Chancery Division)
  2. 23 May 2013Telford Homes (Creekside) Ltd v Ampurius Nu Homes Holdings Ltd[2013] EWCA Civ 577 · Court of Appeal (Civil Division) · this judgment

Cases on related points

Of these 8 cases: 2 cited with it on 2 different points; 1 cited alongside it for another point; 5 related in other ways.

Cited together forRepudiatory breach is assessed at termination, considering the intended benefit, breach effects and likely future performance

  1. Hongkong Fir Shipping Co Ltd v Kawasaki Kisen Kaisha Ltd (The Hongkong Fir)[1962] 2 QB 26 · Court of AppealCited together in 6 later judgments

Cited together forThe substantial-benefit test measures breach against the benefit intended under the contract

  1. Valilas v Januzaj[2014] EWCA Civ 436 · Court of Appeal (Civil Division)Cited together in 3 later judgments

Cited alongside it for other points

  1. Stocznia Gdynia SA v Gearbulk Holdings Ltd[2009] EWCA Civ 75 · Court of Appeal (Civil Division)Corresponding contractual and common-law termination rights require no election if discharge is clearly communicatedCited together in 3 later judgments

Other related cases

5 related cases for signed-in readers

Key cases cited

10 authorities cited.

Sign in to see how the court treated each authority. A free account is enough.

Cases citing this case

12 later cases · 10 positive · 2 caution

Most senior citing decisions:

Sign in for the full treatment table, including the other 2 cases. A free account is enough.