Summary
Transitional provisions for procurement remedies apply according to their clear terms. A contract-award procedure begun before the stated date remained governed by the unamended regime, and the Public Contracts Regulations 2006 did not provide an automatic suspension.
An interim injunction is governed by the American Cyanamid approach. Difficulty in assessing loss-of-chance damages, particularly where an alleged failure in competitive dialogue must be reconstructed through numerous exchanges and hypothetical bids, may make damages inadequate. The court must then weigh the least risk of injustice. In procurement, effective pre-contract review and the public interest in lawful tendering are relevant to the balance of convenience, although neither creates a presumption for an injunction.
Factual background
MWDA conducted a lengthy competitive-dialogue procurement for a resource recovery contract valued at more than £1 billion. Covanta, an unsuccessful tenderer, alleged manifest errors in the evaluation of its tender and failures in the competitive dialogue process. It sought to prevent MWDA from contracting with the successful tenderer, SITA, pending trial.
The application raised two issues. First, whether the automatic suspension introduced by the 2009 amendments to the Public Contracts Regulations 2006 applied to a procurement procedure commenced before 20 December 2009. Secondly, if it did not, whether an interim injunction should be granted under the American Cyanamid principles.
Held
The application for an interim injunction was granted, subject to Covanta providing a parental guarantee for its cross-undertaking in damages. The automatic suspension was unavailable.
Paragraph 11 of the Public Contracts (Amendment) Regulations 2009 was clear: the amendments did not affect a contract-award procedure commenced before 20 December 2009. Legal certainty required the procurement and its aftermath to be governed by the rules in force when the procedure began. The New Remedies Directive did not expressly require the automatic-suspension remedy to apply retrospectively, and the earlier regime was not thereby deficient. The court declined to disapply the transitional provision.
Applying American Cyanamid Co v Ethicon Ltd [1975] AC 396, there was a serious issue to be tried. There was no presumption either for an injunction because European procurement law values pre-contract review, or against one merely because damages could be estimated. The question was whether it was just to confine the claimant to damages.
Damages would not adequately compensate Covanta. The alleged scoring errors, and especially the alleged failures in competitive dialogue, required analysis of numerous exchanges, their effect on both bids, and a hypothetical tender never submitted. The resulting loss-of-chance assessment would be highly speculative. MWDA's financial loss from delay was quantifiable and secured, although environmental harm from continued landfill could not be compensated by damages.
The balance of convenience favoured restraint. Lawful procurement, effective review before contract, and avoidance of potentially substantial damages ultimately borne by taxpayers outweighed the countervailing factors. A nine-month delay was modest against a six-year procurement and a 30–35 year contract. Its environmental effect, though material, did not alter that conclusion. Granting the injunction involved the least risk of injustice.
The court’s approach to earlier authorities
Available to signed-in members.
Appellate history
not stated in the judgment.
Key cases cited
16 authorities cited.
- R v Secretary of State for Transport, Ex p Factortame Ltd (No 2) [1991] 1 AC 603
- American Cyanamid Co v Ethicon Ltd [1975] AC 396
- Araci v Fallon [2011] EWCA Civ 668
- Lettings International Ltd v London Borough of Newham [2007] EWCA Civ 1522
- Metropolitan Resources Northwest Ltd v Home Secretary [2011] EWHC 1186 (Ch)
- Exel Europe Ltd. v University Hospitals Coventry & Anor [2010] EWHC 3332 (TCC)
- Indigo Services (UK) Ltd v The Colchester Institute Corporation [2010] EWHC 3237 (QB)
- Alstom Transport v Eurostar International Ltd & Anor [2010] EWHC 2747 (Ch)
- Morrison Facilities Services Limited v Norwich City Council [2010] EWHC 487 (Ch)
- European Dynamics SA v HM Treasury [2009] EWHC 3419 (TCC)
- Letting International Ltd v London Borough of Newham [2008] EWHC 1583 (QB)
- Lämmerzahl v Freie Hansestadt Bremen [2007] ECR 1-8415
- Alcatel Austria AG Case C-81/98
- Nottingham Building Society v Eurodynamics Systems [1993] FSR 468
- Fellowes and Son v Fisher [1976] 1 QB 122 CA
- Evans Marshall & Co Ltd v Bertola SA [1973] 1 WLR 349
Sign in to see how the court treated each authority. A free account is enough.
Cases citing this case
20 later cases · 10 positive · 3 neutral · 6 caution · 1 negative
Most senior citing decisions:
- Parkingeye Limited v Velindre University NHS Trust & Anor [2026] EWHC 1019 (TCC) explained
- International SOS Assistance UK Limited v Secretary of State for Defence [2025] EWHC 2634 (TCC) applied
- Unipart Group Limited & Anor v Supply Chain Coordination Limited [2025] EWHC 354 (TCC) explained
- Medequip Assistive Technology Limited v The Mayor and Burgesses of the Royal Borough of Kensington and Chelsea & Ors [2022] EWHC 3293 (TCC)
- Practice Plus Group Health and Rehabilitation Services Limited v NHS Commissioning Board [2022] EWHC 2082 (TCC)
- Kellogg Brown & Root Ltd v Mayor's Office for Policing and Crime [2021] EWHC 3321 (TCC)
- Neology UK Ltd v The Council of the City of Newcastle Upon Tyne & Ors [2020] EWHC 2958 (TCC)
- Circle Nottingham Ltd v NHS Rushcliffe Clinical Commissioning Group [2019] EWHC 1315 (TCC)
- Lancashire Care NHS Foundation Trust & Anor v Lancashire County Council [2018] EWHC 200 (TCC)
- Sysmex (UK) Ltd v Imperial College Healthcare NHS Trust [2017] EWHC 1824 (TCC)
Sign in for the full treatment table, including the other 10 cases. A free account is enough.