Nuclear Decommissioning Authority v EnergySolutions EU Ltd

[2017] UKSC 34

Summary

Under EU public procurement law, damages against a contracting authority are required only where the three Francovich conditions are satisfied. The breach must therefore be sufficiently serious, although domestic law may create wider liability.

The Public Contracts Regulations 2006, as amended in 2009, did not create wider liability. Damages under regulation 47J(2)(c) require satisfaction of the Francovich conditions, despite the domestic characterisation of the claim as breach of statutory duty.

An unsuccessful tenderer which begins proceedings within the prescribed 30 days does not fail to mitigate merely by awaiting execution of the contract. It may choose to pursue damages without seeking or maintaining a pre-contract suspension.

Treatment over time

Cited in 26 later judgments between 2017 and 2026, including 1 in the Supreme Court. Applied, followed or approved 18 times, most recently by the High Court in August 2026. 1 negative treatment, by the High Court in 2017.

Most often cited for

  1. Procurement damages require a sufficiently serious breach under the Francovich conditions18 judgments
  2. Domestic implementation is presumed not to exceed EU requirements absent clear contrary intention3 judgments

Factual background

Nuclear Decommissioning Authority v EnergySolutions EU Ltd concerned the award of a major nuclear decommissioning contract. EnergySolutions, subsequently called ATK Energy EU Ltd, belonged to an unsuccessful consortium. For this appeal it was assumed, consistently with Fraser J's later findings in [2016] EWHC 1988 (TCC), that the authority had committed manifest evaluation errors and should have awarded the contract to that consortium.

ATK issued proceedings within the 30-day period prescribed by the Public Contracts Regulations 2006, but only after the authority had entered into the contract with its competitor. Preliminary issues were decided in the High Court, [2015] PTSR 1106, and on appeal by the Court of Appeal, [2015] EWCA Civ 1262; [2016] PTSR 689. The parties subsequently compromised the damages claim but asked the Supreme Court to give judgment.

The issues were whether EU law required damages only for a sufficiently serious breach; whether the domestic Regulations imposed liability for less serious breaches; and whether damages could be denied because ATK had not begun proceedings before the contract was executed.

Held

  1. Disposition. The authority's appeal was allowed on the domestic-law issue and dismissed on the mitigation issue. The Court of Appeal's conclusion on the EU-law issue was affirmed. Lord Mance gave the judgment, with which Lord Neuberger, Lady Hale, Lord Sumption and Lord Carnwath agreed.

  2. The Remedies Directive requires a damages remedy against a contracting authority only where the three Francovich conditions are satisfied: the infringed rule must confer rights on individuals, the breach must be sufficiently serious, and the breach must directly cause the loss. The judgment in Combinatie Spijker Infrabouw-De Jonge Konstruktie v Provincie Drenthe [2010] ECR I-12655 clearly applied those conditions to an awarding authority. Stadt Graz v Strabag AG [2010] ECR I-8769 was consistent with that conclusion: a fixed requirement of fault is impermissible, although fault-related matters may inform whether a breach was sufficiently serious. The position was acte clair and required no reference to the Court of Justice.

  3. The Public Contracts Regulations 2006, as amended in 2009, should be read as providing damages only when the Francovich conditions are met. EU law did not compel that construction because those conditions prescribed only minimum protection. Nevertheless, the implementation materials showed that the legislator intended a minimalist transposition without relevant gold-plating. The word “may” in regulations 47I(2) and 47J(2)(c) was consistent with conditional liability. Characterising the claim in domestic law as breach of statutory duty did not remove the conditions governing the underlying EU liability. The contrary reasoning in Matra Communications SAS v Home Office [1999] 1 WLR 1646 was wrong.

  4. Domestic law may in principle treat reasonable use of available legal remedies as an aspect of mitigation. The procurement breach occurred when the wrongful award decision was made; execution of the contract was its consequence. Nevertheless, an economic operator was entitled to await execution and claim damages. It was not obliged to obtain a suspension, offer a cross-undertaking or provide security for the contracting authority's benefit. The authority could protect itself by postponing execution until the 30-day claim period expired. ATK therefore could not be held to have acted unreasonably merely by failing to prevent the authority from implementing its own wrongful award decision.

The court’s approach to earlier authorities

Available to signed-in members.

Appellate history

  • United Kingdom Supreme Court: In Nuclear Decommissioning Authority v EnergySolutions EU Ltd [2017] UKSC 34 , the appeal was allowed on the construction of the domestic damages provisions and dismissed on mitigation. The Court of Appeal's EU-law conclusion was affirmed.
  • Court of Appeal: [2015] EWCA Civ 1262 ; [2016] PTSR 689 . The court held that EU law required a sufficiently serious breach, but that the Public Contracts Regulations 2006 allowed damages for any breach. It rejected the proposed mitigation defence.
  • High Court: The preliminary issues were determined by Edwards-Stuart J in [2015] PTSR 1106 . He treated damages as available without a sufficiently serious breach and regarded mitigation as fact-sensitive, while expressing views discouraging the proposed defence.

Appeal route

  1. Appealed from · 15 December 2015Energysolutions EU Ltd v Nuclear Decommissioning Authority[2015] EWCA Civ 1262 Court of Appeal (Civil Division)Partly reversedAppeal allowed in part (unanimous)
  2. This judgment · 11 April 2017 [2017] UKSC 34 United Kingdom Supreme Court

Other judgments in these proceedings

5 judgments in these proceedings, earliest first. Linked by appeals and by the court numbers the judgments share.

  1. 23 January 2014Energy Solutions Eu Ltd v Nuclear Decommissioning Authority[2015] EWHC 73 (TCC) · High Court (Technology and Construction Court)
  2. 15 December 2015Energysolutions EU Ltd v Nuclear Decommissioning Authority[2015] EWCA Civ 1262 · Court of Appeal (Civil Division)
  3. 29 July 2016Energysolutions EU Ltd v Nuclear Decommissioning Authority[2016] EWHC 1988 (TCC) · High Court (Technology and Construction Court)
  4. 20 December 2016Energy Solutions EU Ltd v Nuclear Decommissioning Authority[2016] EWHC 3326 (TCC) · High Court (Technology and Construction Court)
  5. 11 April 2017Nuclear Decommissioning Authority v EnergySolutions EU Ltd[2017] UKSC 34 · Supreme Court · this judgment

Often cited alongside this case

Of these 8 cases: 2 cited with it on the same point; 4 cited alongside it for other points; 2 related in other ways.

Cited together forProcurement damages require a sufficiently serious breach under the Francovich conditions

  1. Ocean Outdoor UK Ltd v The London Borough of Hammersmith & Fulham[2019] EWCA Civ 1642 · Court of Appeal (Civil Division)Cited together in 3 later judgments
  2. Phonographic Performance Ltd v Department of Trade and Industry & Anor[2004] EWHC 1795 (Ch) · High Court (Chancery Division)Cited together in 5 later judgments

Cited alongside it for other points

  1. R v Secretary of State for Transport, Ex p Factortame Ltd (No 5)[2000] 1 AC 524 · House of LordsSufficient seriousness is assessed on all circumstances without any single factor being decisiveCited together in 6 later judgments

+3 more for signed-in readers

Other related cases

2 related cases for signed-in readers

Key cases cited

12 authorities cited.

Sign in to see how the court treated each authority. A free account is enough.

Cases citing this case

26 later cases · 18 positive · 4 neutral · 3 caution · 1 negative

Most senior citing decisions:

Sign in for the full treatment table, including the other 16 cases. A free account is enough.