Loughton Contracts Plc v The Amtico Company Limited

[2026] EWHC 2814 (TCC)

Summary

On an application for summary judgment, the court assesses whether a claim has a real prospect of success without conducting a mini-trial. It takes account of evidence reasonably expected at trial, but a party must identify a substantive basis for expecting that evidence.

Terms supplied after a contract is made may become incorporated into later contracts through a sufficiently regular and consistent course of dealing. Whether that has occurred may require investigation of the documents supplied and their consistency. The reasonableness of standard-term exclusions and limitations is fact-sensitive; the party relying on them bears the statutory burden of proof.

When deciding whether to grant relief from sanctions for late particulars of claim, the court considers the seriousness of the breach, its reasons and all the circumstances. A subsequent stay does not cure an earlier default, but may affect its practical significance and the proportionality of strike-out.

Factual background

Loughton Contracts Plc supplied and installed flooring at residential developments for the main contractor, McLaren Construction (Regeneration) Limited. The Amtico Company Limited supplied the flooring products to Loughton. The flooring failed, and McLaren asserted that Loughton was responsible for replacement costs of about £2.9 million. McLaren had not commenced proceedings.

Loughton issued protective proceedings against Amtico but failed to serve particulars of claim by the applicable deadline. The court subsequently stayed the proceedings. Loughton applied to extend the stay, while Amtico sought summary judgment or strike-out on substantive and procedural grounds. The applications raised issues concerning limitation, the incorporation and enforceability of contractual terms, the unparticularised tort and contribution claims, relief from sanctions and the future management of the proceedings.

Held

Held, dismissing Amtico’s applications for summary judgment and strike-out, and granting Loughton relief from sanctions and an extension of time for service of particulars of claim:

  1. The summary judgment test required a realistic prospect of success and an assessment of evidence reasonably expected at trial, without a mini-trial. Amtico’s records showed scheduled delivery dates rather than actual delivery dates. Underlying documents could materially alter the evidence, and Amtico had not established the extent of its statutory limitation defence to the required standard. The unparticularised tort and contribution claims might face substantial difficulties, but it was premature to decide their viability before the material facts were pleaded (paras [8]–[16]).
  2. Terms supplied after an individual contract is made do not ordinarily become terms of that contract merely because they appear on a later invoice. They may be incorporated into later contracts by a sufficiently regular and consistent course of dealing. Here, inconsistencies in the evidence concerning the invoice terms and the absence of documents identified by those terms left a real prospect that disclosure and trial evidence would materially clarify the contractual position (paras [21]–[27]).
  3. Even assuming incorporation, none of the contractual defences justified summary judgment. The meaning of the exclusion of third-party claims and the operation of the liability cap remained unresolved. The court also left open the construction and application of the knowledge-based contractual time limit. The exclusion and limitation clauses were subject to the reasonableness requirements of the Unfair Contract Terms Act 1977. Amtico bore the burden of establishing reasonableness and had provided no evidence directed to it. The fact-sensitive issue could not be decided against Loughton on that basis (paras [27]–[36]).
  4. The claim form identified the product, its alleged failure and the causes of action. The limitation and contractual matters relied on as defences depended on facts outside the claim form. Strike-out for disclosing no reasonable grounds was therefore inappropriate (para [38]).
  5. Applying Denton v TH White Ltd [2014] EWCA Civ 906, the failure to serve particulars or seek an extension in time was serious and significant, and the explanation was not a good reason. The later stay did not cure the default, but materially affected its practical significance. Unlike the relevant proceedings in North Midland Construction plc v Geo Networks Ltd [2015] EWHC 2384, most of the period had been covered by a stay and no trial date was jeopardised. Strike-out could also prevent claims that had been in time when issued from being brought again. In all the circumstances, strike-out would be disproportionate (paras [50]–[61]).

The court refused the proposed six-month extension of the stay. It would hear the parties on whether a short, defined stay and directions for pleadings, targeted disclosure, evidence and possible preliminary issues were appropriate (paras [64]–[66]).

The court’s approach to earlier authorities

Available to signed-in members.

Appellate history

High Court: The claim was issued protectively. A stay was granted on 5 February 2026 until 5 October 2026, with liberty to apply to vary or set it aside. The court subsequently dismissed applications for summary judgment and strike-out, granted relief from sanctions and refused the proposed six-month extension of the stay.